J. Petrocelli Construction, Inc. v. Realm Electrical Contractors, Inc.J. Petrocelli Construction, Inc. v. Realm Electrical Contractors, Inc.
In an action, inter alia, to recover damages for breach of contract and to enforce a trust pursuant to
Ordered that the order dated November 22, 2002, is affirmed insofar as appealed and cross-appealed from, without costs or disbursements; and it is further,
Ordered that the order dated October 24, 2003, is affirmed insofar as appealed from, without costs or disbursements.
On September 11, 1998, the plaintiff, as general contractor, entered into a contract (hereinafter the Contract) with the New York City School Construction Authority (hereinafter the SCA) for the construction of P.S. 6 on Staten Island. On October 6, 1998, the plaintiff entered into a subcontract (hereinafter the Subcontract) with the defendant third-party plaintiff, Realm Electrical Contractors, Inc., also known as Realm Electrical Corp., also known as Realm Electric Corp. (hereinafter Realm), for the performance of electrical work in connection with the project.
From approximately May 1999 until July 2000 the plaintiff repeatedly advised Realm to increase its on-site personnel in order to meet construction deadlines. Following the plaintiff‘s failure to achieve “substantial completion of the work” by June 28, 2000, as required under the terms of the Contract, SCA scheduled a termination-for-cause conference for July 10, 2000. SCA‘s reasons for calling the conference included, inter alia, the failure to “maintain and provide the necessary manpower to complete the electrical portion of the work to meet the substantial completion date.” Immediately following the termination conference, the plaintiff, by letter dated July 10, 2000, terminated the Subcontract effective July 11, 2000.
Thereafter, the plaintiff commenced this action against the defendants to recover damages arising from Realm‘s alleged breach of the Subcontract, and the defendants counterclaimed and commenced a third-party action against Fireman‘s Fund Insurance Company, which had issued a bond guaranteeing payment for money due to the claimants for labor and material used in the project.
The defendants moved for partial summary judgment on their counterclaim to recover damages for breach of contract. They argued that the plaintiff breached section 7.2.1 of the Subcontract which required the plaintiff to provide Realm with seven
Generally, where parties agree on a termination procedure, the clause must be enforced as written (see A.S. Rampell, Inc. v Hyster Co., 3 NY2d 369, 382 [1957]; General Supply & Constr. Co. v Goelet, 241 NY 28 [1925]; Blumberg v Florence, 143 AD2d 380, 381 [1988]). Nevertheless, “[o]nce it becomes clear that one party will not live up to the contract, the aggrieved party is relieved from the performance of futile acts, such as conditions precedent” (Allbrand Discount Liqs. v Times Sq. Stores Corp., 60 AD2d 568 [1977]; accord Oak Bee Corp. v Blankman & Co., 154 AD2d 3, 8 [1990]). Applying these principles, we agree with the Supreme Court‘s assessment that neither party in this case was entitled to judgment as a matter of law on their respective breach of contract claims. Whether the plaintiff is liable for its alleged failure to comply with the termination procedure set forth in section 7.2.1 of the Subcontract hinges on, inter alia, the resolution of factual issues centered around Realm‘s alleged prior repudiation of the Subcontract at the termination confer
With respect to the plaintiff‘s claims pursuant to
The parties’ remaining contentions are without merit. Krausman, J.P., Mastro, Spolzino and Fisher, JJ., concur.