Many v. Village of Sharon Springs Board of TrusteesMany v. Village of Sharon Springs Board of Trustees
Appeal from a judgment of the Supreme Court (Hughes, J.), entered September 26, 1994 in Schoharie County, which, in a proceeding pursuant to CPLR article 78, dismissed the petition due to petitioners’ lack of standing.
In this CPLR article 78 proceeding, petitioners contend, inter alia, that respondent Village of Sharon Springs Board of Trustees (hereinafter the Village), and other agency respondents, failed to comply with the mandates of the State Environmental Quality Review Act (ECL art 8) (SEQRA) during the review and decision-making process that culminated in the approval of a proposal by respondent Wal-Mart Stores, Inc. to construct a large warehouse and price-marking facility on the outskirts of the Village in Schoharie County. Supreme Court did not reach the merits of the petition, for it found that petitioners lacked standing to maintain this proceeding. The lone appellant, petitioner Seth E. Many (hereinafter petitioner), is a property owner and resident of the Village.
As Supreme Court aptly observed, the proximity of petitioner’s properties to the proposed facility—they are situated one half mile from the site—is insufficient, without more, to confer standing; actual injury must be shown (see, Matter of Sun-Brite Car Wash v Board of Zoning & Appeals,
Significantly, the final environmental impact statement (hereafter FEIS) for this project does not categorically controvert petitioner’s claims of injury. In response to comments registered by petitioner and other members of the public, the FEIS merely states that "the fields of hydrogeology and geology are not exact sciences”, that "hydrogeologic paths cannot be determined with complete accuracy”, and that while "the project has been extensively redesigned to avoid construction over sinkholes and the karst areas” and to provide for treatment of stormwater runoff in detention ponds and in on-site created wetlands, "[ijmpacts on adjacent springs are possible”, although "the Village’s natural springs should not be unduly affected” (emphasis supplied). Nor have respondents called into question petitioner’s allegations that the stormwater from the construction site will flow into the Karst hydro-geologic formations underlying the north portion of the site, and from there down the hill and into the area in which petitioner’s well and springs are located. Accordingly, it would be improper to reject petitioner’s claims of injury as "merely speculative” or "wholly conclusory” at this juncture.
Mikoll, J. P., Crew III, White and Peters, JJ., concur. Ordered that the judgment is reversed, on the law, with costs, and petition reinstated.