Case Information
*1 United States Court of Appeals
FOR THE DISTRICT OF COLUMBIA CIRCUIT
Argued May 5, 2014 Decided July 15, 2014
No. 13-5315 R ALLS C ORPORATION , A PPELLANT v.
C OMMITTEE ON F OREIGN I NVESTMENT I N THE U NITED S TATES ,
ET AL ., A PPELLEES Aрpeal from the United States District Court for the District of Columbia (No. 1:12-cv-01513) Paul D. Clement argued the cause for the appellant. Viet D. Dinh , H. Christopher Bartolomucci and George W. Hicks , Jr. , were on brief.
Douglas N. Letter , Attorney, United States Department of Justice, argued the cause for the appellees. Stuart F. Delery , Assistant Attorney General, Ronald C. Machen , Jr. , United States Attorney, and Sonia K. McNeil , Attorney, were on brief.
Before: H ENDERSON , B ROWN and W ILKINS , Circuit Judges .
Opinion for the Court filed by Circuit Judge H ENDERSON .
K AREN L E C RAFT H ENDERSON , Circuit Judge : In March 2012, Appellant Ralls Corporation (Ralls) purchased four American limited liability companies (Project Companies) previously formed to develop windfarms in north-central Oregon. The transaction quickly came under scrutiny from the Committee on Foreign Investment in the United States (CFIUS), an Executive Branch committee created by the Defense Production Act of 1950 (DPA), codified as amended at 50 U.S.C. app. § 2170, and chaired by the Secretary of the U.S. Treasury Department (Treasury Secretary), see 50 U.S.C. app. § 2170(k). Pursuant to section 721 of the DPA, CFIUS reviews any transaction “which could result in foreign control of any person engaged in interstate commerce in the United States.” Id. § 2170(a)(3). Although Ralls is an American corporation, the transaction fell within the ambit of the DPA because both of Ralls’s owners are Chinese nationals. CFIUS determined that Ralls’s acquisition of the Project Companies threatened national security and issued temporary mitigation orders restricting Ralls’s access to, and preventing further construction at, the Project Companies’ windfarm sites. The matter was then submitted to the President, who also concluded that the transaction posed a threat to national security. He issued a permanent order (Presidential Order) that prohibited the transaction and required Ralls to divest itself of the Project Companies. Ralls challenged the final order issued by CFIUS (CFIUS Order) and the Presidential Ordеr in district court, alleging, inter alia , that the orders violate the Due Process Clause of the Fifth Amendment to the United States Constitution because neither CFIUS nor the President (collectively, with Treasury Secretary and CFIUS Chairman Jacob Lew, Appellees) provided Ralls the opportunity to review and rebut the evidence upon which they relied. The district court dismissed Ralls’s CFIUS Order claims as moot and its due process challenge to the Presidential Order for failure to state a claim. For the reasons set forth below, we reverse.
I. BACKGROUND
A. S TATUTORY AND R EGULATORY F RAMEWORK This case involves Executive Branch review of a business transaction under section 721 of the DPA, also known as the “Exon-Florio Amendment.” [1] As amended, section 721 of the DPA directs “the President, acting through [CFIUS],” to review a “covered transaction to determine the effects of the transaction on the national security of the United States.” 50 U.S.C. app. § 2170(b)(1)(A). Section 721 defines a covered transaction as “any merger, acquisition, or takeover . . . , by or with any foreign person which could result in foreign control of any person engaged in interstate commerce in the United States.” Id. § 2170(a)(3).
Review of covered transactions under section 721 begins with CFIUS. As noted, CFIUS is chaired by the Treasury Secretary and its members include the heads of various federal agencies and other high-ranking Government officials with foreign policy, national security and economic responsibilities. [2] See id. § 2170(k)(2), (3). CFIUS review is initiated in one of two ways. First, any party to a covered transaction may initiate review, either before or after the transaction is completed, by submitting a written notice to the CFIUS chairman. See id. § 2170(b)(1)(C)(i); 31 C.F.R. § 800.401(a) (“A party or parties to a proposed or completed transaction may file a voluntary notice of the transaction with the Committee.” (emphases added)); id. § 800.402(c)(1)(vii) (voluntary notice must include “expected date for completion of the transaction, or the date it was completed”); id. § 800.224 (“The term transaction means a proposed or completed merger, acquisition, or takeover.”). [3] Alternatively, CFIUS may initiate review sua sponte . See 50 U.S.C. app. § 2170(b)(1)(D). The CFIUS review period lasts thirty days, during which CFIUS considers the eleven factors set forth in 50 U.S.C. app. § 2170(f) to assess the transaction’s effect on national security. [4] See id. § 2170(b)(1)(A)(ii), (E). officials, among others, to participate as observers. See Exec. Order No. 13,456, § 3(b), (c), 73 Fed. Reg. 4677, 4677 (2008).
[3] The DPA directs the President to “direct . . . the issuance of
regulations to carry out this section.” 50 U.S.C. app. § 2170(h)(1),
which duty the President delegated to the Treasury Secretary. Exec.
Order 13,456, § 4.1(b),
for projected national defense requirements, (2) the capability and capacity of domestic industries to meet national defense requirements, including the availability of human resources, products, technology, materials, and other supplies and services, (3) the control of domestic industries and commercial activity by foreign citizens as it affects the capability and capacity of the United States to meet the requirements of national security, (4) the potential effects of the proposed or pending transaction on sales of military goods, equipment, or technology to [certain] countr[ies] . . . (5) the potential effects of the proposed or pending transaction on United States international technological leadership in areas affecting United During its review, if CFIUS determines that “the transaction threatens to impair the national security of the United States and that threat has not been mitigated,” it must “immediately conduct an investigation of the effects of [the] covered transaction on the national security . . . and take any necessary actions in connection with the transaction to protect the national security.” Id. § 2170(b)(2)(A), (B). CFIUS is given express authority to “negotiate, enter into or impose, and enforce any agreement or condition with any party to the covered transaction in order to mitigate any threat to the national security of the United States that arises as a result of the covered transaction.” Id. § 2170( l )(1)(A). The investigation period lasts no more than forty-five days. See id. § 2170(b)(2)(C). If CFIUS determines at the end of an investigation that the national security effects of the transaction have been mitigated and that the transaction need not be prohibited, action under section 721 terminates and CFIUS submits a final investigation report to the Congress. See id. § 2170(b)(3)(B); 31 C.F.R. § 800.506(d).
States national security; (6) the potential national security-related effects on United States critical infrastructure, including major energy assets; (7) the potential national security-related effects on United States critical technologies; (8) whether the covered transaction is a foreign government-controlled transaction, as determined under subsection (b)(1)(B) of this section; (9) as appropriate, and particularly with respect to transactions requiring an investigation under subsection (b)(1)(B) of this section, a review of the current assessment of [the foreign country’s relationship and cooperation with the United States]; (10) the long-term projection of United States requirements for sources of energy and other critical resources and material; and (11) such other factors as the President or [CFIUS] may determine to be appropriate, generally or in connection with a specific review or investigation.” 50 U.S.C. app. § 2170(f).
If CFIUS concludes at the end of its investigation that a covered transaction should be suspended or prohibited, it must “send a report to the President requesting the President’s decision,” which report includes, inter alia , information regarding the transaction’s effect on national security and CFIUS’s recommendation. 31 C.F.R. § 800.506(b), (c). Once CFIUS’s report is submitted to the President, he has fifteen days to “take such action for such time as the President considers appropriate to suspend or prohibit any covered transaction that threatens to impair the national security of the United States.” 50 U.S.C. app. § 2170(d)(1), (2). The President may exercise his authority under section 721 only if he finds that
there is credible evidence that leads [him] to believe that the foreign interest exercising control might take action that threatens to impair the national security; and . . . provisions of law, other than [section 721] and the International Emergency Economic Powers Act, do not, in the judgment of the President, provide adequate and appropriate authority for the President to protect the national security in the matter before the President.
Id. § 2170(d)(4). Significantly, the statute provides that “[t]he actions of the President under paragraph (1) of subsection (d) of this section and the findings of the President under paragraph (4) of subsection (d) of this section shall not be subject to judicial review.” Id. § 2170(e). In deciding whether to suspend or prohibit a transaction, the President is directed to consider, “among other factors[,] each of the factors described in subsection (f) of this section, as appropriate.” Id. § 2170(d)(5); see supra note 4.
B. F ACTUAL B ACKGROUND
Ralls is an American company incorporated in Delaware with its principal place of business in Georgia. Ralls is owned by two Chinese nationals, Dawei Duan and Jialiang Wu. Duan is the chief financial officer of Sany Group (Sany), a Chinese manufacturing company, and, at the time of the transaction at issue, Wu was a Sany vice-president and the general manager of Sany Electric Company, Ltd. (Sany Electric). Ralls’s amended complaint asserts that “Ralls is in the business of identifying U.S. opportunities for the construction of windfarms in which the wind turbines of Sany Electric, its affiliate, can be used and their quality and reliability demonstrated to the U.S. wind industry in comparison to competitor products.” Am. Compl. ¶ 5, Ralls Corp. v. Comm. on Foreign Inv. in the U.S. , No. 1:12-cv-01513 (D.D.C. Oct. 1, 2012).
In March 2012, Ralls purchased the Project Companies, which are four American-owned, limited liability companies: Pine City Windfarm, LLC; Mule Hollow Windfarm, LLC; High Plateau Windfarm, LLC; and Lower Ridge Windfarm, LLC. [5] The Project Companies were originally created by an Oregon entity (Oregon Windfarms, LLC) owned by American citizens to develop four windfarms in north-centrаl Oregon (collectively, Butter Creek projects). Before Ralls acquired them, each of the Project Companies had acquired assets necessary for windfarm development, including
easements with local landowners to access their property and construct windfarm turbines; power purchase agreements with the local utility, PacifiCorp; generator interconnection agreements permitting connection to PacifiCorp’s grid; transmission interconnection agreements and agreements for the management and use of shared facilities with other nearby windfarms; and necessary government permits and approvals to construct five windfarm turbines at specific, approved locations.
Am. Compl. ¶ 37.
The Butter Creek project sites are located in and around the eastern region of a restricted airspace and bombing zone maintained by the United States Navy (Navy). Three of the windfarm sites are located within seven miles of the restricted airspace while the fourth––Lower Ridge––is located within the restricted airspace. After the Navy urged Ralls to move the Lower Ridge site “to reduce airspace conflicts between the Lower Ridge wind turbines and low-level military aircraft training,” Am. Compl. ¶ 63 (quotation marks omitted), Ralls relocated the windfarm but it remains within the restricted airspace.
Ralls’s complaint alleges that Oregon Windfarms, LLC, has developed nine other windfarm projects (Echo Projects) in the same general vicinity as the Butter Creek projects and that all nine use foreign-made wind turbines. According to Ralls, seven turbines used by the Echo Projects are located within the restricted airspace and one of the nine Echo Projects––Pacific Canyon––is currently owned by foreign investors. In addition, Ralls claims that there are “dozens if not hundreds of existing turbines in or near the western region of the restricted airspace” that “are foreign-made and foreign-owned.” Am. Compl. ¶ 57. The Appellees conceded at oral argument that there are other foreign-owned wind turbines near the restricted airspace. See Recording of Oral Argument at 32:43. On June 28, 2012, [6] Ralls submitted a twenty-five-page notice to CFIUS informing it of Ralls’s March acquisition of the Project Companies. [7] The notice explained why Ralls believed the transaction did not pose a national security threat. CFIUS initiated its review pursuant to 50 U.S.C. app. § 2170(b)(1). During the thirty-day review period, Ralls responded to several questions posed by CFIUS and gave a presentation to CFIUS officials. Ralls contends that CFIUS did not apprise Ralls of the gravamen of its concern with the transaction and did not, during the presentation or at any other time, disclose to Ralls the information it reviewed.
CFIUS determined that Ralls’s acquisition of the Project Companies posed a national security threat and on July 25 it issued an Order Establishing Interim Mitigation Measures (July Order) to mitigate the threat. The July Order required Ralls to (1) cease all construction and operations at the Butter Creek project sites, (2) “remove all stockpiled or stored items from the [project sites] no later than July 30, 2012, and shall not deposit, stockpile, or store any new items at the [project sites]” and (3) cease all access to the project sites. Joint Appendix (JA) 82-83, Ralls v. Comm. on Foreign Inv. in the U.S. , No. 13-5315 (D.C. Cir. Feb. 7, 2014). Five days later, July 30, CFIUS launched an investigation under 50 U.S.C. app. § 2170(b)(2).
Three days into its investigation, August 2, CFIUS issued an Amended Order Establishing Interim Mitigation Measures (CFIUS Order). In addition to the July Order restrictions, the CFIUS Order prohibited Ralls from completing any sale of the Project Companies or their assets without first removing all items (including concrete foundations) from the Butter Creek project sites, notifying CFIUS of the sale and giving CFIUS ten business days to object to the sale. The CFIUS Order remained in effect “until CFIUS concludes action or the President takes action under section 721” or until express “revocation by CFIUS or the President.” JA 88. Neither the July Order nor the CFIUS Order disclosed the nature of the national security threat the transaction posed or the evidence on which CFIUS relied in issuing the orders. On September 13, the investigation period ended and CFIUS submitted its report (including its recommendation) [8] to the President, requesting his decision.
On September 28, the President issued an “Order Regarding the Acquisition of Four U.S. Wind Farm Project Companies by Ralls Corporation” (Presidential Order). The Presidential Order stated that “[t]here is credible evidence that leads [the President] to believe that Ralls . . . might take action that threatens to impair the national security of the United States” and that “[p]rovisions of law, other than section 721 and the International Emergency Economic Powers Act . . . do not, in [the President’s] judgment, provide adequate and appropriate authority for [the President] to protect the national security in this matter.” JA 89. In light of the findings, the Presidential Order directed thаt the transaction be prohibited. “In order to effectuate” the prohibition, the Presidential Order required Ralls to, inter alia , (1) divest itself of all interests in the Project Companies, their assets and their operations within ninety days of the Order, (2) remove all items from the project sites “stockpiled, stored, deposited, installed, or affixed thereon,” (3) cease access to the project sites, (4) refrain from selling, transferring or facilitating the sale or transfer of “any items made or otherwise produced by the Sany Group to any third party for use or installation at the [project sites]” and (5) adhere to restrictions on the sale of the Project Companies and their assets to third parties. JA 89-91. The Presidential Order also “revoked” both orders issued by CFIUS. JA 91.
It is undisputed that neither CFIUS nor the President gave Ralls notice of the evidence on which they respectively relied nor an opportunity to rebut that evidence. See infra note 19.
C. D ISTRICT C OURT P ROCEEDINGS
Approximately two weeks before the Presidential Order issued, Ralls filed suit against CFIUS and its then-chairman, Treasury Secretary Timothy Geithner, in district court. Ralls sought to invalidate the CFIUS Order and to enjoin its enforcement, claiming that CFIUS exceeded its statutory authority and acted arbitrarily and capriciously in issuing the Order in violation of the Administrative Procedure Act (APA), 5 U.S.C. §§ 551 et seq. , and that the Order deprived Ralls of its constitutionally protected property interests in violation of the Due Process Clause of the Fifth Amendment to the United States Constitution. The next day, September 13, Ralls moved for a temporary restraining order and preliminary injunction (TRO/PI). The hearing on the TRO/PI motion was set for Sеptember 20 but Ralls voluntarily withdrew the motion the day before the hearing.
After the President issued the Presidential Order on September 28, Ralls amended its complaint to add claims challenging the Presidential Order and naming the President as a defendant. The amended complaint included five counts: Counts I and II challenged the CFIUS Order under the APA; Count III attacked the actions of the Appellees as ultra vires ; Counts IV and V challenged the constitutionality of both orders, under the Fifth Amendment Due Process Clause (Count IV) and the Equal Protection Clause (Count V).
CFIUS and the President moved to dismiss Ralls’s complaint for lack of subject-matter jurisdiction, which motion the district court granted in part and denied in part in February 2013. The court first concluded that section 721 barred judicial review of Ralls’s ultra vires and equal protection challenges to the Presidential Order but not Ralls’s due process challenge thereto. It also concluded that Ralls’s claims regarding the CFIUS Order were mooted by the Presidential Order. It therefore dismissed Counts I, II, III and V in their entirety and the portion of Count IV challenging the CFIUS Order.
Shortly thereafter, the Appellees moved to dismiss Ralls’s
due process claim attacking the Presidential Order for failure to
state a claim under Federal Rule of Civil Procedure 12(b)(6).
The district court eventually granted the motion in October
2013. In dismissing Ralls’s remaining due process claim, it
first determined that the Presidential Order did not deprive
Ralls of a constitutionally protected property interest.
Although the court acknowledged that Ralls had “entered into
a transaction in March 2012 through which it obtained certain
property rights undеr state law,”
Ralls Corp. v. Comm. on
Foreign Inv. in the United States
, --- F. Supp. 2d ----, No.
1:12-cv-01513,
Ralls timely appealed the district court’s Rule 12(b)(6) dismissal of its due process challenge to the Presidential Order and the Rule 12(b)(1) dismissal of its five CFIUS Order claims. [9] We first address the dismissal of Ralls’s due process claim against the Presidential Order (Count IV in part) and then turn to the dismissal of its CFIUS Order claims (Counts I and II in their entirety and Counts III, IV and V, in part).
II. DUE PROCESS CLAIM
Our first order of business is to satisfy ourselves that we
have jurisdiction to review the dismissal of Ralls’s due process
challenge to the Presidential Order.
See Bancoult v.
McNamara
,
A. S TATUTORY B AR TO J UDICIAL R EVIEW As noted, the DPA provides that
[t]he actions of the President under paragraph (1) of subsection (d) of this section and the findings of the President under paragraph (4) of subsection (d) of this section shall not be subject to judicial review.
50 U.S.C. app. § 2170(e). The “actions of the President” referred to are “such action[s] for such time as the President considers appropriate to suspend or prohibit any covered transaction that threatens to impair the national security of the United States.” Id. § 2170(d)(1). The President’s “findings” under subsection (d) of paragraph (4) include his determination that (1) there is “credible evidence that leads [him] to believe that the foreign interest exercising control might take action that threatens to impair the national security” and (2) other provisions of law do not give him adequate authority to protect the national security. Id. § 2170(d)(4).
The Supreme Court has long held that a statutory bar to
judicial review precludes review of constitutional claims only
if there is “clear and convincing” evidence that the Congress so
intended.
See, e.g.
,
Bowen v. Mich. Acad. of Family
Physicians
, 476 U.S. 667, 681 (1986);
Califano v. Sanders,
430 U.S. 99, 109 (1977);
Weinberger v. Salfi
, 422 U.S. 749,
762 (1975);
Johnson v. Robison
,
Beginning with
Ralpho
, we determined that a broadly
worded statutory bar did not preclude our consideration of a
procedural due process claim. By the Micronesian Claims
Act of 1971 (MCA), the Congress created the Micronesian
Claims Commission (Commission) to administer a five million
dollar fund to Micronesians injured during World War II.
Ralpho
, 569 F.2d at 613. The MCA provided that the
Commission’s settlement and disbursement actions “shall be
final and conclusive for all purposes, notwithstanding any
other provision of law to the contrary and not subject to
review.”
Id.
(quoting 50 U.S.C. app. § 2020 (1972)). A
claimant brought suit in district court alleging that “his right to
a fair hearing” under the Due Process Clause “was abridged by
the Commission’s reliance upon ‘secret’ extra-record
evidence.”
Id.
at 611. Relying on the statutory bar, the
district court dismissed the claim for lack of jurisdiction but we
follow them.
See United States v. Carson
,
reversed. We found no affirmative statement in the text of the
statute or the legislative history addressing judicial review of
constitutional claims and
a fortiori
no clear and convincing
evidence that the Congress intended to bar judicial review of
such claims.
Id.
at 621-22;
see also Griffith
,
We reached a similar result in
Ungar
. There, individuals
with interests in a Hungarian corporation filed claims with the
then-functioning Office of Alien Property (OAP) for the return
of property seized from them during World War II.
See
Ungar
,
We took a somewhat different approach to legislative history in McBryde v. Committee to Review Circuit Council Conduct and Disability Orders of Judicial Conference of U.S. , 264 F.3d 52 (D.C. Cir. 2001). In McBryde , a Texas federal district judge raised a procedural due process challenge to a decision of the Judicial Council of the Fifth Circuit––affirmed by the Committee to Review Circuit Council Conduct and Disability Orders of the Judicial Conference of the United States (Review Committee)––sаnctioning him for judicial misconduct. Id. at 54-55. In sanctioning McBryde, both the Judicial Council and the Review Committee acted under the authority of the Judicial Conduct and Disability Act of 1980, which contained a review provision mandating that “all orders and determinations” made by a committee of the Judicial Conference “shall be final and conclusive and shall not be judicially reviewable on appeal or otherwise.” Id. at 58 (quoting 28 U.S.C. § 372(c)(10) (2001)). In interpreting the preclusive effect of the review provision, we found the legislative history dispositive. Specifically, we determined that, by rejecting a Senate proposal to create a new Article III court to review judicial disciplinary proceedings, the Congress clearly expressed its intent to bar review of McBryde’s due process claim by a conventional Article III court. Id. at 62-63. Our conclusion hinged on the fact that a disciplined judge could obtain review of an as-applied constitutional claim by the Judicial Conference committee, which, like an Article III Court, was comprised of Article III judges. Id. at 63. To read the statute to also allow review of an as-applied constitutional claim by an Article III court, we concluded, “would generate substantial redundancy, an implausible legislative purpose.” Id. at 62.
constitutional question was “not enough . . . to support an inference of intent to preclude constitutional claims.” Id. Notwithstanding the high hurdle this precedent has erected, the Appellees argue that section 2170(e) bars our review of Ralls’s due process claim. According to the Appellees, the text of the provision––which precludes judicial review of “actions of the President under paragraph (1) of subsection (d),” 50 U.S.C. app. § 2170(e)––bars judicial review of all actions taken by the President under the statute, including “the President’s choice not to provide Ralls with more notice than it had already received, his decision not to confide in Ralls his national security concerns, and his judgment about the appropriate level of detail with which to publicly articulate his reasoning.” Br. for the Appellees 27, Ralls Corp. v. Comm. on Foreign Inv. in the U.S. , No. 13-5315 (D.C. Cir. Mar. 14, 2014).
Relying on McBryde , the Appellees also submit that we may infer from current and former congressional oversight provisions in the statute––and the portions of legislative history pertaining to them––that the Congress intended any review of the President’s actions under the DPA to occur in the halls of the Congress, not in the courtrooms of the judiciary. They first point to legislative history relating to a now-superseded provision of the DPA requiring the President to “immediately transmit” to the Congress “a written report of the President’s determination of whether or not to take action under subsection (d).” 50 U.S.C. app. § 2170(g) (1993). The legislative history indicates that this provision was intended to help the “Congress and the public develop an understanding of the policies underlying Presidential determinations, and hold the President accountable for actions under the Exon-Florio Amendment.” H.R. C ONF . R EP . 102-966, at 731-32 (1992). They also cite former section 2170(k), which required the President, “[i]n order to assist the Congress in its oversight responsibilities,” to furnish to the Congress a quadrennial report regarding foreign countries’ efforts to acquire U.S. companies involved in “criticаl technologies” or to “obtain[] commercial secrets related to critical technologies” therefrom. 50 U.S.C. app. § 2170(k) (1993). Under the current DPA, the President’s suspension or prohibition of a covered transaction, as well as the President’s critical technology assessment, are memorialized in a single annual report that is submitted to the Congress. See 50 U.S.C. app. § 2170(m). Finally, the Appellees direct our attention to the Foreign Investment and National Security Act of 2007 (FINSA), Pub. L. No. 110-49, 121 Stat. 246, which amended portions of section 721 of the DPA. According to a Senate report, the purpose of FINSA is “to strengthen Government review and oversight of foreign investment in the United States” and “to provide for enhanced Congressional oversight with respect thereto.” S. R EP . No. 109-264, at 1 (2006). FINSA purported to accomplish this objective by increasing oversight of CFIUS.
We conclude that neither the text of the statutory bar nor the legislative history of the statute provides clear and convincing evidence that the Congress intended to preclude judicial review of Ralls’s procedural due process challenge to the Presidential Order. First, the text does not preclude judicial review of Ralls’s as-applied constitutional claim by barring review of all “actions of the President under paragraph (1) of subsection (d).” 50 U.S.C. app. § 2170(e). We think the most natural reading, given its reference to subsection (d)(1), is that courts are barred from reviewing final “action[s]” the President takes “ to suspend or prohibit any covered transaction that threatens to impair the national security of the United States.” Id. § 2170(d)(1) (emphasis addеd). The text does not, however, refer to the reviewability of a constitutional claim challenging the process preceding such presidential action. [13] This conclusion is consistent with Ralpho and Ungar , where we determined that similarly broad statutory language did not bar our review of constitutional claims challenging the process by which unreviewable determinations were reached. See Ungar , 667 F.2d at 193-96; Ralpho , 569 F.2d at 620-22.
The Appellees’ reliance on legislative history and
congressional oversight provisions is equally unavailing. To
begin with, there is no legislative history expressly addressing
judicial review of constitutional claims arising from the
President’s implementation of section 721. Under
Ungar
and
Ralpho
, this gap may well be dispositive.
See Ungar
, 667
F.2d at 195-96 (no clear and convincing evidence because “no
reference to the proscription of judicial review” in legislative
history of statute or its “relatives”);
Ralpho
,
Even if the absence of express legislative history were not conclusive, the nature of congressional oversight currently provided for in the DPA does not demonstrate that the Congress intended to withhold a judicial forum for a due process claim challenging the procedure followed by the President. Congressional oversight of the President under the current version of the statute consists of an annual, ex post review of “decisions or actions by the President” taken under section 721 and the President’s assessment of foreign efforts to acquire critical technologies. 50 U.S.C. app. § 2170(m)(2), (3). We hardly think that, by reserving to itself such limited review of presidential actions and critical technology assessments, the Congress intended to abrogate the courts’ traditional role of policing governmental procedure for constitutional infirmity and perform that function itself. See, e.g. , Landon v. Plasencia , 459 U.S. 21, 34-35 (1982) (even where matters are “largely within the control of the executive and the legislature,” judiciary retains role in determining whether procedures employed by other branches “meet the essential standard of fairness under the Due Process Clause”). Indeed, the inferences to be drawn from the oversight provisions are unquestionably weaker than the inferences to be
23
drawn from the Congress’s rejection of (1) a judicial review
scheme for trial of just compensation claims,
see Ungar
, F.2d at 195 & n.2, or (2) a provision expressly providing for
judicial review of FLRA decisions involving constitutional
claims,
see Griffith
, 842 F.2d at 495. Yet in neither
circumstance did we find clear and convincing evidence that
the Congress intended to preclude judicial review of
constitutional claims.
See Griffith
, 842 F.2d at 495;
Ungar
,
B. J USTICIABILITY
The Appellees also argue that Ralls’s due process
challenge to the Presidential Order raises a non-justiciable
political question.
See
Br. for the Appellees 31 (due process
challenge to Presidential Order “calls for non-judicial
discretion, is constitutionally committed to the Executive
Branch, and offers no judicially discoverable or manageable
standards”). “The political question doctrine is essentially a
function of the separation of powers and excludes from judicial
review those controversies which revolve around policy
choices and value determinations constitutionally committed
for resolution to the halls of Congress or the confines of the
Executive Branch.”
El-Shifa Pharm. Indus. Co. v. United
States
,
The framework to determine if a complaint presents a non-justiciable political question is set forth in Baker v. Carr , 369 U.S. 186 (1962). Under Baker , the political question doctrine bars a court from considering a claim when
[p]rominent on the surface of [the] case . . . is found a [1] textually demonstrable constitutional commitment of the issue to a coordinate political department; or [2] a lack of judicially discoverable and manageable standards for resolving it; or [3] the impossibility of deciding without an initial policy determination of a kind clearly for nonjudicial discretion; or [4] the impossibility of a court’s undertaking independent resolution without expressing lack of the respect due coordinаte branches of government; or [5] an unusual need for unquestioning adherence to a political decision already made; or [6] the potentiality of embarrassment from multifarious pronouncements by various departments on one question.
Id.
at 217;
see also Wilson v. Libby
,
We disagree. First, Ralls’s due process claim does not challenge (1) the President’s determination that its acquisition of the Project Companies threatens the national security or (2) the President’s prohibition of the transaction in order to mitigate the national security threat. Much like the political question we declined to consider in PMOI I , reviewing these determinations would require us to exercise judgment in the realm of foreign policy and national security. But Ralls does not request that we exercise such judgment. Instead, Ralls asks us to decide whether the Due Process Clause entitles it to have notice of, and access to, the evidence on which the President relied and an opportunity to rebut that evidence before he reaches his non-justiciable (and statutorily unreviewable) determinations. See infra note 19. We think it clear, then, that Ralls’s due process claim does not encroach on the prerogative of the political branches, does not require the exercise of non-judicial discretion and is susceptible to judicially manageable standards. To the contrary, and as the Supreme Court recognized long ago, interpreting the provisions of the Constitution is the role the Framers entrusted to the judiciary. See Zivotfsky , 132 S. Ct. at 1427-28 (“It is emphatically the province and duty of the judicial department to say what the law is.” (quoting Marbury v. Madison , 5 U.S. (1 Cranch) 137, 177 (1803))). [16]
C. T HE M ERITS
“We review the grant of a motion to dismiss
de novo
,”
Cal.
Valley Miwok Tribe v. United States
, 515 F.3d 1262, 1266
(D.C. Cir. 2008), “treat[ing] the complaint’s factual allegations
as true and . . . grant[ing] plaintiff the benefit of all inferences
that can be derived from the facts alleged,”
Sparrow v. United
Air Lines, Inc.
, 216 F.3d 1111, 1113 (D.C. Cir. 2000)
(quotation marks and citation omitted). We do not accept as
true, however, the plaintiff’s legal conclusions or inferences
that are unsupported by the facts alleged.
See Browning v.
Clinton
,
The gravamen of Ralls’s challenge to the Presidential Order is that the President deprived it of its constitutionally protected property interests in the Project Companies and their assets without due process of law. The Due Process Clause of the Fifth Amendment provides that “[n]o person shall be . . . deprived of life, liberty, or property, without due process of law.” U.S. C ONST . amend. V. “The first inquiry in every due process challenge is whether the plaintiff has been deprived of a protected interest in ‘property’ or ‘liberty.’ ” Am. Mfrs. Mut. Ins. Co. v. Sullivan , 526 U.S. 40, 59 (1999). If the plaintiff has been deprived of a protected interest, we then consider whether the procedures used by the Government in effecting the deprivation “comport with due process.” Id.
1. Constitutionally Protected Property Interest
“Because the Constitution protects rather than creates
property interests, the existence of a property interest is
determined by reference to ‘existing rules or understandings
that stem from an independent source such as state law.’ ”
Phillips v. Wash. Legal Found.
, 524 U.S. 156, 164 (1998)
(quoting
Bd. of Regents of State Colleges v. Roth
, 408 U.S.
564, 577 (1972));
see also Cleveland Bd. of Educ. v.
Loudermill
, 470 U.S. 532, 538 (1985). In other words,
property interests “attain . . . constitutional status by virtue of
the fact that they have been initially recognized and protected
by state law.”
Paul v. Davis
,
The district court found, and the Appellees dо not dispute,
that Ralls possessed state law property interests when it
acquired 100% ownership of the Project Companies and their
assets, including local easements permitting the construction of
wind turbines, power purchase and generator interconnection
agreements with the local utility, transmission interconnection
and management agreements with nearby windfarms and the
necessary permits and approvals to construct wind turbines.
See Ralls Corp.
,
In the usual case, the fact that the property interest is recognized under state law is enough to trigger the protections of the Due Process Clause. See, e.g. , Phillips , 524 U.S. at 163-64; Loudermill , 470 U.S. at 538; Paul , 424 U.S. at 710. Yet here, the district court concluded that Ralls’s state law property interests were not constitutionally protected because Ralls (1) acquired its property interests “subject to the known risk of a Presidential veto” and (2) “waived the opportunity . . . to obtain a dеtermination from CFIUS and the President before it entered into the transaction.” Ralls Corp. , 2013 WL 5565499, at *7. The Appellees take up this mantle on appeal, arguing that Ralls’s property interests are too contingent to merit constitutional protection and that Ralls effectively forfeited those interests by not seeking pre-approval of the transaction.
We reject the rationale used by the district court and advocated by the Appellees. First, we disagree with the notion that Ralls’s state-law property interests are too contingent for constitutional protection. Ralls’s state-law property rights fully vested upon the completion of the transaction, meaning due process protections necessarily attached. There is nothing “contingent” about the interests Ralls obtained under state law, and the Appellees offer no legal support––other than the district court order––for the proposition that the nature of a property interest recognized under state law is affected by potential federal deprivation. As Ralls aptly notes, the Federal Government cannot evade the due process protections afforded to state property by simply “announcing that future deprivations of property may be forthcoming.” Br. for Appellant 21, Ralls Corp. v. Comm. on Foreign Inv. in the U.S. , No. 13-5315 (D.C. Cir. Feb. 7, 2014).
This case is quite different from Dames & Moore v. Regan , 453 U.S. 654 (1981), relied upon by the Appellees. There, the Court concluded that petitioner Dames & Moore’s attachment of Iranian property was too contingent to “support a constitutional claim for compensation” under the Takings Clause of the Fifth Amendment, id. at 674 n.6, because, according tо regulations promulgated by the Treasury Department’s Office of Foreign Assets Control, attachments of Iranian property were “null and void” unless licensed and all licenses could be “ ‘amended, modified, or revoked at any time’ ” by the President, id. at 672-73 (quoting 31 C.F.R. § 535.805 (1980)). Thus, Dames & Moore obtained its right to attach only after it was licensed by the Government, which license was itself revocable at any time and, presumably, for any reason. We think there is a significant difference between Ralls’s fully-vested state property interests and an interest like the Dames & Moore attachment, which interest is contingent at best. [17] There is no contingency built into the state law from which Ralls’s property interests derive and to which interests due process protections traditionally apply. See, e.g. , Phillips , 524 U.S. at 163-64; Loudermill , 470 U.S. at 538; Paul , 424 U.S. at 710.
Nor do we think Ralls has waived its property interest by
failing to seek pre-approval of the transaction. The district
court found wavier based on two out-of-circuit cases:
Alvin v.
Suzuki
,
2. What Process is Due?
“[U]nlike some legal rules,” due process “is not a
technical conception with a fixed content unrelated to time,
place and circumstances.”
Nat’l Council of Resistance of Iran
v. Dep’t of State
(
NCRI
),
424 U.S. 319, 335 (1976). Due process ordinarily requires
that procedures provide notice of the proposed official action
and “the opportunity to be heard at a meaningful time and in a
meaningful manner.”
Id.
at 333 (quotation marks omitted);
see also NCRI
, 251 F.3d at 205 (“[T]hose procedures which
have been held to satisfy the Due Process Clause have included
notice of the action sought, along with the opportunity to
effectively be heard.” (quotation marks omitted)). Both the
Supreme Court and this Court have recognized that the right to
know the factual basis for the action and the opportunity to
rebut the evidence supporting that action are essential
components of due process.
See, e.g.
,
Greene v. McElroy
, 360
U.S. 474, 496 (1959) (citing “immutable” principle in case
involving revocation of security clearance that “the evidence
used to prove the Government’s case must be disclosed to the
individual so that he has an opportunity to show that it is
untrue”);
Gray Panthers v. Schweiker
,
Reviewing a due process challenge to the FTO designation process, we concluded in NCRI that NCRI could not be designated a FTO and thereby deprived of its interest in a “small bank account” without first receiving notice of the proposed designation, access to the unclassified evidence supporting the designation and an opportunity to rebut that evidence. 251 F.3d at 201, 208-09. These procedural protections are required by the Due Process Clause, we held, notwithstanding the Government’s “compelling” interest in national security, id. at 207, and despite our uncertainty that NCRI could effectively rebut the Secretary’s evidence, id. at 209 (“We have no reason to presume that the petitionеrs . . . could have offered evidence which might have . . . changed the Secretary’s mind . . . . However, without the due process
35
protections which we have outlined, we cannot presume the
contrary either.”);
see also PMOI II
, 613 F.3d at 228
(following
NCRI
and rejecting State’s argument that “nothing
the [FTO] would have offered . . . could have changed [the
Secretary’s] mind”). At the same time, we made clear––and
we iterate today––that due process does not require disclosure
of
classified
information supporting official action.
See
NCRI
,
Notwithstanding
this precedent,
the district court
concluded that Ralls received adequate process because it was
notified that the transaction was subject to review and was
given an opportunity to present evidence in its favor in both its
voluntary notice filing and during follow-up conversations
with––and a presentation to––CFIUS officials. In light of the
Appellees’ substantial interest in protecting national security,
the court determined that no additional process was required.
Notably, the district court found
NCRI
and its progeny
inapplicable.
NCRI
was inapplicable, the court said, in that it
mandated disclosure of unclassified information only because
the information was eventually going to be publicly available.
See Ralls Corp.
,
The Appellees make a similar argument in their brief, arguing that Ralls’s ability to submit written arguments, meet with CFIUS officials in person, answer follow-up questions and receive advance notice of the Appellees’ intended action constitutes sufficient process in light of the national security interests at stake. The Appellees similarly urge the inapplicability of the FTO cases, arguing that they do “not meaningfully resemble” this case because “the decision whether to prohibit Ralls’ transaction was committed to the President’s discretion.” Br. for the Appellees 42. Finally, the Appellees assert that Ralls cannot “utilize this Court to force disclosure of the President’s thinking on sensitive questions in discretionary areas and obtain otherwise forbidden judicial review.” Id. at 41. And, even if such process is required, the Appellees requested––for the first time during oral argument––that we remand so that the district court can consider whether disclosure of certain unclassified information is nonetheless shielded by executive privilege.
We conclude that the Presidential Order deprived Ralls of
its constitutionally protected property interests without due
process of law. As the preceding discussion makes plain, due
process requires, at the least, that an affected party be informеd
of the official action, be given access to the unclassified
evidence on which the official actor relied and be afforded an
opportunity to rebut that evidence.
See, e.g.
,
McElroy
, 360
U.S. at 496;
NCRI
,
The Appellees’ arguments for distinguishing the FTO
cases are unconvincing. First, and contrary to the district
court, we read
NCRI
and its progeny to hold that disclosure of
unclassified evidence
is
required by the Due Process Clause
and not simply because the unclassified information is going to
be disclosed in any event. Our decisions aрplying
NCRI
make
this clear.
See, e.g.
,
PMOI II
,
The Appellees’ argument that we should refrain from requiring disclosure of the President’s thinking on sensitive questions is off-base. Our conclusion that the procedure followed in issuing the Presidential Order violates due process does not mean the President must, in the future, disclose his thinking on sensitive questions related to national security in reviewing a covered transaction. We hold only that Ralls must receive the procedural protections we have spelled out before the Presidential Order prohibits the transaction. The DPA expressly provides that CFIUS acts on behalf of the President in reviewing covered transactions, see 50 U.S.C. app. § 2170(b)(1)(A) (review conducted by “President, acting through [CFIUS]”), and the procedure makes clear that the President acts only after reviewing the record compiled by CFIUS and CFIUS’s recommendation, see 31 C.F.R. § 800.506(b), (c). Adequate process at the CFIUS stage, we believe, would also satisfy the President’s due process obligation. As for the Appellees’ belated assertion of executive privilege, this argument was not raised in the Appellees’ brief and we leave it to the district court on remand to consider whether the executive privilege shields the ordered disclosure.
In sum, we conclude that Ralls possesses substantial property interests and that the Presidential Order deprives Ralls of its interests without due process of law.
III. CFIUS ORDER CLAIMS
We next consider the district court’s dismissal of Ralls’s
CFIUS Order claims as moot inasmuch as the CFIUS Order
was expressly revoked by the Presidential Order.
Under Article III of the Constitution, a federal court “may
only adjudicate actual, ongoing controversies.”
Honig v. Doe
,
Both parties appear to acknowledge that Ralls’s CFIUS Order claims were mooted when the Presidential Order revoked the CFIUS Order and deprived it of any effect. Ralls contends, however, that we may nonetheless consider the claims under the “capable of repetition yet evading review” exception to mootness. To satisfy the exception, a party must demonstrate that “(1) the challenged action is in its duration too short to be fully litigatеd prior to its cessation or expiration, and (2) there [is] a reasonable expectation that the same complaining party [will] be subjected to the same action again.” Clarke , 915 F.2d at 704 (second alteration added). “When these two circumstances are simultaneously present, the plaintiff has demonstrated an exceptional circumstance in which the exception will apply.” Del Monte Fresh Produce Co. v. United States , 570 F.3d 316, 322 (D.C. Cir. 2009) (quotation marks, citation and brackets omitted). We conclude that Ralls has established both prongs of the exception.
A. E VADING R EVIEW
A challenged action evades review if it is too short in
duration to be fully litigated in the United States Supreme
Court before it expires.
See Christian Knights of Ku Klux
Klan Invisible Empire, Inc. v. District Columbia
,
Armstrong
does not lead to a contrary conclusion. Even
if Ralls had sought judicial review of the CFIUS Order on the
day it issued, it could not have obtained review by the district
court, this Court and the Supreme Court before the order was
revoked. The same is true for CFIUS mitigation orders that
last for the full ninety days as “triаl and appellate proceedings
routinely take more than twelve months to complete.”
Christian Knights of Ku Klux Klan
,
B. C APABLE OF R EPETITION
Action is “capable of repetition” if there is “a reasonable
expectation that the same complaining party [will] be subjected
to the same action again.”
Christian Knights of Ku Klux Klan
,
Doe v. Sullivan demonstrates that a controversy is capable of repetition even if its recurrence is far from certain. There, a U.S. service member serving in Operation Desert Shield brought a putative class action challenging a Food and Drug Administration (FDA) regulation permitting it to “make the determination that obtaining informed consent from military personnel for the use of an investigational drug . . . is not feasible in certain battlefield or combat-related situations.” 938 F.2d at 1373. The FDA determined that “obtaining informed consent was not feasible” for the use of two investigational drugs sought to be used to defend against a chemical weapons attack. Id. at 1374. By the time the case reached this Court, however, the military operation had ended, id. at 1375, and the service member’s claims were therefore mooted. We nevertheless concluded that the challenged actiоn was capable of repetition, i.e. , there was “some likelihood” it would recur, because of the challenger’s “continuing status as a member of our armed forces” and the FDA’s likely retention of the regulation. Id. at 1378-79. We reached this conclusion notwithstanding the fact that the “next conflict [was] not yet upon us.” Id. at 1379.
The district court concluded that Ralls “failed to demonstrate that there is a reasonable expectation that it will be subject to the same action again in the future.” Ralls Corp. , 926 F. Supp. 2d at 97. Although the court accepted Ralls’s claim that it intended to engage in covered transactions involving the acquisition of windfarms across the United States, the court decided there was not “a reasonable likelihood that Ralls’s purchase of a different windfarm in a different location will necessarily give rise to the same response.” Id. at 99. The Appellees similarly contend that CFIUS issued its Order “in response to the particular concerns that arose in the Committee’s review of the particular transaction, involving a particular geographic region” and therefore Ralls cannot show that such a context-specific decision is likely to recur. Br. for the Appellees 46.
We disagree. Ralls alleged in its amended complaint that
it “intends to continue pursuing windfarm development
opportunities in the United States and acquiring existing
windfarm greenfield companies to do so, in the manner of its
acquisition of the Project Companies.” Am. Compl. ¶ 71.
Taking this allegation as true, as we must at the dismissal stage,
see El-Shifa
,
* * * * *
In sum, we conclude that thе Presidential Order deprived Ralls of constitutionally protected property interests without due process of law. We remand to the district court with instructions that Ralls be provided the requisite process set forth herein, which should include access to the unclassified evidence on which the President relied and an opportunity to respond thereto. See NCRI , 251 F.3d at 209 (leaving FTO designation in place and ordering Secretary of State to provide designated entity with access to unclassified evidence supporting designation and opportunity to respond). Should disputes arise on remand––such as an executive privilege claim––the district court is well-positioned to resolve them. Finally, because the CFIUS Order claims were dismissed on a jurisdictional ground, and given the scant merits briefing, we leave it to the district court to address the merits of Ralls’s remaining claims in the first instance. [23]
So ordered. Appellees argue that “Ralls has completed other transactions that have not caused CFIUS to issue mitigation orders.” Br. for the Appellees 46 (citing JA 36, 95-96). But those transactions are not “covered transactions” and are thus plainly distinguishable. These claims include Ralls’s APA challenge to the CFIUS Order (Counts I and II), its ultra vires challenge (Count III) and its due process and equal protection challenges (Counts IV and V, in part).
Notes
[1] The name comes from its co-sponsors, former Senator James Exon (D-Neb.) and former Representative James Florio (D-N.J.).
[2] CFIUS includes the Secretaries of Treasury, Homeland Security, Commerce, Defense, State and Energy; the Secretary of Labor and the Director of National Intelligence, who participate as non-voting, ex officio members; the United States Attorney General; and other officials as the President deems appropriate. 50 U.S.C. app. § 2170(k)(2). The President also appointed the United States Trade Representative and the Director of the Office of Science and Technology Policy to CFIUS and directed several White House
[5] Ralls’s acquisition of the Project Companies resulted from a series of transactions. In 2010, Oregon Windfarms, LLC, sold its interest in the Project Companies to Terna Energy USA Holding Corporation (Terna), a Delaware corporation owned by a publicly traded Greek company. In 2012, Terna sold the Project Companies to Intelligent Wind Energy, LLC (IWE), a Delaware company owned by U.S. Innovative Renewable Energy, LLC (USIRE). USIRE sold IWE to Ralls.
[6] Unless otherwise indicated, all events occurred in 2012.
[7] Ralls conceded in district court that it submitted the notice only after CFIUS informed it that the Defense Department intended to file a notice triggering CFIUS review if Ralls did not file first.
[8] Although the record includes copies of the two orders CFIUS issued in July and August, it does not contain the September report and recommendation CFIUS submitted to the President.
[9] Ralls does not appeal the dismissal of its ultra vires and equal protection challenges to the Presidential Order (Count III in part and Count V in part).
[10] Citing
General Electric Co. v. EPA
,
[11] In Griffith , we declined a similar invitation to draw inferences from legislative history. See 842 F.2d at 494. There, we concluded that a conference committee’s “silent deletion” of a provision in the original Senate bill providing for judicial review of Federal Labor Relations Authority decisions involving a
[12] Among other changes, FINSA requires CFIUS to submit more detailed notices and reports to the Congress upon completion of individual reviews and investigations, see 50 U.S.C. app. § 2170(b)(3), (m), and provide prompt nоtice of the results of its review or investigation to the parties to a covered transaction, see id. § 2170(b)(6). FINSA also requires any agency acting on behalf of CFIUS to make detailed reports to CFIUS regarding “any agreement entered into or condition imposed” by the agency. See id. § 2170( l )(3)(B)(i).
[13] The legislative history of FINSA supports our reading. Specifically, Senate Report No. 109-264 notes that the bar-to-review provision precludes judicial review of “Presidential decisions resulting from exercise of the authorities” granted therein. S. R EP . N O . 109-264, at 11. This statement supports the reading that the provision applies to the President’s final decisions.
[14] This provision is included in the Antiterrorism and Effective Death Penalty Act of 1996 (AEDPA), Pub. L. No. 104-132, 110 Stat. 1214, as amended by the Illegal Immigration Reform and Immigrant Responsibility Act of 1996, Pub. L. No. 104-208, Div. C., 110 Stat. 3009, 3009-546.
[15] In addition to
PMOI I
, 182 F.3d 17, we also resolved due
process challenges to FTO designations in
National Council of
Resistance of Iran v. Department of State
(
NCRI
), 251 F.3d 192
(D.C. Cir. 2001), and
People’s Mojahedin Organization of Iran v.
Department of State
(
PMOI II
),
[16] For the foregoing reasons, we also conclude that justiciability does not present an obstacle to our consideration of the CFIUS Order claims.
[17] Moreover, the Court in Dames & Moore went out of its way to stress that its holding has limited, if any, application beyond its particular facts. See Dames & Moore , 453 U.S. at 661 (“We attempt to lay down no general ‘guidelines’ covering other situations not involved here, and attempt to confine the opinion only to the very questions necessary to decision of the case.”).
[18] But even at the second step of the due process inquiry, the cases do not support the Appellees’ position. We read them to say that a party “waives” a due process claim only if he foregoes constitutionally adequate procedures. See Alvin , 227 F.3d at 116 (“[P]laintiff must have taken advantage of the processes that are available to him or her, unless those processes are unavailable or patently inadequate .” (emphasis added)); Parker ,981 F.2d at 1163 (“There is no violation of due process, because plaintiff chose to end her employment without a hearing and not to avail herself of the available due process procedures .” (emphasis added)). There is no indication that the process Ralls received after the transaction was completed is different from the process it would have received had it sought pre-approval––and, as discussed infra , that process was inadequate.
[19] Because the record did not reflect whether the evidence relied on was classified, unclassified or both, we issued an order before oral argument requesting that the Government be prepared to discuss the nature of the evidence reviewed by CFIUS and the President. Responding to our inquiry at oral argument, the Appellees’ counsel stated that CFIUS and the President relied on both classified and unclassified evidence.
[20] As noted earlier, see supra p. 11, Ralls’s TRO/PI motion was set to be heard on September 20, 2012, eight days before the Presidential Order revoking the CFIUS Order issued.
[21] The CFIUS Order acknowledges as much, stating that it lasts “until CFIUS concludes action or the President takes action . . . or upon revocation by CFIUS or the President.” JA 88.
[22] To support their assertion that the CFIUS Order was precipitated by unique factual circumstances not likely to recur, the
