Manzi v. Town of RiverheadManzi v. Town of Riverhead
In the Matter of LONG ISLAND CONTRACTORS’ ASSOCIATION et al., Petitioners, and RICHARD MANZI et al., Respondents, v TOWN OF RIVERHEAD et al., Appellants. [793 NYS2d 494]—
In a proceeding pursuant to
Ordered that the order is modified, on the law, by deleting the provision thereof denying that branch of the motion which was to dismiss the petition insofar as asserted by the petitioners Irving Walston, Jr., and Thomas Pipczynski for lack of standing and substituting therefor a provision granting that branch of the motion; as so modified, the order is affirmed insofar as appealed from, without costs or disbursements, the proceeding insofar as asserted by the petitioner Richard Manzi, as trustee for the Joseph G. Manzi Irrevocable Trust, is severed, and the matter is remitted to the Supreme Court, Suffolk County, for further proceedings on the petition insofar as asserted by the petitioner Richard Manzi, as trustee for the Joseph G. Manzi Irrevocable Trust; and it is further,
Ordered that the respondent‘s time to answer the petition is extended until 20 days after service upon them of a copy of this decision and order.
In October 1994 the Town of Riverhead and the New York State Department of Environmental Conservation (hereinafter the DEC) entered into a stipulation of settlement requiring the Town to close its Youngs Avenue municipal solid waste landfill
In April 2001 the Town Board of the Town of Riverhead (hereinafter the Town Board) adopted Resolution No. 377, declaring that implementation of the landfill reclamation plan was a Type II action under the
The Town Board designated itself as lead agency for the purpose of conducting a coordinated environmental review of the siting of the asphalt plant. On March 18, 2003, the Town Board issued a negative declaration finding that the siting of the temporary asphalt plant on the Youngs Avenue landfill will not have a significant environmental impact and passed Resolution No. 301 on the same date, adopting the negative declaration. On June 3, 2003, the DEC issued an air permit to GL Paving for the asphalt plant.
On July 16, 2003, the petitioners commenced this
Since the basis for this proceeding is the Town Board‘s alleged noncompliance with SEQRA, the four-month statute of limitations applies (see
In this regard, we concur with the Supreme Court‘s reasoning in its decision and order:
“The law is clear that strict, not substantial, compliance with SEQRA is required (Matter of King v Saratoga County Bd. of Supervisors, 89 NY2d 341 [1996]). The approval of the solid waste material from the landfill to be used in asphalt production pursuant to
6 NYCRR 360-1.15 is not a substitute for SEQRA review, which requires a hard look at the environmental impact of the processing plant itself, not just whether or not the use of the landfill‘s solid waste to produce asphalt would be hazardous to the public health, safety, or welfare. Accordingly, the essence of this petition is a SEQRA challenge to the negative declaration on the basis that it was untimely and substantively inadequate. As such, it is timely, does not require any additional parties and states a cause of action.”
We disagree with the appellants’ contention that the DEC is a necessary party to this proceeding as it did not conduct the SEQRA review (see
The Supreme Court also properly determined that the petitioner Manzi had standing to maintain this proceeding. On a motion pursuant to
We reach a different conclusion, however, with respect to the petitioners Walston and Pipczynski. The petition alleges that Walston resides at a specific address within the Town and Pipczynski resides approximately one-half mile from the asphalt plant, and that both handle asphalt in the course of their employment. Neither may avail themselves of the presumption of injury in fact because they have not demonstrated that their properties lie in close proximity to the asphalt plant (see Matter of Rediker v Zoning Bd. of Appeals of Town of Philipstown, 280 AD2d 548 [2001]; Matter of Many v Village of Sharon Springs Bd. of Trustees, 218 AD2d 845 [1995]; Matter of Casement v Town of Poughkeepsie Planning Bd., 162 AD2d 685 [1990]; see also Matter of Piela v Van Voris, 229 AD2d 94 [1997]). Therefore, they must demonstrate that they would suffer an environmental injury which is “in some way different from that of the public at large” (Society of Plastics Indus. v County of Suffolk, supra at 774; see also Matter of Mobil Oil Corp. v Syracuse Indus. Dev. Agency, 76 NY2d 428, 433 [1990]). They failed to meet this burden (Matter of Sun-Brite Car Wash v Board of Zoning & Appeals of Town of N. Hempstead, supra at 413). Accordingly, the Supreme Court should have dismissed the petition insofar as asserted by Walston and Pipczynski.
The parties’ remaining contentions either are not properly before this Court or are without merit. Cozier, J.P., S. Miller, Spolzino and Skelos, JJ., concur.