In rе Champlain Parkway Act 250 Permit (Fortieth Burlington, LLC, Appellant)
No. 14-352
Supreme Court of Vermont
August 21, 2015
2015 VT 105 | 129 A.3d 670
Present: Reiber, C.J., Dooley, Skoglund, Robinson and Eaton, JJ.
Opinion Filed August 21, 2015
Affirmed.
Brian S. Dunkiel, Geoffrey H. Hand, Elizabeth H. Catlin and Victoria M. Westgate of Dunkiel Saunders Elliott Raubvogel & Hand, PLLC, Burlington, for Appellee City of Burlington.
¶ 1. Skoglund, J. The City of Burlington аnd the Vermont Agency of Transportation (AOT) applied for an Act 250 permit amendment to complete a project known as the Champlain Parkway, a roadway designed to route traffic more efficiently from Interstate 89 in South Burlington to the City of Burlington‘s downtown area. The environmental court concluded that the application complied with Act 250‘s transрortation criterion (Criterion 5) subject to conditions requiring that applicants monitor and report on the project‘s traffic-congestion and safety impacts, and work with the opposing party in this proceeding, Fortieth Burlington, LLC, to resolve any remaining issues. Fortieth has appealed, asserting that: (1) the conditions imposed by the court
¶ 2. The facts may be summarized as follows. The Champlain Parkway is a substantially modified version of thе original Southern Connector project, a proposed four-lane highway running from Interstate 89 in South Burlington to downtown Burlington that received initial Act 250 approval in 1981. Although the first and southernmost phase of the project was constructed in the late 1980s, the discovery of hazardous material along the project route and subsequent remediation efforts halted further progress. The project subsequently evolved to its current form as the Champlain Parkway, with a roadway reduced to two lanes, a new route bypassing the contaminated area, and additional bicycle and pedestrian accommodations.
¶ 3. Applicants sought an Act 250 permit amendment for the redesigned project, which was divided into three segments fоr planning and construction purposes; the first, running from Interstate-189 to Home Avenue, had been previously approved and constructed; the second, running from Home Avenue north to Lakeside Avenue, was previously approved but never constructed; and the third, running from Lakeside Avenue east to Pine Street then north to terminate at Main Street, had not been previously reviewed or approved. In April 2012, the District No. 4 Environmental Commission issued an order finding that the project complied with all but two Act 250 criteria, Criteria 1(B) and 4 relating to wastewater and erosion control, which required approved stormwater permits.
¶ 4. Several parties appealed the ruling to the environmental court, although only one — Fortieth Burlington, LLC — remained by the time of the hearing. The questions on appeal related exclusively to whether the project would “cause unreasonable congestion or unsafe conditions with respect to use of highways . . . and other means of transportation existing or proposed” under Criterion 5 of Act 250.
¶ 5. Fortieth owns property on the north side of Lakeside Avenue, just west оf the intersection with the planned Parkway. Its neighbor to the east on Lakeside is a property owned by the Burlington Department of Public Works (DPW). Fortieth‘s prop-
¶ 6. As it approaches Lakeside Avenue from the south, the planned Parkway will have a traffic signal and a left-turn/through lane for traffic turning left onto Lakeside Avenue or going straight into the DPW access drive, as well as a right-turn lane for traffic travelling east on Lakeside Avenue to Pine Street, where another traffic signal and left-turn lane will allow traffic to continue northbound on the Parkway toward downtown Burlington. The traffic signal at the intersection of the Parkway and Lakeside Avenue will include five separate dedicated phases for traffic from each of the following approaches: the Parkway; eastbound Lakeside Avenue; westbound Lakeside Avenue; DPW‘s driveway; and Fortieth‘s eastern driveway.
¶ 7. The court held a two-day evidentiary hearing in February 2014, and issued a written decision on the merits, containing extensive findings and conclusions, in July 2014. Applicants relied substantially on a detailed report and testimony by an experienced transportation expert analyzing the predicted traffic and safety impacts of the Parkway. His report stated, and the court found, that overall the Parkway “is not a traffic generating project” but rather will “reassign[] traffic from the existing street network” and thereby “generally decrease” congestion in the area. Traffic on Lakeside Avenue from the Parkway intersection to Pine Street, however, was expected to increase. In particular, the traffic expert projected that the Level of Service (LOS) — a standard measure of delays per vehicle at intersections — at Fortieth‘s еastern driveway for both the morning and afternoon “peak hours” would increase as a result of the Parkway project from “LOS A” (little
¶ 8. The expert‘s report noted that its projections were based on future traffic forecasts, or “predictive traffic models,” generated years earlier which assumed traffic growth of aрproximately 2.5% annually along Pine Street, whereas actual growth rates had been much lower, on average 0.25% annually. Thus, employing the “actual vehicle volume” on Lakeside Avenue generated a “built-in reserve capacity” for the system to handle more traffic with fewer delays than the model forecast.1
¶ 9. In light of the foregoing, the trial court concludеd that, “if the[] predicted delays are realized, the traffic attempting to exit Fortieth‘s property may experience unreasonable congestion” and, as a result, “may result in unsafe conditions” if frustrated drivers decided to enter the intersection when lights are yellow or red. (Emphasis added.) Based on the conditional nature of the identified impacts, the trial сourt approved the project but determined to impose conditions focused on “monitoring and reporting, as well as a right of action” if further evidence substantiated “that the Parkway is creating unreasonable traffic congestion and unsafe traffic conditions.” Accordingly, the court ordered applicants to “perform traffic studies and signal warrant analysis” at specified intersections, including Lakeside Avenue and the Parkway, semi-annually for the first year of operation and annually for years two and three; to submit written reports of the monitoring results to the District Commission and Fortieth; and to “work in good faith” with Fortieth to “resolve any traffic congestion and safety issues.” If these efforts failed to achieve resolution, thе court provided that Fortieth could petition the Commission “to reopen its consideration of the application currently before the Court” within sixty days of receipt of the final traffic report. The court thereupon
¶ 10. Under our standard of review, the environmental court determines the credibility of witnesses and weighs the persuasive effect of evidence, and we will not overturn its factual findings unless, taking them in the light most favorable to the prevailing party, they are clearly erroneous. In re Vill. Assocs. Act 250 Land Use Permit, 2010 VT 42A, ¶ 7, 188 Vt. 113, 998 A.2d 712. Thus, the court‘s findings “will not be disturbed merеly because they are contradicted by substantial evidence” but only where the party challenging them demonstrates that “there is no credible evidence to support them.” In re Eastview at Middlebury, Inc., 2009 VT 98, ¶ 10, 187 Vt. 208, 992 A.2d 1014 (quotations omitted). We review issues of law or statutory interpretation de novo. In re Vill. Assocs., 2010 VT 42A, ¶ 7.
¶ 11. Fortieth maintains that the conditions of approval imposed by the trial court here were not supported by the evidence and findings, exceeded the court‘s authority, and were insufficient to mitigate the project‘s traffic and safety impacts. The argument is predicated substantially on Fortieth‘s assertion that the court found unequivocally “that the Parkway as proposed will cause unreasonable congestion” and “will result in deterioration of the LOS experienced by Fоrtieth‘s users from the current A . . . to the E and F unacceptable even under” AOT‘s traffic standards. Thus, Fortieth asserts that the conditions requiring mere monitoring and reporting were inadequate to mitigate the Parkway‘s adverse traffic and safety impacts. See
¶ 12. As noted, however, the trial court‘s findings under Criterion 5 were conditional; it did not find that the project “will” but rather “may” cause unreasonable traffic congestion or unsafe
¶ 13. Fortieth further asserts that the trial court “exceeded its authority” by imposing a condition on a nonparty to the application. More specifically, Fortieth asserts that, by directing the parties “to work in good faith to resolve any traffic congestion and safety issues,” the court necessarily required that Fortieth “alter the use of its property to alleviate the unreasonable congestion which will result from the Parkway.” We discern no impediment, however, to а court generally directing the parties in a proceeding before it to proceed in good faith. See, e.g.,
¶ 15. In response to this argument by Fortieth, applicants respond that their burden of production was merely “to provide enough evidence for the court to rule on what the project‘s impacts are,” thereby allowing the court to impose any mitigating conditions it deemed appropriate. Apрlicants understate the initial evidentiary burden under Criterion 5. See State v. Baker, 154 Vt. 411, 414, 579 A.2d 479, 480 (1990) (noting that “burden of production” is generally carried by establishing “prima facie case on each of the elements“). Nevertheless, we agree with the trial court that applicants met the burden of production here, as the detailed traffic-study report coupled with the evidence showing that its traffic projections were dramatically overstated in material respects with respect to the Parkway project and Lakeside Avenue location, were sufficient to establish prima facie compliance with Criterion 5.
¶ 16. Finally, Fortieth claims that the trial court improperly “shifted the burden to Fortieth to show that congestion would be reduced by altеrnative design of the Parkway/Lakeside Avenue/Eastern Access intersection,” and in so doing erroneously rejected the alternatives proffered by Fortieth. Again the claim is unpersuasive, as we have clearly held that the opposing party‘s burden under
¶ 17. Fortieth overstates the record evidеnce in this regard, which consisted largely of a general concession by applicants’ traffic expert that “some of th[e] congestion issue with the Fortieth driveway would be alleviated if the . . . driveway were aligned [with] the Champlain Parkway . . . to make a four-way intersection.” Fortieth‘s claims to the contrary notwithstanding, the expert did not acknowledge that the altеrnative design would be substantially safer or less confusing, and Fortieth introduced no evidence showing how this redesigned alternative would be engineered, its environmental effects, impact on other components of the Parkway project, and estimated quantitative reduction in traffic congestion and delays. Accordingly, we discern no basis to disturb the trial court‘s finding that Fortieth failed to provide sufficient “details of [the alleged] improvement or the corresponding impacts on traffic,” and no ground to disturb the judgment.
Affirmed.
