In April 2004, appellant DMA International, Inc. (“DMA”) entered into a contract to provide database research services to appellee Qwest Communications International, Inc. (“Qwest”). When the contract expired eight months later, Qwest refused to pay DMA’s final invoice, contending it had already paid DMA in full for its services. DMA accused Qwest of breaching their contract and submitted a demand for arbitration. 1 After the arbitrator ruled in favor of Qwest, DMA filed a motion in the district court to vacate the award under the Federal Arbitration Act (“FAA”). 9 U.S.C. § 10. The district court concluded that it had no basis to vacate the arbitrator’s award and granted a counter motion to confirm the award under 9 U.S.C. § 9. DMA appeals that decision. Exercising jurisdiction under 9 U.S.C. § 16(a) and 28 U.S.C. § 1291, we affirm.
I
The parties’ dispute centers on the contract’s fees provision, Section 4. 1, which states:
[F]ees for Services rendered hereunder are as follows:
... Twenty-five dollars and twenty cents ($25.20) per circuit satisfactorily completed. (Fee is based on an hourly rate of forty-five dollars ($45) with 1.8 circuits completed per hour).
DMA argues that this provision unambiguously provides for payments to be based on the number of circuits completed. Using this interpretation, DMA submitted a final invoice to Qwest seeking approximately $5.4 million for roughly 285,000 completed circuits. This invoice included a $1.7 million deduction, representing fees that Qwest had already paid to DMA. Qwest argues that the parties intended for DMA to be paid on an hourly basis, as reflected in the parenthetical portion of Section 4.1. It also claims that DMA knew from the outset that Qwest’s budget for DMA’s work under the contract was $1.7 million. Based on an hourly rate of forty- *1344 five dollars, Qwest contends that the $1.7 million it had already paid DMA satisfied its payment obligations.
After extensive briefing and an eleven-day arbitration hearing in which sixteen witnesses testified and 140 exhibits were admitted, the arbitrator concluded that the contract’s fees provision was ambiguous:
I can not [sic] determine from a reading of ... section 4.1 at what rate the parties intended that DMA be paid for its work. Was it to be paid per circuit or per hour? Consideration of other relevant portions of the contract only underscore the ambiguity.... When is a circuit “completed” and how does that relate to the work DMA was to perform as described at section 1.2 of the [Statement of Work]?
Accordingly, the arbitrator turned to extrinsic evidence to determine the parties’ intent. He ultimately concluded that the parties intended for DMA to be paid at the rate of forty-five dollars per hour. Based on this finding, the arbitrator ruled that Qwest had paid DMA in full and dismissed DMA’s breach of contract claim.
In the district court, DMA argued that vacatur was warranted because: (1) the award manifestly disregarded the law; (2) the arbitrator was partial or corrupt; (3) the award violated public policy; (4) the arbitrator exceeded his powers; and (5) Qwest did not dispute the final invoice within forty-five days of receipt. In rejecting each of these arguments, the district court based its ruling largely on the highly deferential standard of review applicable to arbitration awards.
See Hollern v. Wachovia Secs., Inc.,
II
In reviewing a district court’s confirmation of an arbitration award, we review factual findings for clear error and legal determinations de novo.
Sheldon v. Vermonty,
DMA’s principal argument on appeal is that the arbitrator’s award should be vacated because the arbitrator acted in manifest disregard for the law.
2
We have characterized the “manifest disregard” standard, however, as “willful inattentiveness to the governing law.”
Jenkins v. Prudential-Bache Sec. Inc.,
As the district court noted in its order, the arbitrator in the present case correctly stated the law governing contract interpretation in Colorado and applied it to the fees provision. Once the arbitrator found Section 4.1 was ambiguous, he appropriately considered extrinsic evidence.
See Fort Lyon Canal Co. v. High Plains A & M, LLC,
DMA also argues that vacatur is warranted because the arbitrator exceeded his power in issuing the award, the award violates public policy, and Qwest did not dispute DMA’s final invoice within forty-five days of receipt. 3 Because of our highly deferential standard of review, we reject these claims on the same basis as set forth in the district court’s order. We therefore affirm the district court’s judgment denying DMA’s motion to vacate and granting Qwest’s motion to confirm the award.
Ill
We turn now to Qwest’s motion for attorney fees under 28 U.S.C. § 1927. That provision states:
Any attorney or other person admitted to conduct cases in any court of the United States or any Territory thereof who so multiplies the proceedings in any case unreasonably and vexatiously may be required by the court to satisfy personally the excess costs, expenses, and attorneys’ fees reasonably incurred because of such conduct.
Federal Rule of Appellate Procedure 38 similarly empowers this court to “award just damages and single or double costs to the appellee” if we determine that an appeal is frivolous. DMA’s appeal in this case regrettably meets both of these standards and an award of attorney fees to Qwest is justified.
We do not take our decision to impose sanctions lightly. To the contrary, we recently took the opportunity to warn those spurned by an arbitration award that we will impose sanctions in appropriate cases.
See Lewis v. Circuit City Stores, Inc.,
*1346
We ultimately decided against imposing sanctions in
Lewis,
concluding that the losing arguments, though meritless, were nonetheless complex and not “completely frivolous.”
Id.
at 1154. But we quoted at length from the Eleventh Circuit’s decision in
B.L. Harbert International LLC v. Hercules Steel Co.,
The overriding issue in this case is nearly identical to the issue presented in B.L. Harbert. As described in the Eleventh Circuit’s opinion:
This is a typical contractual dispute in which the parties disagree about the meaning of terms of their agreement. There are arguments to be made on both sides of the contractual interpretation issue, and they were made to the arbitrator before being made to the district court and then to us. Even if we were convinced that we would have decided this contractual dispute differently, that would not be nearly enough to set aside the award.
B.L. Harbert,
We fully appreciate the financial burden this decision will impose upon DMA’s counsel. But only by imposing sanctions in cases like this can we give breath to the “national policy favoring arbitration.”
Hall St. Assocs.,
IV
The judgment of the district court is AFFIRMED, and Qwest’s motion for single costs and attorney fees is GRANTED. We REMAND to the district court for a determination of the appropriate amount. DMA’s request to file a supplemental appendix is also GRANTED.
Notes
. In addition to its breach of contract claim, DMA asserted various tort claims against Qwest that are not at issue in this appeal.
. Qwest contends that this argument is foreclosed by
Hall Street Associates v. Mattel, Inc.,
. DMA does not argue on appeal that the arbitrator was partial or corrupt.
