Nascimento v. Bridgehampton Construction Corp.Nascimento v. Bridgehampton Construction Corp.
APPEARANCES OF COUNSEL
The Durst Law Firm, P.C., New York City (John E. Durst, Jr., of counsel), for respondent.
OPINION OF THE COURT
Saxe, J.
This appeal brings up questions concerning subcontractor liability under the Labor Law’s strict liability provisions.
Plaintiff was injured while employed as a laborer for what amounts to a sub-sub-subcontractor on a renovation project: the general contractor, defendant Bridgehampton Construction Corp., subcontracted the framing work to defendant Bayview Building & Framing Corp., the appellant here, which in turn subcontracted that work to defendant R&L Carpentry Corp., which further subcontracted the work to defendant Figueiredo Construction, plaintiff’s employer.
In response to a motion by plaintiff for summary judgment on the issue of liability under
The motion court granted plaintiff’s motion, and denied Bayview’s cross motion.
Initially, we agree with the motion court that the difference between the witnesses’ factual recitations does not create a material issue of fact as to whether
“[W]hile determination of a summary judgment motion may be delayed to allow for further discovery where evidence necessary to oppose the motion is unavailable to the opponent, [a] determination of summary judgment cannot be avoided by a claimed need for discovery unless some evidentiary basis is offered to suggest that discovery may lead to relevant evidence” (Anne Koplick Designs, Inc. v Lite, 76 AD3d 535, 536 [2010] [citation and internal quotation marks omitted]).
Bayview failed to provide a basis for the claim that further discovery would lead to additional relevant evidence.
Bayview argues that summary judgment on a
However, with regard to whether there was a violation of a particular Industrial Code provision as a predicate for liability under
A more complex question is raised by Bayview’s contention that as a subcontractor rather than the general contractor, it was entitled to summary judgment dismissing the claim against it because it did not have the authority to oversee the work plaintiff was performing or the site’s safety conditions. In opposition to this contention, plaintiff argues that all subcontractors in the “chain of command” must be as liable as the general contractor.
Initially, we reject plaintiff’s broad assertion; the law does not hold that all subcontractors in the “chain of command” are necessarily as liable as the general contractor. Rather, as a subcontractor rather than the general contractor, Bayview may be held liable for plaintiff’s injuries under
Subcontractors have been held to be the statutory agents of general contractors in situations in which provisions of the subcontracts explicitly granted supervisory authority (see Weber v Baccarat, Inc., 70 AD3d 487, 488 [2010]; Nephew v Klewin Bldg. Co., Inc., 21 AD3d 1419, 1421 [2005]), and those in which evidence showed that the subcontractors actually exercised supervisory authority (see Everitt v Nozkowski, 285 AD2d 442, 444 [2001]). Additionally, evidence that a subcontractor delegated the requisite supervision and control to another subcontractor has been cited as forming part of the proof that the first subcontractor formerly possessed that authority, and may justify imposing Labor Law liability on the first subcontractor as a statutory agent of the general contractor (see Weber v Baccarat, 70 AD3d at 488; Everitt v Nozkowski, 285 AD2d at 444).
In Weber, the plaintiff fell from a defective ladder while installing an HVAC system. This Court found that the plaintiff was entitled to summary judgment against the HVAC subcontractor, King Freeze, because “King Freeze had the authority to supervise and control the work being done by plaintiff pursuant to the terms of its subcontract with IDI. Moreover, it demonstrated this authority by subcontracting a portion of the HVAC work to plaintiff’s employer” (70 AD3d at 488 [citations omitted]). The Court also observed that “[t]he fact that IDI possessed concomitant or overlapping authority to supervise the entire renovation, including the installation of the HVAC system, does not negate King Freeze’s authority to supervise and control the installation of the HVAC system. Whether King Freeze actually supervised plaintiff is irrelevant” (id.).
“the evidence establishes that Shuback did indeed have the authority to supervise and control the drywall installation. Shuback subcontracted out the work he was hired to perform[, but] . . . he visited the work site on a daily basis to check on the drywall installation crew and, more importantly, he instructed [his subcontractor] and his crew as to how and where to install the drywall” (id. at 444).
Bayview relies on the assertion by its president that it did not coordinate and supervise the project and was not empowered to enforce safety standards, and points out that there was no written contract between Bayview and Bridgehampton Construction from which the terms of Bayview’s authority may be definitively established. The record merely contains a written proposal from Bayview naming the work and its price, and Bayview’s written subcontract with its subcontractor, R&L Carpentry, which provided that R&L was agreeing “to provide all labor, tools, equipment, supervision and other items necessary to execute the [framing] work” (emphasis added).
We conclude that Bayview’s protestations do not entitle it to summary judgment. A finder of fact could find that when Bayview undertook responsibility for the framing work, and then subcontracted out that work, specifying that the subcontract included the responsibility to supervise the work, it acknowledged that the job it was subcontracting out included supervision of the framing work. The use of the word “supervision” in the subcontract does not alone establish the exact nature and extent of the assignment Bayview had been given by Bridgehampton; however, the particular circumstances presented here may permit the factfinder to infer that supervision of the framing work was part of the job Bayview had undertaken and, in turn, delegated to R&L. Moreover, nothing in its claim that it did not coordinate and supervise the work establishes as a matter of
Importantly, once a subcontractor qualifies as a statutory agent, it may not escape liability by the simple expedient of delegating that work to another entity (Inga v EBS N. Hills, LLC, 69 AD3d 568, 570 [2010]). If it undertook the supervision of the framing work, Bayview cannot avoid liability under the Labor Law by showing that R&L further subcontracted the work to Figueiredo.
In view of the foregoing, the affidavit by Bayview’s president fails to conclusively establish Bayview’s entitlement to summary judgment. Rather, a question of fact is presented as to the authority Bayview was given when the work was originally subcontracted to it. Therefore, the denial of Bayview’s cross motion for summary judgment was correct.
However, the question of fact regarding whether Bayview qualified as a statutory agent of Bridgehampton Construction requires us to reverse the grant of plaintiff’s motion for summary judgment on the issue of liability.
Accordingly, the order of the Supreme Court, New York County (Milton A. Tingling, J.), entered January 15, 2010, which, insofar as appealed from, granted plaintiff’s motion for summary judgment as against defendant Bayview Building & Framing Corp. on the issue of liability for violations of
Andrias, J.P., Moskowitz, Acosta and Freedman, JJ., concur.
Order, Supreme Court, New York County, entered January 15, 2010, modified, on the law, so as to deny plaintiff’s motion, and otherwise affirmed, without costs.