History
  • No items yet
midpage
In re Champlain Parkway Act 250 Permit (Fortieth Burlington LLC, Appellant)
129 A.3d 670
Vt.
2015
Read the full case

Background

  • The City of Burlington and Vermont AOT sought an Act 250 permit amendment to construct the Champlain Parkway, a redesigned, two-lane roadway connecting I-89 to downtown Burlington.
  • The project was divided into three segments; earlier approvals and partial construction existed for segments 1 and 2, segment 3 required review.
  • Fortieth Burlington, LLC owns a commercial property adjacent to the planned Parkway/Lakeside intersection; primary access is via an eastern driveway ~150 feet from the Parkway intersection.
  • A traffic expert for applicants predicted reassignment of traffic generally reducing congestion, but forecasted significant LOS deterioration at Fortieth’s eastern driveway (from LOS A to LOS E/F) under modeled growth assumptions.
  • The trial court found the predicted adverse effects conditional ("may" occur) because the traffic model used overstated growth; it approved the permit subject to monitoring, reporting, and a good‑faith resolution requirement with Fortieth plus a procedure to reopen review if problems emerged.
  • Fortieth appealed, arguing the conditions were unsupported or insufficient, the court misallocated burdens, and the court erred in rejecting Fortieth’s design alternative (realigning to a four‑way intersection).

Issues

Issue Plaintiff's Argument (Fortieth) Defendant's Argument (City/AOT) Held
Adequacy of conditions under Act 250 Criterion 5 Court found Parkway will cause unreasonable congestion; monitoring/reporting conditions inadequate to mitigate impacts Court’s findings were conditional ("may" occur); monitoring/reporting and reopening procedure appropriately tailored Conditions upheld as supported by evidence and findings; monitoring/reporting appropriate given uncertainty
Authority to direct parties / impose obligations on non‑party Court exceeded authority by effectively requiring Fortieth to alter property use to mitigate congestion Court may direct parties to proceed in good faith; it did not mandate specific property changes No error; court did not impose concrete obligations requiring Fortieth to change property use
Burden of production and proof under §6088(b) Applicants failed initial burden—applicants’ own evidence showed unreasonable congestion so court should have denied permit or required mitigation Applicants met burden of production with detailed traffic study; conditional findings justified Applicants met initial burden of production; opposing party retains burden to show adverse effect and propose alternatives
Rejection of Fortieth’s alternative intersection design Aligning driveway to create a four‑way intersection would materially reduce congestion and mitigate impacts Fortieth offered no detailed engineering, environmental, or quantitative evidence to support feasibility/benefit Court did not err in rejecting the alternative for lack of sufficient detail and proof

Key Cases Cited

  • In re Vill. Assocs. Act 250 Land Use Permit, 188 Vt. 113, 998 A.2d 712 (Vt. 2010) (standard of review for environmental court findings and credibility determinations)
  • In re Eastview at Middlebury, Inc., 187 Vt. 208, 992 A.2d 1014 (Vt. 2009) (factual findings will not be disturbed unless unsupported by credible evidence)
  • State v. Baker, 154 Vt. 411, 579 A.2d 479 (Vt. 1990) (discussion of burden of production/prima facie case)
  • In re Goddard Coll. Conditional Use, 111 A.3d 1285 (Vt. 2014) (opposing party’s burden includes demonstrating availability of reasonable mitigating steps and alternatives)
Read the full case

Case Details

Case Name: In re Champlain Parkway Act 250 Permit (Fortieth Burlington LLC, Appellant)
Court Name: Supreme Court of Vermont
Date Published: Aug 21, 2015
Citation: 129 A.3d 670
Docket Number: 2014-352
Court Abbreviation: Vt.