RLI Ins. Co. v. LABOR DEPT.RLI Ins. Co. v. LABOR DEPT.
In the Matter of RLI INSURANCE COMPANY, SURETY DIVISION, Appellant,
v.
NEW YORK STATE DEPARTMENT OF LABOR et al., Respondents.
Court of Appeals of the State of New York.
*258 Ernstrom & Dreste LLP, Rochester (Theodore M. Baum, Michael F. Dehmler and John W. Dreste of counsel), for appellant.
Eliot Spitzer, Attorney General, New York City (M. Patricia Smith, Caitlin J. Halligan, Michael S. Belohlavek and Daniel J. Chepaitis of counsel), for New York State Department of Labor and another, respondents.
*259 Wolff & Samson, P.A., New York City (Armen Shahinian and Scott D. Baron of counsel), for Surety Association of America, amicus curiae.
Chief Judge KAYE and Judges SMITH, CIPARICK, WESLEY, ROSENBLATT and GRAFFEO concur.
*260 OPINION OF THE COURT
LEVINE, J.
Petitioner RLI Insurance Company, as surety, posted performance and payment bonds on a public improvement project. RLI now claims subrogation rights after fully completing the construction on behalf of the defaulting contractor and paying all subcontractors, laborers and suppliers. At issue is whether RLI's right to funds still in the possession of the project owner is superior to a claim filed by respondent Department of Labor (DOL) for underpaid wages rendered on an unrelated project. We conclude that it is. We therefore reverse the contrary ruling by the courts below.
On May 5, 1998, D.C. White Company Inc. entered into an agreement with the Queensbury Union Free School District to be the general contractor on a public improvement project involving renovations to the School District's buildings (the Queensbury Project). Shortly thereafter, White procured payment and performance bonds from RLI. White commenced work and submitted an application to the School District for payment in June 1998. The project's construction manager and architect certified in July 1998 that $53,424 was due.
Subsequently, the School District's construction manager notified White that it was in default and the District terminated the contract effective August 21, 1998. RLI, as surety, thereafter undertook performance of the contract and expended in excess of $176,000 to complete the Queensbury Project and pay all claims of Lien Law article 3-A trust beneficiaries. Concededly, the remaining liability of the School District for the completion of the project after White's default was $135,250.
On July 9, 1999, respondent DOL served the School District with a Notice of Withholding of payment from White in the amount of $19,150.15, pursuant to
RLI commenced this CPLR article 78 proceeding seeking to compel DOL to withdraw its Notice of Cross-Withholding and to enjoin the School District from releasing any funds to DOL pursuant to the notice. Supreme Court denied the petition, holding that DOL's claim to the cross-withheld funds is consistent *261 with the provisions of Lien Law article 3-A and superior to any claim of RLI, as surety. The court relied upon RLI's concession that the Notice of Withholding on the Queensbury Project has priority and concluded that because
The Appellate Division affirmed, reasoning that the clear intent of
The statutory framework for the resolution of this appeal consists of Labor Law article 8 and Lien Law article 3-A.
RLI contends that the funds still held by the School District pursuant to the Notices of Withholding and Cross-Withholding are article 3-A trust assets. It further argues that the School District, as owner, has the contractual right to withhold the funds to pay article 3-A trust beneficiaries, such as suppliers, subcontractors and laborers on the Queensbury Project; that those beneficiaries are entitled to be paid from the trust funds; and that in making full payment and completing performance, RLI is subrogated to the rights of both the owner and the statutory trust beneficiaries.
DOL asserts that funds withheld pursuant to the Labor Law do not constitute assets of a Lien Law article 3-A trust since the assets of such a trust are derivative of the contractor's right to payment. Therefore, DOL maintains, if it is established that the contractor failed to pay prevailing wages, its right to *262 payment supersedes to that extent any amount due the contractor and, hence, neither the contractor nor the article 3-A beneficiaries have any right to the withheld funds. Alternatively, DOL argues that even if the funds at issue were the assets of an article 3-A trust, the general contractor here has no beneficial interest in the funds and RLI's subrogation rights are limited to those of the contractor.
We disagree with both of DOL's contentions. As a matter of statutory construction and under our precedents, even before funds are "due or earned," they become assets of an article 3-A trust. In addition, RLI may rely upon its equitable subrogation rights to recover the funds withheld by the School District.
An article 3-A trust commences "when any asset thereof comes into existence" and continues until all trust claims have been paid or discharged, or all assets have been applied for trust purposes (see, Lien Law § 70 [3]; see also, Postner and Rubin, New York Construction Law Manual § 9.69, at 352-353). The trust is "broadly inclusive" and consists of assets of every conceivable type arising from the work, including rights of action, as well as realized assets (see, City of New York v Cross Bay Contr. Corp.,
Section 70 (1) (a) thus "extend[s] the right of action as a trust asset to contingent, not fully matured rights to receive payment for work in progress" (Canron Corp. v City of New York,
Lien Law article 3-A mandates that once a trust comes into existence, its funds may not be diverted for non-trust purposes. Use of trust assets for any purpose other than the expenditures authorized in Lien Law § 71 before all trust claims have been paid or discharged constitutes an improper diversion of trust assets, regardless of the propriety of the trustee's intentions (see, Lien Law § 72 [1]; Canron, supra, at 154; Aquilino v United States,
Given the comprehensive language of Lien Law article 3-A and the inclusion of even unmatured rights to future payment as trust assets, DOL's position that its cross-withholding attached before any article 3-A trust asset came into existence is untenable. A comparison of the literal language of
This conclusion is supported by the primary purpose of article 3-A and its predecessors"to ensure that `those who have directly expended labor and materials to improve real property [or a public improvement] at the direction of the owner or a general contractor' receive payment for the work actually performed" (Canron, supra, at 155 [quoting West-Fair Elec. Contrs. v Aetna Cas. & Sur. Co.,
Therefore, the reliance by the courts below on the absence of any distinction in
We similarly reject DOL's alternative argument that RLI's rights, as subrogated surety, are limited to those available to White, as contractor. RLI has paid all outstanding claims of the trust beneficiaries pursuant to its obligation under the payment bond. Under equitable subrogation principles, where a surety has fully satisfied its obligations under a payment *265 bond and the owner has retained funds to be used in completion of the improvement,
"the [owner] had a right to use the retained fund to pay laborers and materialmen; * * * the laborers and materialmen had a right to be paid out of the fund; * * * the contractor, had [it] completed [its] job and paid [its] laborers and materialmen, would have become entitled to the fund; and * * * the surety, having paid the laborers and materialmen, is entitled to the benefit of all these rights to the extent necessary to reimburse it" (Pearlman v Reliance Ins. Co.,371 US 132 , 141 [1962]).
Thus, in Caristo Constr. Corp. v Diners Fin. Corp. (
Further, this Court has long held that a completing surety succeeds under equitable subrogation principles to all rights that the obligee/owner has against the contractor, including the right to use the unpaid contract balance to complete the project or satisfy outstanding claims for labor and materials furnished (see, Aetna Cas. & Sur. Co. v United States,
*266 Our decision in City of New York v Cross Bay Contr. Corp. (
Contrary to DOL's position, our decision does not render its rights under
Finally, a holding in favor of RLI here is supported by public policy considerations. Were we to adopt DOL's position, completing sureties would be forced to pay for obligations they did not bond. Such a result would lead to increased risks and uncertainties of exposure for sureties and, ultimately, greater costs to the taxpayers on public improvement projects.
Accordingly, the order of the Appellate Division should be reversed, with costs, the petition granted and DOL directed to withdraw its Notice of Cross-Withholding.
Order reversed, etc.
NOTES
Notes
[*] Under Lien Law article 3-A, wage-related claims of laborers, as trust beneficiaries, are given priority status (see, Lien Law § 77 [8]). In this proceeding, RLI has not contested the priority of DOL's Notice of Withholding for unpaid laborers' prevailing wages attributable to the Queensbury Project.