Petticrew v. St. Lawrence Cement, Inc.Petticrew v. St. Lawrence Cement, Inc.
Carpinello, J.
This negligence and Labor Law action stems from an accident that plaintiff Timothy E. Petticrew (hereinafter plaintiff) had in the course of his employment as a welder. On the day in question, plaintiff was working atop scaffolding inside a kiln owned by defendant St. Lawrence Cement, Inc. when he fell, fracturing his leg and ankle. Supreme Court (McNamara, J.) granted plaintiff and his wife, derivatively, summary judgment on their
To recover under
The kiln in which plaintiff was working was a cylinder, 17 feet in diameter, and a “spider” had been erected on the inside so as to maintain the kiln‘s structural integrity during repair work. A spider is composed of steel beams arranged in the form of an asterisk and welded to the inside of the kiln at eight equidistant points, described by the parties with reference to positions on the face of a clock. The beams are also welded at the centerpoint and reinforced by a metal plate. At the time of his injury, plaintiff was in the process of dismantling the entire spider, which required him to stand on an eight- to nine-foot high scaffolding to permit him to cut each beam with a torch. He removed each beam in pieces, beginning at the ceiling and moving towards the center plate. Plaintiff testified at his deposition that, prior to beginning his work, he tied off his harness and lanyard to a pad eye1 that was affixed to the 12 o‘clock beam, about a foot down from the kiln wall. According to him, he first removed the beams located at the 1 o‘clock and 3 o‘clock positions and then proceeded to cut the weld that attached the 12 o‘clock beam to the kiln wall, a mere foot from the pad eye securing his lanyard. He further testified that he then began to remove the 11 o‘clock beam and, as soon as he cut the weld that attached that beam to the kiln wall, the welds attaching the remaining beams failed and the spider collapsed, pulling him off the scaffolding to the floor of the kiln.
The only witness to the accident, plaintiff‘s coworker Edward Ulmer, related a drastically different version of events. Ulmer testified at his deposition that, just prior to the accident, all of the beams of the spider had been removed except those in the 11 o‘clock and 9 o‘clock positions. According to Ulmer, as plaintiff cut the weld in the 11 o‘clock position, the remains of
Given these discordant versions of events, there is an issue of fact as to whether the scaffolding collapsed or otherwise failed to support plaintiff in violation of
Next, while it is undisputed that plaintiff was wearing a safety harness with a lanyard at the time of the accident, a question of fact has been raised concerning whether a proper tie off point for the lanyard was provided. St. Lawrence‘s senior maintenance supervisor testified that, because welders change work areas frequently, they weld their own pad eyes to tie themselves off. Similarly, its maintenance manager and human resource safety representative testified that the welders working on the inside of a kiln are themselves responsible for attaching pad eyes as needed. Plaintiff himself did not dispute this point. Indeed, according to him, he could have made a pad eye from scrap material and could have attached it to the kiln wall free from the spider, but instead elected not to do so because a pad eye was already available on the spider itself. Notwithstanding, plaintiff submitted an expert affidavit that opined that it was St. Lawrence‘s duty to provide a proper fall protection system, such as a suspended steel cable or proper tie off points independent of the structure being removed. Thus, we find a question of fact as to whether St. Lawrence breached its duty pursuant to
Mercure, J.P., Rose, Kane and Malone Jr., JJ., concur. Ordered that the order is modified, on the law, without costs, by reversing so much thereof as granted plaintiffs’ motion for partial summary judgment; said motion denied; and, as so modified, affirmed. Ordered that the judgment is reversed, on the law, without costs.