In the Matter of Issuance of Air Emissions Permit No. 13700345-101 for Polymet Mining, Inc., City of Hoyt Lakes, St. Louis County, Minnesota.
A19-0115 A19-0134
STATE OF MINNESOTA IN COURT OF APPEALS
Filed March 23, 2020
Rodenberg, Judge
Remanded; motion to supplement granted and motion to strike denied Minnesota Pollution Control Agency
Sean Copeland, Fond du Lac Band of Lake Superior Chippewa, Cloquet, Minnesota; and
Vanessa L. Ray-Hodge (pro hac vice), Sonosky, Chambers, Sachse, Mielke & Brownell, LLP, Albuquerque, New Mexico (for relator Fond du Lac Band of Lake Superior Chippewa)
Monte A. Mills, Caitlinrose H. Fisher, Green Espel PLLP, Minneapolis, Minnesota; and
Jay C. Johnson (pro hac vice), Venable LLP, Washington, District of Columbia (for respondent PolyMet Mining, Inc.)
Keith Ellison, Attorney General, St. Paul, Minnesota; and
Emily C. Schilling (pro hac vice), Holland & Hart LLP, Salt Lake City, Utah; and
Sarah Koniewicz, Holland & Hart LLP, Boulder, Colorado; and
Adonis A. Neblett, General Counsel, Minnesota Pollution Control Agency, St. Paul, Minnesota (for respondent Minnesota Pollution Control Agency)
S Y L L A B U S
- In a certiorari appeal challenging an agency decision to issue a permit, documents that were submitted to the agency after the close of the noticed public-comment period and that were not considered by the agency are not part of the record that must be submitted to this court by the agency. However, in evaluating a challenge to the agency’s decision for failure to adequately consider an important aspect of the permitting decision, this court may consider documents and information that were submitted to the agency at any time before it issued its decision.
- This court’s authority under
Minn. Stat. § 14.69 (2018) to remand an administrative case for further proceedings is not dependent on establishment of one of the six reasons for reversal of the agency’s decision under that provision. This court may remand for further proceedings when the record submitted by the agency and the written agency decision are insufficient to facilitate judicial review.
O P I N I O N
RODENBERG, Judge
These two consolidated certiorari appeals are brought by relators Minnesota Center for Environmental Advocacy, et al.1 (MCEA) and Fond du Lac Band of Lake Superior Chippewa (the band) to challenge a decision by respondent Minnesota Pollution Control
FACTS
If built, PolyMet’s NorthMet project would be the first copper-nickel-PGE (platinum group elements) mine in Minnesota. We have extensively discussed the nature of the proposed project in several recent decisions in related matters. See In re NorthMet Project Permit to Mine Application Dated Dec. 2017, No. A18-1952, 2020 WL 130728, at *2-3 (Minn. App. Jan. 13, 2020) (PTM Appeals); Minn. Ctr. for Envtl. Advocacy v. Minn. Dep‘t of Nat. Res., No. A18-1956, 2019 WL 3545839, at *1 (Minn. App. Aug. 5, 2019), review denied (Minn. Oct. 29, 2019); In re Applications for a Supplemental Envtl. Impact Statement for Proposed NorthMet Project, No. A18-1312, 2019 WL 2262780, at *1 (Minn. App. May 28, 2019) (SEIS Appeals), review denied (Minn. Aug. 20, 2019). The NorthMet project requires multiple permits from state and federal authorities and also triggered joint
Among the permits required for the NorthMet project is an air-emissions permit from the MPCA. PolyMet submitted an application for an air-emissions permit in August 2016 and a revised application in January 2018. PolyMet applied for what is known as a “synthetic minor permit” based on its requests for permit limitations on ore-processing, or “throughput,” volumes. Specifically, PolyMet proposed to limit ore throughput to 32,000 tons per day (tpd) (11,680,000 tons per year (tpy)). As we explain further herein, requesting this throughput limit allowed PolyMet to avoid the requirements for “major source” permitting under the federal Clean Air Act.
The MPCA commenced a public notice and participation process on the air-emissions-permit application in January 2018. On January 5, 2018, the MPCA issued a public notice of two public meetings that were held on February 7 and 8, 2018, in Aurora and Duluth. And on January 31, 2018, the MPCA issued a public notice of its commissioner’s preliminary determination and intent to issue the draft air-emissions permit. That public notice commenced a 45-day public-comment period that ran through March 16, 2018. During the public-comment period, the MPCA received 88 comments from government agencies, tribal parties (including the band), environmental groups (including MCEA), and individuals.
Ten days after the close of the public-comment period, on March 26, 2018, PolyMet filed with Canadian securities regulators a Form NI 43-101F1 Technical Report (the
In June 2018, MCEA submitted to the DNR, with a copy to the MPCA commissioner, a petition for a supplemental environmental-impact statement (SEIS). MCEA argued that the Canadian technical report evidenced PolyMet’s intent to build a larger project than that for which it was seeking permits, and that the report “makes plain that the PolyMet project is financially feasible only if the current proposal is the first phase of an expanded and/or accelerated project.” MCEA argued that the Canadian technical report thus included “substantial new information” that required preparation of an SEIS. See
In October 2018, after making changes to the draft permit based on public comments, the MPCA provided a copy of the air-emissions-permit application, proposed permit, and technical support document to the United States Environmental Protection Agency (EPA). The EPA’s review period ended on December 10, 2018, and the EPA did not submit any written comments or object to the proposed final permit.
Meanwhile, on November 1, 2018, the DNR had issued a permit to mine, dam-safety permits, and other permits for the NorthMet project.5 On November 8, 2018, MCEA submitted a letter to the DNR and the MPCA requesting that they stay all permits for the NorthMet project pending resolution of the appeal from the DNR decision denying an SEIS. The MPCA denied the stay request as prematurely made before it had issued any permits.
On Thursday, December 13, 2018, MCEA submitted a letter to the MPCA commissioner, asserting that the MPCA had a duty to investigate whether “PolyMet is
Six calendar days later, on Wednesday, December 19, 2018, the MPCA commissioner sent a letter of reply to MCEA. The reply cited cautionary language from the Canadian technical report, and stated that the increased-throughput scenarios examined in the report were “speculative at best.” The MPCA commissioner concluded: “Neither the Technical Report, nor PolyMet’s submittals in support of the Air Permit, indicate any intent by PolyMet to circumvent major source permitting. For these reasons, the Technical Report does not provide a basis for withholding issuance of the final PolyMet Air Permit.”
The next day, December 20, 2018, the MPCA issued the air-emissions permit to PolyMet for the NorthMet project.
MCEA and the band filed separate certiorari appeals, which this court consolidated. During the processing of the appeals, the parties have filed motions raising issues as to the appropriate scope of the record for this court’s review.
ISSUES
- Should the motions related to the record be granted?
- Have relators established a basis for relief under
Minn. Stat. § 14.69 ?
ANALYSIS
The air-emissions permit in this case is governed by the federal Clean Air Act,
Under the New Source Review (NSR)/Prevention of Significant Deterioration (PSD) provisions of the CAA,
Although not specifically defined by the CAA or federal regulations, a “synthetic minor source” has come to be understood as a source that “accepts limitations that restrict its potential to emit air pollutants to a level below the PSD threshold.” In re Shell Offshore, Inc., 15 E.A.D. 536, 2012 WL 1123876, at *12 (EAB. March 30, 2012). Synthetic-minor permits are issued to provide federally enforceable limits that avoid application of PSD requirements. Synthetic-minor permits are allowed under the CAA. Issues may arise, however, when an applicant seeks a synthetic-minor permit but does not actually intend to comply with the limits provided in that permit. In such a circumstance, the applicant is understood to have sought a “sham permit,” which, according to the EPA, is not permitted under the CAA. See Memorandum from Terrell Hunt, Assoc. Enforcement Counsel, U.S. EPA, & John Seitz, Dir., Stationary Source Compliance Div., U.S. EPA, Guidance on Limiting Potential to Emit in New Source Permitting 12-13 (June 13, 1989), available at https://www3.epa.gov/airtoxics/pte/june13_89.pdf (EPA Guidance).
The MPCA’s decision to issue PolyMet a synthetic-minor permit is subject to judicial review under
the court may affirm the decision of the agency or remand the case for further proceedings; or it may reverse or modify the decision if the substantial rights of the petitioners may have been prejudiced because the administrative finding, inferences, conclusion, or decisions are:
(a) in violation of constitutional provisions; or
(b) in excess of the statutory authority or jurisdiction of the agency; or
(c) made upon unlawful procedure; or
(d) affected by other error of law; or
(e) unsupported by substantial evidence in view of the entire record as submitted; or
(f) arbitrary or capricious.
Relators argue that the MPCA’s decision to issue the permit is arbitrary and capricious and unsupported by substantial evidence. As a threshold matter, however, they assert that the MPCA failed to take a required “hard look” at whether PolyMet is engaged in sham permitting, and that this court should reverse or, at a minimum, remand on that basis. See Citizens Advocating Responsible Dev. v. Kandiyohi Cty. Bd. of Comm‘rs, 713 N.W.2d 817, 832 (Minn. 2006) (CARD) (“Our role when reviewing agency action is to determine whether the agency has taken a ‘hard look’ at the problems involved, and whether it has ‘genuinely engaged in reasoned decision-making.’” (quoting Reserve Mining Co. v. Herbst, 256 N.W.2d 808, 825 (Minn. 1977))). Respondents assert that the “hard look” standard does not apply to permitting decisions and that, in any event, the MPCA has taken the requisite hard look. In section II below, we address the appropriate application of the standard of review and whether relators have established a basis for this court to grant relief. But we first address, in section I, the motions submitted by the parties in relation to the record.
I.
In a certiorari appeal, the agency decision-maker is required to serve and file an itemized list of the contents of the record after the writ of certiorari is issued, and to submit the record itself at this court’s request, which generally is made after a relator’s brief is filed. See
After the MPCA submitted the itemized list in this case, relators filed a motion to complete or supplement the administrative record,8 seeking to include in the record two
Relators argue that all of the disputed citations and documents are properly before this court under the supreme court’s decision in Crystal Beach Bay Ass‘n v. County of Koochiching, 243 N.W.2d 40, 43 (Minn. 1976), and this court’s decision in White v. Minn. Dep‘t of Nat. Res., 567 N.W.2d 724, 735 (Minn. App. 1997).9 In Crystal Beach Bay, the
We agree with relators that this court may consider the disputed citations and documents under Crystal Beach Bay and White. The crux of relators’ arguments on appeal is that the MPCA failed to adequately consider information that was available to it and that the information not adequately considered demonstrates PolyMet’s intent to exceed the throughput limits in the air-emissions permit. The disputed citations and documents contain that information. Thus, we may consider the disputed citations and documents as probative of whether the MPCA “failed to consider information relevant to making its decision,” White, 567 N.W.2d at 735, or “entirely failed to consider an important aspect of the problem,” CARD, 713 N.W.2d at 832, and because such consideration is “commend[ed]” by “the orderly administration of justice,” Crystal Beach Bay, 243 N.W.2d
characterization of those documents is disputed by the MPCA and PolyMet. We accordingly decline to take judicial notice.
II.
Standard of Review
As we note above, this court may affirm or remand an agency decision, or we may reverse the decision if one of six statutory criteria are met, including that the agency’s decision is arbitrary and capricious or that it is unsupported by substantial evidence.
The MPCA and PolyMet argue that the “hard look” analysis applies only in the context of environmental-review decisions under the Minnesota Environmental Policy Act (MEPA) and that this court should not apply the analysis in this permitting case. We reject this argument for two reasons. First, although the “hard look” analysis is often applied in MEPA cases, its application has not been exclusive to those cases. See, e.g., In re A.D., 883 N.W.2d 251, 260 (Minn. 2016) (citing analysis in appeal from school’s expulsion decision); In re Reichmann Land & Cattle, LLP, 867 N.W.2d 502, 512 (Minn. 2015) (applying analysis in appeal from agency order requiring relator to obtain NPDES/SDS permit); Cable Commc’ns Bd., 356 N.W.2d at 669 (applying analysis in appeal from order granting cable franchise); U.S. Steel, 937 N.W.2d at 786-88 (applying analysis in appeal from decision to reissue NPDES/SDS permit). Second, MPCA’s and PolyMet’s arguments appear to be based on the mistaken premise that the “hard look” analysis is distinct from
Although we reject the MPCA’s and PolyMet’s arguments that we should not apply the “hard look” analysis, we emphasize that the “hard look” analysis is part of this court’s standard of review—it does not create substantive obligations on the part of the MPCA. Under the “hard look” analysis, this court will inquire whether the MPCA took a “hard look at the salient problems.” Cable Commc’ns Bd., 356 N.W.2d at 669 (quotation omitted). But the scope of the “salient problems” will be determined by the substantive law governing the MPCA’s decision.
Remand
Although we may reverse an agency decision only for one of the six reasons specified in
As we explain above, the MPCA issued the air-emissions permit in relation to its authority to enforce the CAA. Under rules adopted pursuant to that authority, eight conditions must be satisfied in order for the MPCA to issue an air-emissions permit. See
Importantly, the MPCA issued these conclusory findings after questions were raised concerning PolyMet’s intent to abide by the terms of the synthetic-minor permit. During the public-comment period, MCEA had noted that the crusher lines at the former LTVSMC plant had more throughput capacity than PolyMet claimed to intend to use, and it urged that strict production and monitoring conditions should be included in the permit. After the close of the public-comment period—but before MPCA issued the permit—MCEA submitted to the MPCA commissioner a copy of its petition for an SEIS, which included as exhibits the Canadian technical report and other documents reflecting statements by PolyMet concerning the potential for expansion of the NorthMet project. And on December 13, 2018, MCEA sent a letter to the MPCA commissioner expressly urging that the MPCA investigate whether PolyMet was seeking a sham permit. Notwithstanding these documented concerns, the MPCA’s decision to grant the permit—issued just seven
This deficit was not remedied by the MPCA commissioner’s short December 19, 2019 letter in response to the MCEA’s December 13 letter raising concerns about sham permitting. That letter is deficient for the same reasons as the MPCA’s formal findings in its December 20 decision. The letter acknowledges the increased-throughput scenarios analyzed in the Canadian technical report—which was commissioned by PolyMet and distributed to its investors and potential investors—but then the letter summarily dismisses those analyses as preliminary and speculative, and concludes, without further explanation, that “[n]either the Technical Report, nor PolyMet’s submittals in support of the Air Permit, indicate any intent by PolyMet to circumvent major source permitting.” Yet the Canadian technical report analyzes not only the current NorthMet project, but also discusses two scenarios that would involve throughput that would exceed the 32,000-tpd level needed to limit air emissions to synthetic-minor-permit levels. According to the Canadian technical report, the greater throughputs would increase profits and would allow the project to continue to operate profitably when metal prices are depressed. Put differently, the Canadian technical report raises questions concerning whether, if metal prices drop, the project can remain viable with the 32,000-tpd-throughput limitation that the synthetic-minor permit necessitates.
Even if speculative, PolyMet’s explicit consideration of the potential for an expansion of the NorthMet project is probative of whether PolyMet can be expected to
In sum, without particularized findings, and without the agency having submitted everything it considered or may have considered, we are unable to determine if the MPCA’s decision to grant a synthetic-minor permit for the NorthMet project was arbitrary and capricious or unsupported by substantial evidence. For this reason, we conclude that a remand to the MPCA for additional findings is warranted. See Restorff, 932 N.W.2d at
D E C I S I O N
We grant the MCEA’s motion to supplement, deny the MPCA’s motion to strike, and—because the MPCA’s findings in support of its decision to issue the air-permit are not sufficient to facilitate judicial review—remand to the MPCA for additional findings and a revised decision. On remand, the MPCA shall reopen the record to ensure the adequacy of the record and hold such further proceedings as it deems appropriate to develop those findings.
Remanded; motion to supplement granted and motion to strike denied.
