258 Mass. 26 | Mass. | 1926
This is an action to recover damages for negligent delay in transporting .a carload of figs from Fall River to Montreal. The figs were delivered to the New Haven railroad at Fall River, on January 24, 1920, and arrived at Framingham January 31, 1920; the shipment left Framingham on March 17, and the next day was delivered to the Boston and Maine Railroad at Lowell. Federal control of carriers ceased March 1, 1920. The car was in possession of the defendant from March 1, to March 18, 1920. Lowell is distant thirty-seven miles from Framingham. The shipment arrived at Montreal on March 29, having been delayed for six days at the international boundary. The plaintiff’s claim was for the loss of market. There was a verdict for the plaintiff.
The first contention of the defendant is that the plaintiff
The defendant received the shipment from the United States Railroad Administration on March 1, 1920, at Framingham. The shipment remained in the defendant’s control at this point until March 17; it was then moved to Lowell and delivered to the Boston and Maine Railroad. There was evidence that from March 1,1920, to March 18, the weather conditions were not unusual, and the jury could have found that the defendant was negligent in permitting the plaintiffs’ property to remain in Framingham for seventeen days without moving it to the connecting carrier. The judge instructed the jury that, if the plaintiffs’ injury was due to weather conditions which could not be overcome by due diligence, there would be a justification for the delay; that the defendant was not liable for unusual or extraordinary emergencies, and was only required to use reasonable diligence “for the ordinarily normal conditions.” The defendant cannot complain of this instruction. See Bernier v. Pittsfield Coal Gas Co. 257 Mass. 188. A delay of eighteen days before delivering to the Boston and Maine Railroad,
The jury were instructed that the defendant was in no way responsible for anything which took place prior to March 1,1920, and was not responsible for any damage after the delivery of the car to the Boston and Maine Railroad. They were also instructed that, if the delay was caused in part by the negligence of the Federal government up to March 1, and in part to the negligence of the defendant, then the defendant would be liable on the principle that if two concur in producing a wrong either maybe said to have contributed in whole or in part to the tort; “not that the defendant would be liable for the delay caused by the Federal government, but because — if you are satisfied of that — because you would be satisfied that the defendant was in part responsible for the delay for a portion of the time from March first or any portion of the time from March first to March seventeenth.” The defendant asked for this instruction:, “If any preexisting negligence of the United States Railroad Administration was the sole cause, or the proximate cause of any delay, then the defendant is not liable.” This request was given with the qualification, “Except in the manner in which I heretofore stated, that if the defendant’s negligence contributed in whole or in part to the delay, it would be liable.” There was no error in adding the qualification to the request. If the damages were the result of the neglect of the United States Railroad
The defendant, however, was hable for its own carelessness, and the jury could have found that the defendant was negligent in failing to move the car; that this neglect was the proximate cause of the damage. See Fox v. Boston & Maine Railroad, 148 Mass. 220; Denny v. New York Central Railroad, 13 Gray, 481. The jury must have understood that the defendant was responsible solely for its own neglect and was not to be held for any neglect of the United States Railroad Administration. We find nothing in Nutting v. Connecticut River Railroad, 1 Gray, 502, Darling v. Boston & Worcester Railroad, 11 Allen, 295, Burroughs v. Norwich & Worcester Railroad, 100 Mass. 26, and Nominsky v. New York, New Haven & Hartford Railroad, 239 Mass. 254, to the contrary.
There was no error in the instructions given the jury in reference to the question of the defendant’s neglect in failing to provide suitable equipment. The question, whether the defendant failed in this respect, was one of fact, and the jury were correctly instructed on this point.
Exceptions overruled.