PINNACLE ENTERPRISES, INC., APPELLANT AND CROSS-APPELLEE, V. CITY OF PAPILLION, A MUNICIPAL CORPORATION, APPELLEE AND CROSS-APPELLANT.
No. S-12-385
Supreme Court of Nebraska
July 26, 2013
286 Neb. 322
WRIT OF MANDAMUS DENIED.
MILLER-LERMAN, J., not participating.
N.W.2d
- Judgments: Jurisdiction. Jurisdictional questions that do not involve a factual dispute present questions of law.
- Statutes: Judgments: Appeal and Error. The meaning and interpretation of a statute are questions of law. An appellate court independently reviews questions of law decided by a lower court.
- Jurisdiction: Appeal and Error. An appellate court has a duty to raise and determine any jurisdictional issue of its own accord.
- Jurisdiction: Time: Appeal and Error. A party has only 30 days to appeal from a final order, and a party‘s failure to timely appeal from a final order prevents an appellate court from exercising jurisdiction over the issues raised and decided in that order.
- Eminent Domain. Condemnation proceedings are special proceedings.
- Actions. A “claim for relief” under
Neb. Rev. Stat. § 25-1315(1) (Reissue 2008) is equivalent to a separate cause of action. - Eminent Domain: Parties: Appeal and Error. In a condemnation action, because a district court appeal is a de novo proceeding, which contemplates the filing of pleadings and the framing of issues, no longer is the condemnee automatically the plaintiff in the district court proceeding. Rather, who the plaintiff is depends on who appeals first from the appraisers’ award.
Appeal from the District Court for Sarpy County: DANIEL E. BRYAN, JR., Judge. Affirmed.
Paul F. Peters, P.C., L.L.O., for appellant.
HEAVICAN, C.J., WRIGHT, CONNOLLY, STEPHAN, MCCORMACK, MILLER-LERMAN, and CASSEL, JJ.
CONNOLLY, J.
SUMMARY
The City of Papillion (City) condemned property owned by Pinnacle Enterprises, Inc. (Pinnacle), for the City‘s Schram Road project. The project connected various streets by building a new road and accompanying fixtures on Pinnacle‘s former property. Along with the road, the City built an iron fence on the north side of the new road, which abutted Pinnacle‘s remaining property. Pinnacle alleges that (1) the City lacked statutory authority to condemn the property for the fence and, alternatively, (2) the City imposed a second taking by building the fence and limiting its access to the new road. Because Pinnacle failed to timely appeal those issues, we do not reach them.
The City cross-appealed, alleging that the district court erred in granting Pinnacle interest, fees, expenses, and costs because the jury verdict did not exceed the City‘s prior offer to confess judgment. We conclude that the court correctly applied the statutes at issue and properly awarded Pinnacle interest, fees, expenses, and costs. We affirm.
BACKGROUND
The City wanted some of Pinnacle‘s land for a project to “redesign[], relocat[e] and mak[e] improvements to Schram Road . . . including paving, grading, curbing, integral storm sewers, decorative lighting and other necessary appurtenant improvements.” The City intended to build a new road, as an extension of the then-existing Schram Road, to connect several arterial streets. Because Pinnacle and the City could not agree, the City decided to condemn the property.
In its initial filing in county court, the City set out the property it sought to condemn, its authority to do so, the purpose for the condemnation, and the parties’ failure to reach an agreement. The City sought to acquire some property in
The City offered to confess judgment for $500,000,1 which Pinnacle refused. Before trial, Pinnacle filed what it termed its “Dispositive Pre-trial Motions.” Those motions essentially claimed—in addition to the insufficiency of the appraisers’ award—that the condemnation was void because the City (1) failed to negotiate in good faith and (2) lacked statutory authority to condemn Pinnacle‘s property for the fence. The parties agreed to try these issues to the court and reserve the sufficiency of the appraisers’ award for a later jury trial.2 Later, Pinnacle amended its petition to include these issues.
At the bench trial, Pinnacle argued that the easements were fatally vague, that the City lacked authority under
[T]he City . . . did negotiate in good faith with Pinnacle prior to the City[‘s] filing eminent domain proceedings in the County Court . . . .
. . . [T]he fence referenced in [Pinnacle‘s] Dispositive Pre-Trial Motions, does not constitute a second eminent domain taking and the Court specifically finds against [Pinnacle] and in favor of the [City] on all issues raised by [Pinnacle‘s] Dispositive Pre-trial Motions . . . .
Pinnacle did not appeal this order.
Following the jury trial, the court awarded Pinnacle interest, attorney and expert witness fees, expenses, and costs. In its order, the court determined that under
ASSIGNMENTS OF ERROR
Pinnacle assigns, restated, that the court erred in concluding that (1) the City had statutory authority to condemn the property for the fence and (2) the City‘s building of the fence was not a second taking that limited Pinnacle‘s access to the new road.
On cross-appeal, the City assigns, reordered and restated, that the court erred in (1) granting Pinnacle interest because the jury verdict did not exceed the City‘s $500,000 offer to confess judgment and (2) granting Pinnacle fees, expenses, and costs because the jury verdict did not exceed the City‘s $500,000 offer to confess judgment by more than 15 percent.
STANDARD OF REVIEW
[1] Jurisdictional questions that do not involve a factual dispute present questions of law.3
ANALYSIS
FINAL ORDER
[3,4] Although neither party raised or discussed whether the court‘s order resolving the issues addressed in the bench trial was a final, appealable order, an appellate court has a duty to raise and determine any jurisdictional issues of its own accord.6 A party has only 30 days to appeal from a final order,7 and a party‘s failure to timely appeal from a final order prevents an appellate court from exercising jurisdiction over the issues raised and decided in that order.8
Here, Pinnacle filed its appeal on May 2, 2012 (within 30 days of judgment on the jury verdict), but the issues that Pinnacle raised on appeal—whether the City had authority under
[5] Under
The meaning of a “substantial right” is somewhat vague. We have stated that a substantial right is an essential legal right, not a mere technical right.11 We have also stated that a substantial right is affected if an order affects the subject matter of the litigation, such as diminishing a claim or defense that was available to the appellant before the order from which the appeal is taken.12
We turn now to the court‘s order and whether it affected a substantial right. The order denied Pinnacle‘s “Dispositive Pre-Trial Motions,” which argued, among other things, that the City lacked statutory authority under
The court‘s ruling that the City had statutory authority to condemn the property for the construction of a fence was a final, appealable order. This conclusion flows from our reasoning in SID No. 1 v. Nebraska Pub. Power Dist.13 In
We first addressed whether the orders were final, because other issues—including the adequacy of the damages—were still pending before the court. We noted that whether the orders were final depended on whether they qualified under one of the three categories enumerated in
Similarly, the court‘s order here eliminated what Pinnacle alleged to be a defense to condemnation—that the City had no authority to condemn property for construction of a fence. And although Pinnacle did not allege that such a finding would
The court‘s ruling that the City‘s construction of the fence was not a second taking was also a final, appealable order. We read the court‘s order as concluding that the construction of the fence was simply not a taking. This reading is supported by various portions of the bill of exceptions and by the court‘s later ruling that Pinnacle was foreclosed from adducing evidence of its purported damages from the fence‘s construction (which the court would have allowed had it considered it to be a taking involved in the current condemnation proceeding).
Remember, “[a] substantial right is affected if the order affects the subject matter of the litigation, such as diminishing a claim or defense that was available to the appellant prior to the order from which the appeal is taken.”20 The court‘s order meant that Pinnacle could not adduce evidence of any purported damage from the City‘s building of the fence in the present proceeding. Notably, too, it meant that Pinnacle was
We note briefly that Pinnacle, in its response to our order to show cause, argued that the January 2012 order was not final because the order did not comply with
When more than one claim for relief is presented in an action, . . . or when multiple parties are involved, the court may direct the entry of a final judgment as to one or more but fewer than all of the claims or parties only upon an express determination that there is no just reason for delay and upon an express direction for the entry of judgment.
Pinnacle argues that because it presented multiple claims for relief (which were not all resolved), and because the court did not expressly state that the January order was final, it was not a final order.
[6] But
CROSS-APPEAL
As our appellate rules explain, “[t]he proper filing of an appeal shall vest in an appellee the right to a cross-appeal against any other party to the appeal. The cross-appeal need only be asserted in the appellee‘s brief as provided by § 2-109(D)(4).”23 The City properly asserted its cross-appeal in its brief.
The City disagrees with the court‘s award of interest, fees, expenses, and costs to Pinnacle. The City claims that the court erred in entering the award because the jury verdict did not exceed the City‘s prior offer to confess judgment. But the initial question is whether the City could offer to confess judgment. We conclude that it could not and, furthermore, that the court‘s award of interest, fees, expenses, and costs was proper.
Both
The defendant in an action for the recovery of money only, may, at any time before the trial, serve upon the plaintiff, or his attorney, an offer in writing to allow judgment to be taken against him for the sum specified therein. . . . If the plaintiff fails to obtain judgment for more than was offered by the defendant, he shall pay the defendant‘s cost from the time of the offer.
The question is whether
We take this opportunity to clarify the status of the parties in the district court appeal of a condemnation proceeding. Initially, as the condemnor is the party initiating the proceeding, the condemnor is the plaintiff and the condemnee is the defendant at the county court level. But this can change at the district court level. Under prior versions of
[7] This changed in 1995 when the Legislature removed that language and substituted the following: “The first party to perfect an appeal shall file a petition on appeal in the district court. . . .”25 The change was meant to place the onus of filing a petition on the party who was appealing the appraisers’ award rather than always requiring the condemnee to do so.26 And because the district court appeal is a “de novo” proceeding,27 which contemplates the ““filing of pleadings and the framing of issues,”28 no longer is the condemnee automatically the plaintiff in the district court proceeding. Rather, who the plaintiff is depends on who appeals first from the appraisers’ award. So on appeal, the City was the defendant.
We give statutory language its plain and ordinary meaning.29 Section 25-901 provides that “[t]he defendant” may offer to confess judgment. The statute also provides that the defendant may do so “in an action for the recovery of money only.” While the City is the defendant in this condemnation proceeding, such a proceeding is not “for the recovery of money only.” As such, the City‘s offer to confess judgment was invalid.
Here, the proceeding was a condemnation proceeding commenced by the City against Pinnacle. A condemnation proceeding is “the exercise of eminent domain by a governmental
The proceeding does not change simply because Pinnacle appealed the appraisers’ award to the district court. It is true that the district court proceeding is a de novo proceeding which contemplates the filing of pleadings and the framing of issues.32 But it is not a new proceeding. We recognized this in Wooden v. County of Douglas,33 when we explained that “the [condemnee‘s] petition on appeal . . . was not the commencement of a new action, but simply a continuation of the condemnation action filed by the County.”34 And, as noted above, a condemnation proceeding is not “for the recovery of money only.” Section 25-901 does not apply, and so the City‘s offer to confess judgment was invalid.
Because
Under
If an appeal is taken from the award of the appraisers by the condemnee and the amount of the final judgment
is greater by fifteen percent than the amount of the award, . . . the court may in its discretion award to the condemnee a reasonable sum for the fees of his or her attorney and for fees necessarily incurred for not more than two expert witnesses.
The court awarded such fees, and we find no abuse of discretion.
The district court also awarded “costs” to Pinnacle. From the court‘s order, we read “costs” to include the deposition expenses for $1,419.50. We have treated such expenses as costs in the past.35 Unlike interest and fees, however, the eminent domain statutes do not expressly allow the court to award costs when the condemnee appeals the appraisers’ award and obtains a greater amount from the jury. Nevertheless, the court‘s award of costs was proper under our case law.36
CONCLUSION
We conclude that the court‘s January 2012 order was a final order from which Pinnacle failed to timely appeal. We also conclude that the City‘s offer to confess judgment was invalid and that the court‘s award of interest, fees, expenses, and costs was proper.
AFFIRMED.
CONNOLLY, J.
