Kemper Insurance Companies v. StateKemper Insurance Companies v. State
Ernstrom & Dreste, L.L.P., Rochester (Theodore M. Baum of counsel), for appellant.
Andrew M. Cuomo, Attorney General, Albany (Paul Groenwegen of counsel), for respondent.
OPINION OF THE COURT
Garry, J.
In March 2000, Haseley Construction entered into a contract with defendant to reconstruct part of a roadway in the Town of Niagara, Niagara County (hereinafter the Military Road Project). Claimant, as Haseley’s surety, provided performance and payment bonds for the Military Road Project on which Haseley was named as the principal and defendant was named as obligee. In August 2001, defendant declared Haseley in default and formally terminated it from the project. The parties have stipulated that at the time of Haseley’s termination, defendant was holding $579,779.68 which was due or to become due to Haseley in connection with the Military Road Project. In October 2001, defendant and claimant entered into a takeover agreement by which claimant agreed to complete the Military Road Project,
In June 2002, the Internal Revenue Service (hereinafter IRS) issued a notice of levy to defendant with reference to outstanding tax obligations owed by Haseley. In January 2003, the IRS issued a second notice of levy to defendant. In response to the second notice of levy, the Office of the State Comptroller issued payment of $579,779.68 to the IRS, using funds from the Military Road Project (hereinafter referred to as the project funds). Defendant did not then know nor inquire whether Haseley’s tax obligations arose from the Military Road Project. Neither defendant nor the IRS advised claimant of the notices of levy or of defendant’s payment of the project funds to the IRS.
Claimant completed the Military Road Project, satisfied all of its obligations under the surety and takeover agreements, and demanded payment from defendant. Defendant’s payment did not include the sum that had been turned over to the IRS, and the funds paid were insufficient to complete the work and cover claimant’s payments to laborers, suppliers, and others under the payment bonds, causing claimant to suffer a loss. Therefore, in May 2003, claimant served a notice of intention to file a claim before the Court of Claims. This claim was held in abeyance during the pendency of an action filed by claimant against the United States in the United States District Court for the Western District of New York, in which claimant contended that the IRS had wrongfully levied on the project funds. In April 2006, claimant and the United States executed a stipulation of judgment in the federal action, agreeing that, at the time of the levy, claimant was entitled to $535,885.78.1 This was approved by the federal court in May 2006. Upon appeal, claimant accepted $300,000 to settle the federal action.
Claimant thereafter amended its claim against defendant in the Court of Claims to allege that defendant wrongfully diverted the contract funds and breached the takeover agreement, and to
Under the Internal Revenue Code, any person3 in possession of property that is subject to a federal tax levy and not subject to attachment or execution under judicial process must surrender the property to the IRS upon demand (see
Federal laws do not themselves create property rights; instead, they attach consequences to property rights created by state laws (see United States v National Bank of Commerce, 472
As the agreement between Haseley and defendant was a construction contract, all funds under the contract were subject to a statutory trust imposed by
Prior to its termination from the contract, Haseley held a “right of action” in all funds due or to become due to it under the contract (
Even this contingent interest was cut off by defendant’s own actions prior to the first notice of levy. By formally terminating Haseley from the contract and entering into the takeover agreement, defendant eliminated whatever beneficial interest, if any, Haseley might have retained in the project funds. Having thus terminated all of Haseley’s actual interest in the project funds, there was no basis on which defendant could have determined that Haseley had an “apparent interest” in those funds at the time that it turned them over to the IRS (see
In dismissing the claim, the Court of Claims found that if the project funds were wrongfully turned over to the IRS, claimant’s exclusive remedy was an action in federal court. In this regard, the court relied upon
Claimant moved for summary judgment in its favor on its breach of contract claim. In the takeover agreement, defendant agreed that it would pay to claimant “[a]ll sums now due and payable and to become due and payable” on the Military Road Project, “subject to applicable liens and setoffs . . . as if there had been no declared termination of employment of [Haseley].” The parties stipulated that claimant fully performed its obliga-
Mercure, J.P., Spain, Rose and Kane, JJ., concur.
Ordered that the judgment is reversed, on the law, without costs, defendant’s cross motion denied, claimant’s motion granted and summary judgment awarded to claimant.