NEWMONT U.S.A. LIMITED, formerly known as NEWMONT MINING CORPORATION, and N.I. LIMITED, Plaintiffs-Counter-Claim-Defendants-Appellants-Cross-Appellees, v. INSURANCE COMPANY OF NORTH AMERICA, Defendant-Counter-Claimant-Appellee-Cross-Appellant.
Nos. 08-1347 and 08-1370
United States Court of Appeals, Tenth Circuit
August 11, 2010
Before TACHA, ALARCÓN, and TYMKOVICH, Circuit Judges.
PUBLISH. APPEAL FROM THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLORADO (D.C. NO. 1:06-CV-1178-ZLW-BNB)
Lloyd A. Gura, Mound Cotton Wollan & Greengrass, New York, New York (Matthew J. Lasky, Mound Cotton Wollan & Greengrass, New York, New York and Andrew D. Ringel, Hall & Evans, Denver, Colorado with him on the briefs) for Defendant-Counter-Claimant-Appellee-Cross Appellant.
In this insurance matter, Newmont U.S.A. Limited (Newmont), f/k/a Newmont Mining Corporation, and N.I. Limited (NIL) brought suit against the Insurance Company of North America (INA). Newmont sought a declaratory judgment that NIL was no longer liable to INA for reinsurance arising out of policies INA had issued to Newmont, and an injunction barring INA from proceeding to arbitrate the companies’ disputes. The district court compelled arbitration and the arbitration panel found in INA‘s favor, awarding money damages. The district court subsequently modified the portion of the arbitration panel‘s award concerning post-judgment interest, and entered final judgment.
On appeal, Newmont and NIL argue the district court erred by compelling arbitration. In a cross-appeal, INA contends the district court erred by altering the arbitration panel‘s post-judgment interest rate determination and setting the post-judgment interest accrual date.
Our jurisdiction arises under
I. Background
During the early 1980s, INA issued general liability policies to Newmont, the parent corporation of NIL,1 and certain of its subsidiaries and affiliates. INA and NIL, in turn, entered into three successive reinsurance agreements under which NIL committed to reinsure INA with respect to the policies INA had issued to Newmont. The last effective date of the applicable Reinsurance Agreements was July 18, 1985.
For our purposes, the Reinsurance Agreements may be considered identical. Several provisions of the Agreements are relevant to our analysis of whether and when arbitration may be compelled. Article X of the Reinsurance Agreements provides: “As a condition precedent to any right of action hereunder, any dispute arising out of this Agreement shall be submitted to the decision of a board of arbitration . . . .” Aplt. App. at 22. And, Article XIII of the Reinsurance Agreements states: “Either party will pay to the other an interest charge at the monthly rate of . . . 1.5%[] on any amount that is not paid within the time required by this Agreement, said charge to commence at the time any such
In the early 1980s, the State of Colorado brought claims against two of Newmont‘s subsidiaries, the Idarado Mining Company and the Resurrection Mining Company. In response, Newmont filed a declaratory judgment action against INA in state court, seeking defense coverage and indemnity from INA under the general liability policies.
In 1997, INA and Newmont entered into a Settlement Agreement relating to the general liability policies. The Recitals section of the agreement states “this settlement resolves all claims of Newmont for insurance coverage for Idarado Environmental Claims” and “this settlement resolves only Newmont‘s claims arising from the Idarado mining site and does not settle or resolve Newmont‘s, or any other entity‘s, claims arising from the Resurrection mining site or any other site . . . .” Id. at 141-42. The 1997 Settlement Agreement also provides:
INA . . . release[s] [NIL] from all claims . . . relating to the Declaratory Judgment Action . . . , which claims arise from any . . . reinsurance contract with [NIL]. The foregoing to the contrary notwithstanding, this release shall not apply to (I) claims by INA against [NIL] for reinsurance coverage . . . , which claims are based on alleged occurrences at the California Gulch Mining Site [(i.e., the Resurrection Site)] or any other site other than the Idarado Mining Site . . . .
Id. at 147-48.
In 2002, INA and Newmont entered into another Settlement Agreement. The Recitals section of that agreement states “this settlement resolves all claims
INA . . . release[s] [NIL] . . . from all claims . . . relating to the Declaratory Judgment Action . . . , which arise . . . from any . . . reinsurance contract . . . of [NIL].
The foregoing to the contrary notwithstanding, this release shall not apply to (I) claims by INA against [NIL] for reinsurance coverage . . . , on account of alleged occurrences at any site other than the California Gulch Mining Site or the Idarado Mining Site . . . .2
Id. at 165-66.
Neither Settlement Agreement contains an arbitration provision. Both, however, contain merger clauses. And, both are to be construed according to Colorado law.
In 2000, BHP Copper, Inc., a former Newmont subsidiary, sued INA in state court, seeking coverage under the general liability policies for environmental liabilities at BHP‘s Pinal Creek Site (the BHP Litigation). INA drew upon a letter of credit from NIL in 2002 to reimburse itself for approximately $439,000 in costs it allegedly incurred defending the BHP Litigation. INA maintained it was due the money under the Reinsurance
In 2006, INA demanded, under Article X of the Reinsurance Agreements, the parties’ dispute over reimbursement be arbitrated. Newmont and NIL responded by filing an action in state court, which was subsequently removed to federal district court, seeking a declaratory judgment that the Settlement Agreements released NIL from reinsurance liability with respect to the BHP Litigation, an injunction barring INA from proceeding to arbitration, and money damages.3 The district court compelled arbitration.4
The arbitration panel issued a final award on December 21, 2007, finding for INA and against NIL in all material respects. The panel found in INA‘s favor with regard to reimbursement under the Reinsurance Agreements and, based on
The district court entered final judgment on September 19, 2008, nunc pro tunc June 5, 2008. Citing
Newmont and NIL appeal the district court‘s decision to compel arbitration, arguing that the Settlement Agreements released NIL from reinsurance and arbitration obligations existing under the Reinsurance Agreements. INA appeals the district court‘s rulings setting the post-judgment interest rate in accordance with
II. Discussion
The district court‘s granting of a motion to compel arbitration is reviewed de novo, see Riley Mfg. Co. v. Anchor Glass Container Corp., 157 F.3d 775, 779 (10th Cir. 1998), as is the district court‘s interpretation and application of
A. Arbitration
Newmont and NIL first challenge the district court‘s decision to compel arbitration. They contend the district court improperly determined the reimbursement issue is within the scope of the arbitration clause contained in the Reinsurance Agreements and that the clause survived the expiration of those contracts and the entry into force of the Settlement Agreements. We disagree.
Our cases hold unless the parties to an agreement “clearly and unmistakably” provide otherwise, “the question of arbitrability—whether a contract creates a duty for the parties to arbitrate the particular grievance—is undeniably an issue for judicial determination.” Id. (internal punctuation omitted). Here, we cannot conclude INA and Newmont clearly and unmistakably provided that an arbitration panel, rather than a court, decide issues of arbitrability relating to the Reinsurance Agreements. The agreements are completely silent on the issue. Given the lack of contractual guidance, we look to
Second, in deciding if a dispute is arbitrable, a court must initially determine whether the arbitration provision is broad or narrow. See Cummings v. FedEx Ground Package Sys., Inc., 404 F.3d 1258, 1261 (10th Cir. 2005). “Where the arbitration clause is broad, there arises a presumption of arbitrability and arbitration of even a collateral matter will be ordered if the claim alleged implicates issues of contract construction or the parties’ rights and obligations under it.” Id. (internal quotation marks omitted). Looking to the plain language of the arbitration provision contained in the Reinsurance Agreements, including its use of the phrase “arising out of,” we have little trouble determining that it is a broad provision.5 We find therefore the arbitration provision pertaining to the Reinsurance Agreements covers the parties’ dispute. In reaching this conclusion, we bear in mind that “any doubts concerning the scope of arbitrable issues should be resolved in favor of arbitration.” Moses H. Cone Mem‘l Hosp. v. Mercury Const. Corp., 460 U.S. 1, 24-25 (1983).
Here, the Settlement Agreements do not evidence the parties’ express or clearly implied intent to repudiate post-expiration arbitrability. An examination of the Settlement Agreements in their entirety reveals that they were intended to resolve claims relating to the Idarado and Resurrection sites only—claims concerning reinsurance coverage for the BHP Litigation were not released.6 Also, there can be no doubt that the parties’ dispute over the BHP Litigation “arose
The arbitration provision in the Reinsurance Agreements encompasses the parties’ dispute concerning the BHP Litigation and neither the Reinsurance Agreements’ expiration nor the Settlement Agreements extinguish arbitrability. Accordingly, the district court did not err in compelling arbitration.
B. Post-Judgment Interest Rate
INA contends the district court erred by altering the post-judgment interest rate provided in the arbitration panel‘s final award. The district court replaced the post-judgment interest rate the arbitration panel established with the rate set forth in
As discussed above, a broad arbitration clause gives rise to the presumption of arbitrability and arbitration of a collateral matter will be ordered if it implicates issues of contract construction or the parties’ contractual rights and obligations. See Cummings, 404 F.3d at 1261. Doubts about the arbitrability of
Here, as we have already determined, the arbitration provision contained in the Reinsurance Agreements is a broad provision. Also, because parties may set their own rate of post-judgment interest through contract, see Westinghouse Credit Corp. v. D‘Urso, 371 F.3d 96, 101 (2d Cir. 2004) (cited favorably in Reinhart, 402 F.3d at 1004), determining the rate of post-judgment interest to be applied to the money damages the arbitration panel awarded implicates Article XIII of the Reinsurance Agreements. Article XIII provides for an interest rate of 1.5 percent per month on any amount due under the Reinsurance Agreements. See 3 THOMAS H. OEHMKE, COMMERCIAL ARBITRATION § 124:2 (2010) (“Parties may ‘contract out’ of statutory interest rates if their agreement expresses the parties’
Neither
Because the post-judgment interest issue was arbitrable under the Reinsurance Agreements, the arbitration panel had the authority to determine the issue. The district court therefore erred by modifying the final award based on
C. Interest Accrual Date
The last issue involves the applicable date interest begins accruing. INA contends the district court erred by fixing June 5, 2008 as the date after which post-judgment interest should begin to accrue. We agree. In this case,
Section 1961 provides the statutorily determined post-judgment interest rate goes into effect on the date of the entry of judgment. See
The district court thus erred in identifying June 5, 2008 as the post-judgment interest accrual date. The district court should have identified
III. Conclusion
For the foregoing reasons, we find the district court rightly compelled arbitration, but erred by modifying the post-judgment interest rate and in setting the post-judgment interest accrual date. We AFFIRM in part and REVERSE in part.
