OGLALA SIOUX TRIBE v. U.S. NUCLEAR REGULATORY COMMISSION AND UNITED STATES OF AMERICA
No. 17-1059
United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT
Decided July 20, 2018
Argued March 20, 2018
POWERTECH (USA), INC., INTERVENOR
On Petition for Review of an Order of the United States Nuclear Regulatory Commission
Jeffrey C. Parsons argued the cause for petitioner. With him on the briefs was Travis Stills. Roger Flynn entered an appearance.
James E. Adler, Senior Attorney, U.S. Nuclear Regulatory Commission, argued the cause for respondents. With him on the brief were Jeffrey H. Wood, Acting Assistant Attorney General, U.S. Department of Justice, Eric Grant, Deputy Assistant Attorney General, Lane N. McFadden, Attorney, and Andrew P. Averbach, Solicitor, U.S. Nuclear Regulatory Commission.
Christopher S. Pugsley argued the cause for intervenor-respondent. With him on the brief was Anthony J. Thompson.
Before: GARLAND, Chief Judge, and HENDERSON and GRIFFITH, Circuit Judges.
Opinion for the Court filed by Chief Judge GARLAND.
On administrative appeal, the Commission decided to leave the license in effect -- notwithstanding its own determination that
The National Environmental Policy Act, however, obligates every federal agency to prepare an adequate environmental impact statement before taking any major action, which includes issuing a uranium mining license. The statute does not permit an agency to act first and comply later. Nor does it permit an agency to condition performance of its obligation on a showing of irreparable harm. There is no such exception in the statute.
In fact, such a policy puts the Tribe in a classic Catch-22. In order to require the agency to complete an adequate survey of the project site before granting a license, the Tribe must show that construction at the site would cause irreparable harm to cultural or historical resources. But without an adequate survey of the cultural and historical resources at the site, such a showing may well be impossible. Of course, if the project does go forward and such resources are damaged, the Tribe will then be able to show irreparable harm. By then, however, it will be too late.
The Commission‘s decision to let the mining project proceed violates the National Environmental Policy Act. Indeed, it vitiates the requirements of the Act. We therefore find the decision contrary to law and grant the petition for review in part. The Tribe also challenges other aspects of the Commission‘s order but, as we explain, we lack jurisdiction to consider those rulings.
I
The Atomic Energy Act,
The licensing process involves three relevant components of the NRC.
The first is the Commission Staff, which is responsible for reviewing a license application, analyzing the environmental effects and other features of the proposed project, and issuing an initial decision approving or denying the application.
The second is an Atomic Safety and Licensing Board (ASLB), a panel that can be designated to preside over a licensing hearing, at which the Board hears contentions from intervenors and then issues an initial decision on those contentions.
Third is the Commission itself. Once the Board issues an initial decision on the contentions before it, parties can seek review from the Commission.
In 2009, Powertech applied for an NRC license authorizing it to “construct and operate” a uranium mining project, called the “Dewey-Burdock project,” in the southwest corner of South Dakota. NRC, Record of Decision for the Dewey-Burdock Uranium In-Situ Recovery Project at 1 (2014) (“Record of Decision“) (J.A. 738). The NRC described the project as follows:
The proposed facility will encompass approximately . . . 10,580 acres[,] which consists of two contiguous mining units . . . Powertech intends to recover uranium and produce yellowcake at the Dewey-Burdock site. Powertech‘s proposed activities include construction, operation, aquifer restoration, and decommissioning of its ISR facility. In addition, Powertech has proposed that liquid wastewater generated during uranium recovery be disposed of through one of the following methods: (i) deep well disposal via Class V injection wells, (ii) land application, or (iii) a combination of deep well disposal and land application.
Id. at 1-2 (J.A. 738-39).1 The NRC‘s chief administrative judge established an Atomic Safety and Licensing Board to preside over Powertech‘s licensing proceeding.
The petitioner here, the Oglala Sioux Tribe, intervened to challenge Powertech‘s application. The Tribe‘s Pine Ridge Reservation is located roughly fifty miles from the project site, Powertech USA, Inc., 81 N.R.C. 618, 656 (2015) (“ASLB Initial Decision“) (J.A. 455), and the project lands are within the Tribe‘s traditional territory, see Trina Lone Hill Decl. ¶ 5. A sizable number of cultural, historical, and archaeological sites have already been identified in the project area, including burial sites. EIS for Dewey-Burdock Project, NUREG-1910 at 4-159 to -182 (Jan. 2014) (“EIS“) (J.A. 655-78). The Tribe also owns lands near the proposed project, which it has “leased for domestic, agricultural, water development, conservation, and other purposes.” Oglala Br. 4. The Tribe‘s primary concerns regarding the project are protecting the Tribe‘s cultural and historical resources, as well as protecting groundwater from mining contamination. Id.
While the Board set the stage for the Powertech hearing, the Commission Staff drew up environmental documents for the Dewey-Burdock project, including an EIS, which it published in 2014. See EIS, NUREG-1910 (J.A. 567-737).2 After publishing the EIS, the Staff granted Powertech‘s
The Tribe promptly moved to stay the license. Without assessing the merits of the Tribe‘s contentions, the Board denied
the stay. It did so on the ground, inter alia, that the Tribe‘s allegations “lack[ed] the specificity needed to demonstrate a serious, immediate, and irreparable harm to cultural and historic resources.” Order, Powertech USA, Inc., No. 40-9075-MLA at 6 (May 20, 2014) (“ASLB Stay Denial Order“) (J.A. 516).
After denying the stay, the Board held a hearing on the merits of the contentions pending before it. The Board ruled against the Tribe, and in favor of the Staff and Powertech, on the bulk of those contentions.3 However, on two of the Tribe‘s contentions, Contentions 1A and 1B, the Board ruled in favor of the Tribe. ASLB Initial Decision, 81 N.R.C. at 708-10 (J.A. 507-09).
In Contention 1A, which is most significant for our purposes, the Tribe charged that the EIS did not satisfy NEPA because it failed to adequately address the environmental effects of the Dewey-Burdock project on Native American cultural, religious, and historical resources. The Board agreed with this charge, finding that:
[T]he [EIS] in this proceeding does not contain an analysis of the impacts of the project on the cultural, historical, and religious sites of the Oglala Sioux Tribe
and the majority of the other consulting Native American tribes. . . . Because the cultural, historical, and religious sites of the Oglala Sioux Tribe have not been adequately catalogued, the [EIS] does not include mitigation measures sufficient to protect this Native American tribe‘s cultural, historical, and religious sites that may be affected by the Powertech project.
Accordingly, as to Contention 1A, the Board finds and concludes that the [EIS] has not adequately addressed the environmental effects of the Dewey-Burdock project on Native American cultural, religious, and historic resources. . . . NEPA‘s hard look requirement has not been satisfied.
Id. at 655 (citations omitted) (J.A. 454).
In Contention 1B, the Tribe charged that the NRC Staff had failed to fulfill its responsibilities regarding consultation with Native American tribes under the National Historic Preservation Act (NHPA),
Despite what the Board concluded was a “significant deficiency in the NRC Staff‘s NEPA review,” it did not suspend Powertech‘s previously issued license. Id. at 658 (J.A. 457). Instead, it retained jurisdiction and directed the Staff to cure “the deficiencies in Contentions 1A and 1B.” Id. In the interim, it said, the Tribe “may petition this Board for a stay of the license‘s effectiveness, as may be necessary to halt ground disturbing activities,” but only “if the . . . Tribe can identify specific
The action then moved to the Commission. The Tribe, the Staff, and Powertech all petitioned the Commission for review of the Board‘s decision. The Staff and Powertech challenged the Board‘s partial resolution of Contentions 1A and 1B in favor of the Tribe. With respect to those same contentions, the Tribe argued that NEPA and the National Historic Preservation Act “prohibit[ed] the Board from leaving [Powertech‘s] license in place,” given the project‘s inadequate environmental review. Powertech (USA), Inc., 84 N.R.C. 219, 245 (2016) (“NRC Order“) (J.A. 268). The Tribe also challenged the Board‘s rejection of its other contentions. Id. at 224-26 (J.A. 240-43).
The Commission generally upheld the Board‘s rulings. Id. It left in place the findings that the Staff had failed to comply with NEPA and the National Historic Preservation Act. See id. at 248 (J.A. 272). Nonetheless, it affirmed the Board‘s decision to leave the license in effect because the Tribe “has not articulated any harm or prejudice” from the Staff‘s failure. Id. at 245 (J.A. 268). The Commission then directed that the proceeding “remain open for the narrow purpose of resolving the deficiencies identified by the Board.” Id. at 262 (J.A. 292). And it denied the Tribe‘s other challenges. Id. at 229, 237, 253, 256, 262 (J.A. 246, 258, 279-80, 283, 291-92).
Commissioner Baran dissented on the point that is now at issue before us: the Commission‘s decision to leave Powertech‘s license in effect while the Staff attempted to resolve the deficiencies in its NEPA review. His dissent stated as follows:
[A] core requirement of NEPA is that an agency decisionmaker must consider an adequate environmental review before making a decision on a licensing action. If the Commission allows a Board to supplement and cure an inadequate NEPA document
after the agency has already made a licensing decision, then this fundamental purpose of NEPA is frustrated.
In this case, the Board found that the Staff‘s [EIS] did not meet the requirements of NEPA because the [EIS] was deficient with respect to the effects of the licensing action on Native American cultural, religious, and historic resources. Thus, the agency did not have an adequate environmental analysis at the time it decided whether to issue the license. In fact, the deficiencies in the NEPA analysis remain unaddressed today, and therefore the Staff still cannot make an adequately informed decision on whether to issue the license. The Staff‘s licensing decision was based on (and continues to rest on) an inadequate environmental review. As a result, the Staff has not complied with NEPA.
The Commission should suspend the license until the Staff has . . . demonstrat[ed] that the [EIS] complies with NEPA . . . .
Id. at 269 (Commissioner Baran, dissenting in part) (citations omitted) (J.A. 301-02).
Thereafter, the Tribe filed a petition in this court for review of the Commission‘s order. Its principal challenge is to the NRC‘s decision to leave the license in effect pending the Staff‘s effort to cure the NEPA deficiencies. The Tribe also challenges the disposition of its other contentions, which are set out in footnote 3, supra.
II
We begin with our jurisdiction.
A
Under the Hobbs Act, this court has jurisdiction to review “final orders” of the Commission.
Applying this standard, we conclude that the Commission‘s order, as a whole, is not final. It did not consummate the agency‘s decisionmaking process as to all issues, but instead left the proceeding “open” while the Staff attempted to resolve the deficiencies in NEPA compliance (Contention 1A) and in the National Historic Preservation Act consultation process (Contention 1B). NRC Order, 84 N.R.C. at 262 (J.A. 292).
In keeping with this instruction, the Atomic Safety and Licensing Board has continued to oversee the Staff‘s efforts to cure the statutory deficiencies. In October 2017, the Board granted the Staff‘s motion for summary disposition regarding Contention 1B, concluding that the Staff‘s consultation efforts over the intervening two years had satisfied the National Historic Preservation Act. Powertech USA, Inc., 86 N.R.C. 167, 173 (2017) (“ASLB Summary Disposition Order“). But the Board denied the Staff‘s motion to dismiss the Tribe‘s NEPA
contention (Contention 1A), and the adjudication of that contention remains pending. Id. at 173-74. The Board order set a schedule contemplating resolution of the outstanding NEPA contention on or before October 12, 2018, id. at 210, but the Board has since suspended that schedule without imposing a new end date, see Order Suspending Scheduled Dates, Powertech USA, Inc., No. 40-9075-MLA at 2-3 (Apr. 12, 2018).
Because the Commission‘s order did not end the agency proceeding as to all issues, we do not have jurisdiction to review the bulk of the rulings challenged by the Tribe.
B
We do have jurisdiction, however, to review one of the rulings contained in the NRC order: the decision to leave the license in effect -- notwithstanding the NRC‘s determination that the agency is not in compliance with NEPA -- pending further proceedings before the Atomic Safety and Licensing Board.4 That ruling falls within the collateral order doctrine.5
Pursuant to
To effectuate that admonition, the Court has limited appealable collateral rulings to a “small category [that] includes only decisions [1] that are conclusive, [2] that resolve important questions separate from the merits, and [3] that are effectively unreviewable on appeal from the final judgment in the underlying action.” Id. (quoting Swint v. Chambers Cty. Comm‘n, 514 U.S. 35, 42 (1995)). Applying these conditions, we conclude that the ruling before us, which expressly permits a license to go forward despite the agency‘s acknowledgment
that it has not complied with NEPA, is a reviewable collateral order.
First, that ruling is “a fully consummated decision . . . that conclusively and finally determine[s]” the effectiveness of Powertech‘s license for the foreseeable future. See CalPortland Co., 839 F.3d at 1160 (internal quotation marks omitted). More important, it conclusively determines the Commission‘s interpretation of what NEPA requires in this circumstance. The Commission has decided that a license can remain effective and that construction can go forward -- despite the agency‘s failure to satisfy the requirements of NEPA -- unless the Tribe can show irreparable harm from leaving the license in place while the NEPA violation is cured. There is “no basis to suppose that the [Commission] contemplate[s] any reconsideration of [the] decision,” id. (internal quotation marks omitted), to permit such a license to remain effective unless irreparable harm can be shown. See NRC Br. 33 (stating that the Tribe can seek a stay only if a “new development [arises] that could potentially support an irreparable harm demonstration“). To the contrary, the “irreparable harm” standard appears to be the agency‘s settled practice. See infra Part III.A.
Second, the order resolves an “important question[] separate from the merits,” Mohawk Indus., 558 U.S. at 106 (quoting Swint, 514 U.S. at 42). Powertech now has the right to an effective license, despite an ongoing NEPA violation that the agency acknowledges. The Commission‘s irreparable harm standard for vacating the license pending the conclusion of its administrative adjudication has no bearing on its ultimate resolution of the merits of the Tribe‘s multiple contentions, including whether NEPA actually has been (or subsequently will be) satisfied. And the Commission‘s resolution of the merits of those questions will not address the validity of that standard.
Third, the ruling that permits projects to go forward despite “significant” NEPA violations will be effectively unreviewable
In evaluating this third condition, the Supreme Court has said that “the decisive consideration is whether delaying review until the entry of final judgment would imperil a substantial public interest or some particular value of a high order.” Mohawk Indus., 558 U.S. at 107 (internal quotation marks omitted). We know that the environmental values protected by NEPA are of a high order -- because Congress has told us so.6 We likewise know (as discussed in Part III.A below) that Congress has directed that, to protect those values, “all agencies
of the Federal Government” must prepare an environmental impact statement that satisfies NEPA before taking an action like granting Powertech‘s license.
Finally, in making the collateral order determination, the Court has instructed that we “not engage in an individualized jurisdictional inquiry,” but rather focus on “the entire category to which a claim belongs.” Mohawk Indus., 558 U.S. at 107 (internal quotation marks omitted). “[T]he chance that the litigation at hand might be speeded, or a particular injustic[e] averted, does not provide a basis for . . . jurisdiction.” Id. (internal quotation marks omitted). Our conclusion in this case is in accord with that direction as well. Here, we focus not only on the Tribe‘s challenge to the effectiveness of Powertech‘s license, but rather on the entire category of claims that challenge (and will challenge) NRC‘s legal position that it may leave a license in full effect despite the agency‘s failure to comply with NEPA.
We therefore have jurisdiction to consider whether the NRC may authorize a licensee to go ahead with construction -- notwithstanding the Commission‘s conclusion that there has
been a significant deficiency
III
Our review of this matter is governed by the Administrative Procedure Act (APA),
A
NEPA requires that “all agencies of the Federal Government shall . . . include in every recommendation or report on proposals for . . . major Federal actions significantly affecting the quality of the human environment, a detailed statement by the responsible official” on:
(i) the environmental impact of the proposed action,
(ii) any adverse environmental effects which cannot be avoided should the proposal be implemented,
(iii) alternatives to the proposed action,
(iv) the relationship between local short-term uses of man‘s environment and the maintenance and enhancement of long-term productivity, and
(v) any irreversible and irretrievable commitments of resources which would be involved in the proposed action should it be implemented.
This statutory provision requires agencies to take a “hard look” at environmental consequences before undertaking any such action. Robertson, 490 U.S. at 350. The environmental effects that must be assessed include “aesthetic, historic, cultural, economic, social, or health” effects.
analysis of significant problems and objections raised by . . . any affected Indian Tribes.”
The Atomic Safety and Licensing Board ruled that, to “fulfill the agency‘s NEPA responsibilities to protect and preserve
The Board did not find just a technical violation of NEPA. Rather, it found that “the inadequate discussion of potential impacts to Sioux cultural, historical, or religious sites in the [EIS] or Record of Decision is a significant deficiency in the NRC Staff‘s NEPA review.” Id. at 658 (emphasis added) (J.A. 457). And the Commission did not disagree. Refusing to “second guess the Board‘s fact-finding,” the Commission declined to set aside the Board‘s order and denied the Staff‘s petition for review with respect to the Tribe‘s NEPA contention. NRC Order, 84 N.R.C. at 248 (J.A. 272-73).
For purposes of our review, we accept the Board‘s finding -- undisturbed by the Commission -- that the agency did not fulfill its NEPA responsibilities. We do not review the merits of that conclusion.
Notwithstanding the Board‘s finding, and in particular its acknowledgment that the Staff “must conduct a study or survey of tribal cultural resources before granting a license” in order to fulfill the agency‘s NEPA responsibilities, ASLB Initial Decision, 81 N.R.C. at 653 (emphasis added) (J.A. 452), the Board ruled that it would not suspend Powertech‘s license unless the Tribe sought a stay within ten days and showed that “specific cultural, historic, or religious sites . . . are subject to immediate and irreparable harm.” Id. at 658 (J.A. 457). The Commission likewise refused to vacate the license on the ground that more than just a NEPA violation was required, stating that there was no need to disturb the license because the “Tribe ha[d] not articulated any harm or prejudice.” NRC Order, 84 N.R.C. at 245 (J.A. 268).
The agency thus conditioned enforcement of NEPA on a showing of irreparable harm by the Tribe.8 It did so even though, as Commissioner Baran explained in dissent, the agency lacked an adequate environmental analysis when it first issued the license and the significant NEPA deficiencies identified by the Board “remain[ed] unaddressed” at the time of the
Commission‘s decision. Id. at 269 (Commissioner Baran, dissenting in part) (J.A. 301). Therefore “[t]he Staff‘s licensing decision was based on (and continues to rest on) an inadequate environmental review.” Id.
The agency‘s decision in this case and its apparent practice are contrary to NEPA. The statute‘s requirement that a detailed environmental impact statement be made for a “proposed” action makes clear that agencies must take the required hard look before taking that action. See, e.g., Pub. Emps. for Envtl. Responsibility v. Hopper, 827 F.3d 1077, 1081 (D.C. Cir. 2016) (holding that an agency‘s decision to issue a lease for a windpower project “without first obtaining sufficient site-specific data violated” NEPA (internal quotation marks omitted)); New York, 681 F.3d at 476 (“Under NEPA, each federal agency must prepare an [EIS] before taking a ‘major Federal action[] significantly affecting the quality of the human environment.‘” (quoting
The nontextual exception upon which the NRC insists would vitiate the statute‘s “‘action-forcing’ purpose.” Robertson, 490 U.S. at 349. As the Court explained in Robertson:
The statutory requirement that a federal agency contemplating a major action prepare such an environmental impact statement serves NEPA‘s “action-forcing” purpose in two important respects.... It ensures that the agency, in reaching its decision, will have available, and will carefully consider, detailed information concerning significant environmental impacts; it also guarantees that the relevant information will be made available to the larger audience that may also play a role in both the decisionmaking process and the implementation of that decision.
id. (emphasis added); see Baltimore Gas & Electric Co. v. Nat. Res. Def. Council, 462 U.S. 87, 97 (1983). If an agency fails to complete the required review before authorizing a proposed project -- whether or not a party is able to present evidence of harm at that stage -- it runs the risk “that important effects will... be overlooked or underestimated only to be discovered after... the die [has been] cast.” Robertson, 490 U.S. at 349; see Winter v. Nat. Res. Def. Council, 555 U.S. 7, 23 (2008); Ill. Commerce Comm‘n v. ICC, 848 F.2d 1246, 1259 (D.C. Cir. 1988).
Indeed, the nature of the agency action in this case puts the problem in high relief. As we have noted, the Tribe “has shown it has the most direct historical, cultural, and religious ties to the [Dewey-Burdock project] area.” ASLB Initial Decision, 81 N.R.C. at 656 (J.A. 455). A significant number of cultural, historical, and archaeological sites have already been identified in the project area, including burial sites. EIS, NUREG-1910 at 4-159 to -182 (J.A. 655-78). The Tribe is concerned that mining, as well as the construction and other land disturbances that precede mining, will damage those resources. See Trina Lone Hill Decl. ¶¶ 5, 28. The purpose of an EIS is, in part, to determine whether the land contains such resources and where they are located, so that damage to them can be avoided or mitigated. If the project is permitted to go forward without the necessary land survey, such damage may well be done.
In short, the NRC has placed the Tribe in a classic Catch-22. It must show irreparable harm to insist that an adequate survey be completed. But it likely cannot show even the risk of such harm unless that survey is completed. Of course, if the project goes forward and the burial or other sites are damaged, the Tribe will then be able to show irreparable harm -- but by then, it will be too late to stop it.
The NRC‘s conduct in this case may be compared -- unfavorably -- to that of the Interstate Commerce Commission in Illinois Commerce Commission v. ICC, 848 F.2d 1246. There, the court declined to remand the agency‘s policy of publishing an environmental assessment after publishing notice of proposed abandonment of a railroad line. But it did so only because the agency represented that, if environmental issues were raised, a stay would “automatically be granted until the concerns are resolved by the [agency],” with “no showing of irreparable harm or probability of success . required.” Id. at 1260. That procedure, we said, “obviate[d] the possibility that an abandonment would be authorized even though environmental questions were still outstanding.” Id. Needless to say, that procedure -- providing for an automatic stay without the need to show irreparable harm -- stands in stark contrast to the approach the Commission employed here. And for the reasons we have stated, the latter is contrary to law.
B
In this subpart, we address the NRC‘s defense of its ruling.
1. The justification upon which the Commission relied in its order was an analogy to this court‘s treatment of “harmless error” when reviewing an agency decision. NRC Order, 84 N.R.C. at 245 (J.A. 268) (“[F]ederal courts have required that parties demonstrate harm or prejudice to disturb an agency‘s decision.“). The analogy is inapt.
The “harmless error” doctrine that this court applies is compelled by a statute, the Administrative Procedure Act, which provides that “due account shall be taken of the rule of prejudicial error,”
But whether or not that ends the argument -- a question we do not need to decide -- what the agency has done here looks nothing like the harmless error review undertaken by this court.
First, it is true that “[w]e have applied the prejudicial error rule in the NEPA context where the proposing agency engaged in significant environmental analysis before reaching a decision but failed to comply precisely with NEPA procedures.” Nevada v. Dep‘t of Energy, 457 F.3d 78, 90 (D.C. Cir. 2006) (emphasis added); see, e.g., Int‘l Bhd. of Teamsters v. U.S. Dep‘t of Transp., 724 F.3d 206, 217 (D.C. Cir. 2013) (holding that any “technical error” in the timing of the release of an environmental assessment was harmless when the agency completed the assessment “before authorizing any” operations). But the error here was neither a failure of precision nor a technicality. Rather, as the Board itself said, it was a “significant deficiency” in the Staff‘s NEPA review. ASLB Initial Decision, 81 N.R.C. at 658 (J.A. 457).10
The Commission‘s order disparaged this error as merely “procedural.” NRC Order, 84 N.R.C. at 245 (J.A. 268); see NRC Br. 34, 35. But “NEPA imposes only procedural requirements.” Winter, 555 U.S. at 23. If even “significant” deficiencies in NEPA reviews are forgiven because they are merely procedural, there will be nothing left to the protections that Congress intended the Act to provide. Moreover, in a comparable situation, “[w]e have not been hospitable to government claims of harmless error in cases in which the government violated [the procedural requirement of APA]
Given the significant deficiency at issue in this case, the harmless error doctrine cannot justify the agency‘s ruling. As we have noted, the Board found that the EIS “does not contain an analysis of the impacts of the project on the cultural, historical, and religious sites of the Oglala Sioux Tribe and the majority of the other consulting Native American tribes.” ASLB Initial Decision, 81 N.R.C. at 655 (J.A. 454). As a consequence, “the EIS does not include mitigation measures sufficient to protect this Native American tribe‘s cultural, historical, and religious sites that may be affected by the Powertech project.” Id. That assessment of the risks to the Tribe‘s sites is consistent with the Commission‘s generic EIS for these kinds of mining projects: “[D]epending on local conditions,” the agency has explained, ISL facility construction can cause a “large” impact on “ecological, historical, or cultural resources” because of the “potential for unidentified resources to be altered or destroyed during excavation, drilling, and grading.” Generic EIS for In-Situ Leach Uranium Milling Facilities, NUREG-1910 at xlii (May 2009) (J.A. 531).
In this context, the agency may not properly conclude that its failure to comply with NEPA is harmless simply because the Tribe cannot point to specific historical sites that are at risk. Indeed, placing the burden on the Tribe to show harm was
Second, the point at issue here is not simply forgiveness of a single error. As we have explained, it appears to be the NRC‘s settled practice to keep licenses in effect, notwithstanding significant NEPA deficiencies, unless an intervenor shows irreparable harm. See supra Part III.A. That does not represent the application of a harmless error exception to a statutory violation. It represents a wholesale rewrite of NEPA.
Third, the standard of review the Commission approved is not just a “harmless” error standard -- it is an “irreparable harm” standard. See supra note 8. The harmless error standard of the APA merely requires a showing of prejudice. That standard does not “impose a . . . particularly onerous requirement.” Shinseki v. Sanders, 556 U.S. 396, 410 (2009); see Jicarilla Apache Nation v. U.S. Dep‘t of Interior, 613 F.3d 1112, 1121 (D.C. Cir. 2010) (“If prejudice is obvious to the court, the party challenging agency action need not demonstrate anything further.“).
The irreparable harm standard applied by the Board, in contrast, derives from the standard courts must apply in granting injunctive relief. See Monsanto Co. v. Geertson Seed Farms, 561 U.S. 139, 156-57 (2010); Winter, 555 U.S. at 20, 22. It is not the standard for the “less drastic” APA remedy of vacatur, see Monsanto, 561 U.S. at 165-66, nor is it the standard applied under the APA‘s harmless error provision, see Shinseki, 556 U.S. at 410. Rather, it requires a substantially higher showing. See Chaplaincy of Full Gospel Churches v. England, 454 F.3d 290, 297-98 (D.C. Cir. 2006). Here, it requires a well-nigh impossible one. How, after all, can the Tribe show that Powertech‘s project will irreparably damage its cultural artifacts if there has not been a survey adequate to determine where those artifacts are located?
2. NRC counsel -- but not the Commission itself -- also analogize the Commission‘s treatment of the erroneous Staff decision to the analysis this court applies when considering whether to vacate or merely remand erroneous agency actions. NRC Br. 34-39. As counsel correctly note, “[t]his Court has long held when considering remedies under
Because the NRC order appealed here does not rely upon this reasoning, see NRC Order, 84 N.R.C. at 245 (J.A. 268), neither can we. SEC v. Chenery Corp., 318 U.S. 80, 87-88 (1943) (“The grounds upon which an administrative order must be judged are those upon which the record discloses that its action was based.“); see NLRB v. CNN Am., Inc., 865 F.3d 740, 751 (D.C. Cir. 2017). In any event, this argument-by-analogy has flaws that are similar to those of
As is true of this court‘s “harmless error” analysis, our remand practice is informed by the APA. Compare
Without resolving whether the absence of statutory authority is sufficient to reject the analogy to judicial remand-without-vacatur, what the agency has done here does not mirror the court‘s decisionmaking process in that regard.
As the above quotation from Allied-Signal indicates, in deciding whether vacatur is required, we first consider the “seriousness of the order‘s deficiencies.” 988 F.2d at 150. Here, the NRC acknowledged a “significant deficiency in the NRC Staff‘s NEPA review.” ASLB Initial Decision, 81 N.R.C. at 658 (J.A. 457). It nonetheless left the license in place, in part because it regarded the failure to comply with NEPA as merely a “procedural deficienc[y].” NRC Br. 34; see id. at 37. But as we have just underlined, NEPA is a purely procedural statute and taking such an approach would vitiate it. Nor is it true, as counsel claim, that this court routinely remands (without vacatur) violations of procedural requirements. See NRC Br. 37. To the contrary, in the comparable circumstance of the APA‘s procedural requirements, we have held that “deficient notice is a ‘fundamental flaw’ that almost always requires vacatur.” Allina Health Servs., 746 F.3d at 1110 (quoting Heartland Reg‘l Med. Ctr. v. Sebelius, 566 F.3d 193, 199 (D.C. Cir. 2009)).
The seriousness of the NEPA deficiency is particularly clear here because the point of NEPA is to require an adequate EIS before a project goes forward, so that construction does not begin without knowledge of the affected cultural and historical sites. “Part of the harm NEPA attempts to prevent in requiring an EIS is that, without one, there may be little if any information about prospective environmental harms and potential mitigating measures.” Winter, 555 U.S. at 23 (emphasis added). As the ASLB acknowledged, “[b]ecause the cultural, historical, and religious sites of the Oglala Sioux Tribe have not been adequately catalogued, the [EIS] does not include mitigation measures sufficient to protect this Native American tribe‘s cultural, historical, and religious sites that may be affected by the Powertech project.” ASLB Initial Decision, 81 N.R.C. at 655 (J.A. 454). Indeed, even when we have remanded without vacatur, we have considered this kind of concern and conditioned the remand accordingly. Cf. Pub. Emps. for Envtl. Responsibility, 827 F.3d at 1084 (declining to vacate a windpower project owner‘s lease for a deficient EIS, but vacating the agency‘s impact statement and requiring it “to supplement [the impact statement] with adequate geological surveys before [the project] may begin construction“). The Commission did not do that here.11
Finally, once again the issue here is not just what to do about a single agency error, but what to do about the validity of an NRC practice that permits NEPA-deficient licenses to remain in place unless an intervenor can show irreparable harm. We have never turned merely to a remand remedy when an agency refused to adhere to a statutory command in such an across-the-board fashion.
validity, which reaffirms the wisdom of adhering to Chenery‘s rule that the soundness of an agency‘s decision must rest on the reasoning contained therein, and not on any post hoc justifications offered by counsel. Chenery Corp., 318 U.S. at 87-88; see NLRB v. CNN Am., Inc., 865 F.3d at 751.
3. NRC counsel make two further arguments that are also not reflected in the Commission‘s order. Even if they were meritorious, Chenery would render them insufficient to uphold the order.
First, NRC counsel maintain that the ASLB‘s decision to leave the license in place was justified because it was “based in part on the Tribe‘s own actions making the NHPA consultation process unnecessarily difficult.” NRC Br. 35. But the Commission‘s order did not rely on this justification and instead noted that “the Board acknowledged that it could not definitively determine whether the Staff or the Tribe bore responsibility for what the Board considered a breakdown in consultation.” NRC Order, 84 N.R.C. at 244 (J.A. 266-67).
Second, counsel argue that the agency‘s “adjudicatory hearing process, which led to the identification of deficiencies in NRC‘s compliance with NEPA . . ., did not arise from th[at] statute[], but, rather, from the Atomic Energy Act.” NRC Br. 38. Whether the Commission could have delegated to its Staff the final authority to resolve NEPA issues without appeal to the Commission is a question that we need not answer today. The fact is that the Commission did not do so, and thus must explain why it permitted the project to go forward despite its own determination that the Staff had failed to comply with NEPA. As we have explained, the Commission has failed to offer a justification that is consistent with its statutory responsibility.
C
To be clear, today we hold only that, once the NRC determines there is a significant deficiency in its NEPA compliance, it may not permit a project to continue in a manner that puts at risk the values NEPA protects simply because no intervenor can show irreparable harm. We do not decide that the Commission may never leave in place a license that its Staff previously issued but that the Commission later finds NEPA-deficient. That is, we do not decide that there is no version of a harmless error rule that the Commission may apply. Nor do we decide that there are no protective conditions the Commission might impose that would justify leaving a license in place during an administrative remand intended to cure a NEPA deficiency. Cf. Pub. Utils. Comm‘n v. FERC, 900 F.2d 269, 282 (D.C. Cir. 1990) (holding that NEPA did not preclude FERC from issuing an approval that was “expressly not to be effective until [an] environmental hearing was completed“).
Regardless of whether one of those options might pass muster, the Commission did not follow such a course here.
IV
Because the standard that the Commission applied in permitting Powertech‘s license to remain in effect is inconsistent with NEPA, we remand this matter to the agency for further consideration consistent with this opinion. We do not, however, vacate the agency‘s ruling. As we recounted above, an appellate court‘s decision regarding whether to vacate or merely remand “depends on the seriousness of the order‘s deficiencies (and thus the extent of doubt whether the agency chose correctly) and the disruptive consequences of an interim change that may itself be changed.” Allied-Signal, 988 F.2d at 150-51 (internal quotation marks omitted).
We have no doubt about the seriousness of the order‘s deficiencies. But we have not been given any reason to expect that the agency will be unable to correct those deficiencies, and we are concerned about the disruptive consequences of vacating the license while the agency proceeds to satisfy NEPA. Powertech reasonably relied on the NRC‘s ruling and settled practice that permitted the continued effectiveness of the license the Staff issued. And it has represented to the court that its stock price “would plummet” if the license were “suspended, vacated, or revoked.” Oral Arg. Tr. 30.
More important, it appears that the Tribe will not suffer harm -- irreparable or otherwise -- from a disposition that leaves the license in effect for now. Powertech has further represented that a South Dakota permitting requirement independently bars it from moving forward with construction on the site until the NRC completes its compliance with NEPA. Oral Arg. Tr. 32-35. We note that the Tribe doubts this representation. Id. at 37. But for now, we rely on it. If the representation turns out not to be correct, the Tribe will have grounds to seek further redress from this court. Cf. Pub. Emps. for Envtl. Responsibility, 827 F.3d at 1084 (requiring the agency “to supplement [the impact statement] with adequate geological surveys before [the project] may begin construction“).
V
The Nuclear Regulatory Commission‘s December 2016 order is not entirely final, and as a consequence we do not have jurisdiction over the bulk of the rulings challenged by the Oglala Sioux Tribe. Under the collateral order doctrine, however, we do have jurisdiction to review the Commission‘s decision to leave Powertech‘s license in place -- notwithstanding the
So ordered.
Notes
Record of Decision at 2 (J.A. 739).[A]n oxidant-charged solution, called a lixiviant, will be injected into the production zone aquifer (uranium orebody) through injection wells. . . . As the lixiviant circulates through the production zone, it will oxidize and dissolve the mineralized uranium . . . . The resulting uranium-rich solution will be drawn to recovery wells by pumping and then transferred to a processing facility via a network of underground pipelines. At the processing facility, the uranium will be removed from solution via ion exchange.
