PW CAMPBELL CONTRACTING COMPANY v. AMANDA YETTER, JAY YETTER
No. 910 WDA 2024
IN THE SUPERIOR COURT OF PENNSYLVANIA
FILED: APRIL 14, 2025
NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT O.P. 65.37
BEFORE: KUNSELMAN, J., MURRAY, J., and BECK, J.
In the Court of Common Pleas of Washington County Civil Division at No(s): 2023-5633
MEMORANDUM BY BECK, J.:
PW Campbell Contracting Company (“PWCC“) appeals from the order entered by the Washington County Court of Common Pleas (“trial court“) striking PWCC‘s mechanics’ lien on the property of Amanda Yetter and Jay Yetter (together, the “Yetters“). Because we conclude that PWCC failed to comply with the pertinent provision of the Mechanics’ Lien Law (“MLL“),1 we affirm.
On August 9, 2021, PWCC entered into a contract with the Yetters to make certain improvements on their house in Canonsburg, Pennsylvania. The improvements included construction of a covered porch and pool house, along with the replacement of a window, door, roof, and siding of the main house.
Toward the end of 2022 and in the beginning of 2023, PWCC and the Yetters began to disagree about the quality of the improvements. The Yetters demanded PWCC remedy certain deficiencies in their work while PWCC demanded payment. PWCC stopped work on April 6, 2023.
On October 3, 2023, PWCC filed a statement of mechanics’ lien and alleged therein that the Yetters owed $77,292.29 as a “remainder balance owed for labor, material, supervision, equipment, and tools” required for the improvements made on the house. Subsequently, on December 4, 2023, PWCC filed a complaint to enforce their mechanics’ lien. PWCC attached the contract to the statement of mechanics’ lien and complaint but attached no invoices or any other documentation supporting the calculation of the $77,292.29 amount.
On January 3, 2024, the Yetters filed preliminary objections to the complaint for failure to conform and legal insufficiency. Of relevance to the pending matter, the Yetters argued that (1) the statement of mechanics’ lien claim was untimely and (2) despite being labeled “lump sum,” the contract
On March 8, 2024, PWCC filed a brief in opposition to the Yetters’ preliminary objections. Therein, PWCC argued that the timeliness of the statement of mechanics’ lien depended on a factual dispute between PWCC and the Yetters over when PWCC ceased working. PWCC further argued that the contract was not required under the MLL to list a “total sales price,” the contract set out exactly how the Yetters were charged, and the Yetters received monthly invoices with supporting documentation.
On June 20, 2024, the trial court entered an order sustaining the Yetters’ preliminary objections. The trial court initially found that strict compliance with the MLL is required to effectuate a valid claim. Trial Court Memorandum, 6/20/2024, at 3. The trial court observed that the PWCC did not state that the contract with the Yetters was for an “agreed sum” in its mechanics’ lien claim, as required for section 1503(5) to apply.2 Though the contract included a flat charge of $20,000 for architecture and engineering, PWCC asserted a lien for the “remainder balance owed for labor, material, supervision,
On July 22, 2024, PWCC filed a timely notice of appeal.4 It raises the following question for our review: “Whether the trial court erred in sustaining the Yetters’ Preliminary Objection under Pennsylvania Rule of Civil Procedure 1028(a)(2) because PWCC‘s mechanics’ lien complied with Section 1503(5) of Pennsylvania‘s [Mechanics‘] Lien Law,
In determining whether the trial court properly sustained preliminary objections, the appellate court must examine the averments in the complaint, together with the documents and exhibits attached thereto, in order to evaluate the sufficiency of the facts averred.
Our inquiry goes only to determining the legal sufficiency of appellant‘s complaint and we may only decide whether sufficient facts have been pleaded which would permit recovery if ultimately proven. We must be able to state with certainty that upon the facts averred, the law will not permit recovery by the plaintiff.
This Court will reverse the trial court‘s decision only where there has been an error of law or abuse of discretion. Further, when the sustaining of preliminary objections results in the denial of a claim or the dismissal of a suit in a mechanics’ lien proceeding, preliminary objections should be sustained only where the case is clear and doubtless.
Denlinger, Inc. v. Agresta, 714 A.2d 1048, 1050-51 (Pa. Super. 1998) (citations and quotation marks omitted). In interpretating and applying the MLL, our scope of review is plenary and non-deferential. Terra Tech. Svcs., LLC v. River Station Land, L.P., 124 A.3d 289, 298 (Pa. 2015).
PWCC argues the trial court erred in sustaining the Yetters’ preliminary objections. PWCC‘s Brief at 7. It asserts that the trial court erroneously applied a strict construction standard, rather than a substantial compliance standard, under
The MLL provides a right to a mechanics’ lien “for the payment of all debts due by the owner to the contractor ... for labor or materials furnished in the erection or construction ....”
Section 1503 governs the contents of MLL claims and provides, in relevant part:
The claim shall state:
* * *
(5) if filed by a contractor under a contract or contracts for an agreed sum, an identification of the contract and a general statement of the kind and character of the labor or materials furnished;
(6) in all other cases than that set forth in clause (5) of this section, a detailed statement of the kind and character of the labor or materials furnished, or both, and the prices charged for each[.]
The MLL does not define “agreed sum.” See generally id.
Here, it is clear that the relevant portion of the contract between PWCC and the Yetters was not for an “agreed sum.” The contract price for “[h]ard construction costs” had no amount of money listed, but instead was to be calculated based upon “the cost of the work, plus 25%.” Standard Form of Agreement, 8/9/2021, at 5. There is no indication in the contract that the Yetters had any knowledge of the amount of money that would constitute “the cost of work,” such that they agreed to a particular amount. We therefore agree with the trial court that PWCC was required to comply with
PWCC does not contend that it complied with
Order affirmed.
Judgment Entered.
Benjamin D. Kohler, Esq.
Prothonotary
DATE: 04/14/2025
