Price Trucking Corp. v. Norampac Indus., Inc.
Docket No. 11-2917-cv
UNITED STATES COURT OF APPEALS FOR THE SECOND CIRCUIT
Decided: March 18, 2014
August Term, 2012
(Argued: September 24, 2012)
Appeal from a judgment of the United States District Court for the Western District of New York (Richard J. Arcara, Judge). The district court, upon the report and recommendation of Magistrate Judge Hugh B. Scott, granted the plaintiff partial summary judgment on the issue of liability, and subsequently entered final judgment at the request of both parties. The district court
REVERSED and the case REMANDED.
JOHN GILBERT HORN (Craig A. Slater, of counsel), Harter Secrest & Emery LLP, Buffalo, N.Y., for Appellant.
KEVIN M. HOGAN, Phillips Lytle LLP (Patricia A. Mancabelli, of counsel), Buffalo, N.Y., for Appellee.
SACK, Circuit Judge:
This dispute presents an issue of apparent first impression regarding the federal Comprehensive Environmental Response, Compensation, and Liability Act (“CERCLA“). The defendant, a landowner, paid a general contractor for costs associated with the cleanup of a contaminated parcel of land that the defendant owned. The general contractor failed, however, to remit those payments to the
BACKGROUND
The principal facts underlying this lawsuit are undisputed. At all relevant times, the defendant Norampac Industries, Inc., owned a parcel of land in Erie County, New York. After Norampac discovered that soil at the site contained levels of lead and other contaminants that exceeded maximums set by the New York State Department of Environmental Conservation (“DEC“), the company entered into a Brownfield Site1 Cleanup Agreement with the DEC. The
In October 2007, pursuant to its cleanup obligations under the Agreement, Norampac contracted with AAA Environmental, Inc., a contractor located in upstate New York, to perform remedial work, including the excavation and removal of contaminated soil. The contract required that Norampac make “progress payments” to AAA Environmental at regular intervals based on the amount of work completed. The agreement between Norampac and AAA Environmental required the contractor to furnish performance and payment bonds in amounts equal to the total contract price, but these requirements were waived in a contract addendum.
In December 2007, AAA Environmental subcontracted with Price Trucking to transport from the site and dispose of the contaminated soil. Throughout the following year, Price Trucking hauled the soil to licensed disposal facilities. AAA Environmental initially paid Price for this service, but on or about October 6, 2008, the payments stopped. Once AAA Environmental refused to pay outstanding invoices, Price Trucking stopped working on the project, insisting that Norampac first agree to pay Price Trucking directly for its portion
As of September 19, 2008, the parties had substantially finished work on the site, and the DEC subsequently certified completion. By that time, Norampac had paid AAA Environmental more than $3 million for services related to the cleanup effort, in addition to the payments that Norampac had made directly to Price Trucking pursuant to the arrangement noted above. But Price was unable to recover the balance of the payments due to it from AAA Environmental. Other subcontractors who worked on the site also complained that they had not been paid in full. The parties agree that Price completed its work in compliance with the Agreement, the contract between Norampac and AAA, the subcontract between AAA and Price, and all applicable laws and regulations, and that Price received no objections from AAA Environmental, Norampac, or the DEC regarding its work.
On November 16, 2009, Price Trucking instituted this lawsuit against Norampac in the United States District Court for the Western District of New York, seeking $780,204.08 in unpaid bills for its work regarding the site. Price‘s sole theory of recovery in this action was premised on CERCLA‘s liability
On March 31, 2010, Price moved for partial summary judgment against Norampac on the issue of liability. Norampac cross-moved for summary judgment and an order dismissing the lawsuit. On June 17, 2010, Magistrate Judge Hugh B. Scott recommended that the district court rule in favor of Price Trucking on both motions. Price Trucking Corp. v. Norampac Indus., Inc., No. 09-cv-990A, 2010 WL 4069223, 2010 U.S. Dist. LEXIS 113216 (W.D.N.Y. June 17, 2010). District Judge Richard J. Arcara subsequently adopted the report‘s findings and recommendations, found in favor of Price on the issue of liability, and scheduled a trial to assess damages. Price Trucking Corp. v. Norampac Indus., Inc., No. 09-cv-990, 2011 WL 767702, 2011 U.S. Dist. LEXIS 18631 (W.D.N.Y. Feb. 25, 2011).
Instead of litigating the issue of damages, the parties stipulated that if there were liability, the damages were equal to the outstanding sum owed to Price Trucking: $631,257.02, plus interest. This amount is less than that stated in the complaint, reflecting, among other things, amounts recovered by Price Trucking in one of two related state court lawsuits, although the suits were pending at the
In the first such state-court action, Price Trucking sought to foreclose on a mechanic‘s lien imposed on Norampac‘s real property. See Second Am. Verified Compl. & Supplemental Summons, ¶¶ 27-35, Price Trucking Corp. v. Norampac Indus., Inc., No. 001547/2009 (N.Y. Sup. Ct. Erie Cnty. Nov. 12, 2009) (now consolidated in Case No. 000116/2009). In the same action, Price Trucking brought claims against AAA Environmental and its owner on theories of, inter alia, breach of contract, quantum meruit, unjust enrichment, and breach of trust. Id. ¶¶ 36-72. It appears that Price Trucking has so far been unable to recover from AAA directly; Norampac has asserted that AAA is out of business. But Price Trucking did recover $131,576.27 plus interest from Norampac on its lien-foreclosure claim.2
Price Trucking also brought a state-court action against First Niagara Bank, one of AAA‘s creditors, on behalf of itself and other similarly situated
In light of the pendency of the state proceedings, the parties prepared a consent order setting out the amount that would be the subject of this appeal and providing that any additional amounts recovered in state court would further reduce the amount of the federal claim. The district court adopted this order, and, on June 24, 2011, entered final judgment in favor of Price Trucking.
Norampac appeals.
DISCUSSION
The sole question presented by this appeal is whether CERCLA creates direct liability between owners and subcontractors with respect to cleanup on a
“We review a district court‘s decision grant of summary judgment de novo, viewing the evidence in the light most favorable to the non-moving party and drawing all inferences and resolving all ambiguities in its favor.” CILP Assocs., L.P. v. PriceWaterhouse Coopers LLP, 735 F.3d 114, 122 (2d Cir. 2013) (internal quotation marks omitted). “Specifically, [where] the district court‘s disposition presents only a legal issue of statutory interpretation[,] we review de novo whether the district court correctly interpreted the statute.” City of Syracuse v. Onondaga Cnty., 464 F.3d 297, 310 (2d Cir. 2006) (internal quotation marks, ellipsis, and brackets omitted); accord New York v. Next Millenium Realty, LLC, 732 F.3d 117, 126 (2d Cir. 2013) (stating that the interpretation of CERCLA “is a question of law that we review de novo“).
I. CERCLA
CERCLA‘s “primary purposes are axiomatic: (1) to encourage the timely cleanup of hazardous waste sites; and (2) to place the cost of that cleanup on those responsible for creating or maintaining the hazardous condition.” W.R. Grace & Co.-Conn. v. Zotos Int‘l, Inc., 559 F.3d 85, 88 (2d Cir. 2009) (internal
CERCLA imposes liability for response costs incurred both by the government and by private parties.
To make out a prima facie case for liability under the Act, a plaintiff must establish that: (1) the defendant is an “owner” or is otherwise liable under
The parties have stipulated for the purposes of this litigation that Norampac owned the site at issue, that the site was a “facility” within the meaning of the statute, and that there were releases or threatened releases of hazardous substances at the site. We also assume without deciding that Price Trucking‘s actions were consistent with the National Contingency Plan.4 Finally,
There is no serious question as to whether the cost of removing contaminated soil constituted “response costs” within the meaning of CERCLA.5 The issue here is when and how liability for such costs is discharged by the owner of the site in question. Norampac contends that CERCLA liability is
The parties phrase their arguments in terms of whether the payments demanded by Price from Norampac constitute “necessary costs of response.” But, in simple terms, the issue in this case is not whether CERCLA requires Norampac to pay for the cleanup. The sole question is whether – under the circumstances presented here – CERCLA also requires Norampac to ensure that Price is made whole for its work.6
II. Analysis
A. Text of 42 U.S.C. § 9607(a)
Although CERCLA defines “response” to encompass a range of activities, it does not define the term “response costs.” See
The statute provides that the term “‘liability’ . . . shall be construed to be the standard of liability which obtains under section 311 of the Federal Water Pollution Control Act.”
Even bearing in mind that “response costs are liberally construed under CERCLA,” W.R. Grace, 559 F.3d at 92, we find nothing on the face of the statute that compels either the conclusion that, in the circumstances presented here,
B. Purpose of the Liability Provision
“Congress passes legislation with specific purposes in mind. When the ordinary tools of statutory construction permit us to do so, we must attempt to discover those purposes from the text, structure and history of the acts in question.” N.Y.C. Health & Hosps. Corp. v. Perales, 954 F.2d 854, 862-63 (2d Cir.), cert. denied, 506 U.S. 972 (1992); accord Internal Revenue Serv. v. WorldCom, Inc., 723 F.3d 346, 360 (2d Cir. 2013). This Court has long understood that “Congress enacted CERCLA with the expansive, remedial purpose of ensuring that those responsible for any damage, environmental harm, or injury from chemical poisons bear the costs of their actions.” Schiavone v. Pearce, 79 F.3d 248, 253 (2d Cir. 1996) (internal quotation marks omitted); see also W.R. Grace, 559 F.3d at 88 (a primary purpose of CERCLA is “to place the cost of . . . cleanup on those responsible for creating or maintaining [a] hazardous [environmental] condition” (internal quotation marks and brackets omitted)).
CERCLA accomplishes that purpose in two relevant ways. First, it imposes liability on a range of persons, including not only the property owner who might have been responsible for environmental damage, but other owners,
By clearing the path to liability of any obstacles or inconsistences imposed by varying state laws, CERCLA “encourage[s] private parties to assume the financial responsibility of cleanup by allowing them to seek recovery from others.” Key Tronic Corp. v. United States, 511 U.S. 809, 819 n.13 (1994) (quoting FMC Corp. v. Aero Indus., Inc., 998 F.2d 842, 847 (10th Cir. 1993)); accord W.R. Grace, 559 F.3d at 94; see also S. Rep. No. 96-848, at 31 (1980) (stating that CERCLA “is intended to induce potentially liable persons to voluntarily mitigate damages rather than simply rely on the government to abate hazards“). But while CERCLA obviously is designed to facilitate cost recovery, it does so through the assignment of tort-like liability and the clarification of the relevant standards; it does not provide for cost recovery in all cases and in all circumstances.8
And if the responsibility-assigning function of CERCLA will facilitate cost recovery by private parties in most cases, it need not and does not do so in every
CERCLA‘s purposes are served when landowners and others who profit from hazardous activities are made to bear the costs of accidents on their land. See, e.g., Commander Oil Corp. v. Barlo Equip. Corp., 215 F.3d 321, 330 (2d Cir.) (noting Congress‘s reference in crafting CERCLA to “the underlying fairness of imposing on the beneficiaries of an ultra-hazardous activity the ultimate costs of that activity“), cert. denied, 531 U.S. 979 (2000); S. Rep. No. 96-848, at 13 (“Strict
C. Role of State Law
We note, finally, that state law provides a well-developed, if not necessarily effective, system for resolving disputes like this one. “It is well settled that a subcontractor may not assert a cause of action to recover damages for breach of contract against a party with whom it is not in privity.” Perma Pave Contracting Corp. v. Paerdegat Boat & Racquet Club, Inc., 156 A.D.2d 550, 551, 549 N.Y.S.2d 57, 58 (2d Dep‘t 1989) (internal citation omitted); see also Remediation of Contaminated Materials Contract, Standard General Conditions § 6.06©, J.A. 219 (providing that no contractual obligations would exist between owner and subcontractor). Subcontractors who wish to hold a property owner responsible for unpaid work may proceed instead by placing a mechanic‘s lien on the owner‘s property. See
In light of our conclusion that CERCLA does not expressly create the liability that the plaintiff seeks to impose, we have no reason to suppose that Congress meant to upend by inference the longstanding principles of common law that bar direct recovery for breach of contract against a party not in privity with the claimant. See Isbrandtsen Co. v. Johnson, 343 U.S. 779, 783 (1952) (“Statutes which invade the common law . . . are to be read with a presumption favoring the
Here, Price Trucking has pursued its remedies under state law with some, albeit limited, success. Norampac has not disputed Price‘s right, as a subcontractor, to recover unpaid bills by placing a mechanic‘s lien directly on Norampac‘s property, at least insofar as payments from Norampac to AAA Environmental remain outstanding. Indeed, as already noted, Price was able to recover more than $130,000 from Norampac through a lien-foreclosure action. Our reading of CERCLA does nothing to close this avenue of recovery, nor does
Although CERCLA‘s liability provision may have been designed to impose a uniform standard of strict liability for specified costs, neither its terms nor the legislative history contain a comparable suggestion that the statute is meant to provide a substitution for the usual manner in which contractors and subcontractors are paid. The statute‘s drafters were doubtless aware that CERCLA responses would be carried out through public and private contracts. See, e.g.,
The purpose of CERCLA‘s liability provisions is to ensure that actors responsible for creating or maintaining hazardous environmental conditions bear the costs of their actions. In this case, that purpose was served when Norampac accepted responsibility for cleaning the Erie County site, ensured that the cleanup was completed as planned, and made payments under its contract with AAA Environmental for the removal of contaminated soil. To the extent that Norampac paid for Price Trucking‘s activities either through direct payments or through payments to its general contractor, it satisfied its responsibility to bear response costs under
Trucking has been unable to recover a portion of its costs falls outside the scope of Congress‘s concern in enacting the statute.
CONCLUSION
For the foregoing reasons, we REVERSE the judgment of the district court, and we REMAND the case with instructions to deny the plaintiff‘s motion for summary judgment and to grant summary judgment in favor of the defendant.
