IN RE APPLICATION OF NORTHEAST NEB. PUB. POWER DIST. NORTHEAST NEBRASKA PUBLIC POWER DISTRICT ET AL., APPELLANTS, V. NEBRASKA PUBLIC POWER DISTRICT, APPELLEE.
No. S-17-529
Nebraska Supreme Court
Filed June 15, 2018
300 Neb. 237
Nebraska Supreme Court Advance Sheets 300 NEBRASKA REPORTS
Nebraska Power Review Board: Arbitration and Award: Appeal and Error. On an appeal from the decision of an arbitration board convened under Neb. Rev. Stat. § 70-1301 et seq. (Reissue 2009), trial in the appellate court is de novo on the record.- Nebraska Power Review Board: Arbitration and Award: Evidence: Appeal and Error. Despite de novo review, when credible evidence is in conflict on material issues of fact, the appellate court will consider and may give weight to the fact that the arbitration board under
Neb. Rev. Stat. § 70-1301 et seq. (Reissue 2009) observed the witnesses and accepted one version of the facts over another. - Jurisdiction: Appeal and Error. Before reaching the legal issues presented for review, it is the duty of an appellate court to determine whether it has jurisdiction over the matter before it.
- ____: ____. An appellate court has an independent duty to decide jurisdictional issues on appeal, even if the parties have not raised the issue.
- Jurisdiction: Words and Phrases. Subject matter jurisdiction is the power of a tribunal to hear and determine a case in the general class or category to which the proceedings in question belong and to deal with the general subject matter involved.
- Jurisdiction. A lack of subject matter jurisdiction may be raised at any time by any party or by the court sua sponte.
- Jurisdiction: Appeal and Error. When a trial court lacks the power, that is, jurisdiction, to adjudicate the merits of a claim, an appellate court also lacks the power to adjudicate the merits of the claim.
- Arbitration and Award: Jurisdiction: Statutes. An arbitration board under
Neb. Rev. Stat. § 70-1301 et seq. (Reissue 2009), as a creatureof statute, has only such authority as has been conferred upon it by statute. - Statutes: Legislature: Intent. Components of a series or collection of statutes pertaining to a certain subject matter are in pari materia and should be conjunctively considered and construed to determine the intent of the Legislature, so that different provisions are consistent, harmonious, and sensible.
- Public Utilities. Persons receiving similar service from a public power district under similar circumstances cannot be сharged for such service in an arbitrary, designed, dissimilar manner.
- Contracts: Parties. The implied covenant of good faith and fair dealing exists in every contract and requires that none of the parties to the contract do anything which will injure the right of another party to receive the benefit of the contract.
- ____: ____. The nature and extent of an implied covenant of good faith and fair dealing are measured in a particular contract by the justifiable expectations of the parties. Where one party acts arbitrarily, capriciously, or unreasonably, that conduct exceeds the justifiable expectations of the second party.
- ____: ____. A violation of the covenant of good faith and fair dealing occurs only when a party violates, nullifies, or significantly impairs any benefit of the contract.
Appeal from the Power Review Board. Affirmed.
Steven D. Davidson and David C. Levy, of Baird Holm, L.L.P., for appellants.
Kile Johnson and Corey Wasserburger, of Johnson, Flodman, Guenzel & Widger, and John C. McClure, of Nebraska Public Power District, for appellee.
HEAVICAN, C.J., CASSEL, STACY, and FUNKE, JJ., and STEINKE, District Judge.
CASSEL, J.
I. INTRODUCTION
This is our first opinion addressing an appeal from an arbitration board‘s decision under
II. BACKGROUND
1. OVERVIEW OF WHOLESALE RATE DISPUTE PROCESS
Nebraska‘s public policy is to “provide adequate electrical service at as low overall cost as possible, consistent with sound business practices.”2 To further that policy, “electric service should be provided by nonprofit entities including public power districts, public power and irrigation districts, nonprofit electric cooperatives, and municipalities.”3 Public power districts are required by law to fix rates which are fair, reasonable, and nondiscriminatory.4
In 1979, the Legislature enacted
A party who is unsatisfied with the arbitration board‘s decision may appeal to reverse, vacate, or modify the decision.13 To do so, the party must file a notice of aрpeal with the Nebraska Power Review Board within 30 days after the arbitration board‘s decision is filed with the Nebraska Power Review Board.14 “Trial in the appellate court shall be de novo on the record.”15 As noted, this is our first such decision concerning such an appeal from the arbitration board. We now turn to the facts of the case.
2. CONTRACTS
NPPD, a public power district, derives the majority of its revenue from wholesale power supply contracts with political subdivisions in Nebraska. These wholesale power supply contracts often are the largest single financial obligation of the purchasing political subdivision.
The appеllants (hereinafter purchasers) are political subdivisions engaged in the distribution of electricity to retail electric customers. They are wholesale customers of NPPD.
The 2002 WPC included a 20-year term beginning on January 1, 2002. After December 31, 2021, the 2002 WPC would automatically renew from year to year unless terminated with 5 years’ notice by either party.
The 2002 WPC obligated wholesale customers to purchase their full energy requirements from NPPD for the first 6 years of the contract. After that point, a wholesale customer could limit or reduce its purchases of demand and energy from NPPD in varying amounts depending on the length of advance notice provided to NPPD. To limit purchases meant that a customer could continue to buy power in the same amount as on the date of its notice to NPPD, but that it would not buy any future growth in its electricity from NPPD going forward. To reduce purchases meant that the customer could purchase less than its full requirements from NPPD. The 2002 WPC imposed no fee or rate increase in exchange for the privilege to limit or reduce purchases. Each purchaser had given, or intended to give, notice to NPPD of its intention to limit or reduce its purchases, which reductions would commence at various times on and after January 1, 2017.
The 2002 WPC listed different types of costs that NPPD was authorized to include in its revenue requirement for rate-setting purposes. One such cost was “amounts reasonably required to be set aside in reserves for items of costs the payment of which is not immediately required, such as . . . post-retirement employee benefit reserves.” Thus, the 2002 WPC allowed NPPD to include in its revenue requirements a reasonable amount to be set aside for other postemployment benefits (OPEB). OPEB are benefits promised to employees once they retire. They are unfunded liabilities associated with past service.
In 2009, NPPD formed a contract strategy team to look at options for extension of the 2002-era contracts. NPPD desired more certainty in its revenue stream than that provided by
In 2013, NPPD initiated negotiations to replace the 2002 WPC with a new standard wholesale contract. The negotiations resulted in a 20-year contract beginning on January 1, 2016, and ending on December 31, 2035 (2016 WPC). A customer under the 2016 WPC could not limit or reduce its purchases unless NPPD failed to meet certain performance standards. NPPD decided to charge extеnding and nonextending customers the same general firm power service rate. But as an incentive to get customers to execute a new contract, NPPD created a discount for renewing customers. Thus, the 2016 WPC provides a rate discount through December 31, 2021, at an amount to be approved by the NPPD board of directors. Purchasers did not execute the 2016 WPC.
3. FUNDING OPEB OBLIGATION
Prior to 2007, NPPD funded its OPEB obligation on a “pay-as-you-go” basis. In 2007, the Governmental Accounting Standards Board implemented Governmental Accounting Standards Board Statement No. 45. This statement required NPPD to use actuaries to calculate and identify its unfunded OPEB liability and include those amounts in notes to its financial statements. It allowed NPPD to amortize the unfunded OPEB liability over a period up to 30 years. The statement also introduced the concept of the annual required contribution, which is the theoretical amount, if contributed consistently each year, that would fully prefund future retiree benefits associated with benefits earned for past service.
NPPD then explored its options for accounting and reporting of OPEB. One was continuation of “pay-as-you-go.” This had the lowest impact on rates. However, because of a perception that NPPD was not addressing the liability, it had the potential for a negative response from rating аgencies and the investment community. Another option was to put the annual
At that point, NPPD adopted a plan to obtain additional funding in rates. Under the plan, NPPD would continue on the pay-as-you-go basis for 2007. Through rates, NPPD would collect $4 million over the pay-as-you-go amount between 2008 and 2013, and then $10 million above the pay-as-you-go amount thereafter. The money would fund an OPEB trust, which was projected to be fully funded by 2033.
By 2011, actuarial studies showed that NPPD would need to contribute more in order to have the liability funded by 2033. NPPD decided to accelerate the collection of the OPEB liability to the 6-year term remaining in the 2002 WPC. Otherwise, based on purchasers’ notifications of reductions, purchasers would be able to avoid 40 percent of their pro rata share of the OPEB obligation. NPPD estimated the liability to be $155 million. To collect that amount over 6 years, NPPD increased the annual budgeted contribution to the OPEB trust by $25 million. NPPD refеrred to it as a “catch-up.”
The Governmental Accounting Standards Board also created Governmental Accounting Standards Board Statement No. 75, which became effective for fiscal years ending after June 2017. This statement no longer permitted disclosure of OPEB in notes to the financial statements; it required entities such as NPPD to recognize the entire OPEB as a “hard” liability on its balance sheet. Because the statement recommended early implementation, NPPD chose to do so for the 2016 year end.
4. 2016 AND 2017 RATES
The inclusion of the $25 million in OPEB catch-up expense resulted in a 3.7-percent increase for 2016 rates. Wholesale
5. COMPLAINT
Purchasers filed a complaint against NPPD before the arbitration board. They alleged that NPPD violated
At a hearing, the arbitration board received extensive evidence. We will discuss the evidence in more detail in the analysis section of the opinion.
6. ARBITRATION BOARD‘S DECISION
The arbitration board determined that the 2016 and 2017 rates were reasonable. It stated that the OPEB catch-up amounts were reasonable, because they related to the value of the service rendered to purchasers during their years of taking service from NPPD. It further stated that NPPD did not arbitrarily select the amounts to include in the catch-up, but, rather, those amounts were “the product of a systematic study of the actuarial liability of OPEB attributable to prоduction-level services.”
The arbitration board also determined that the 2016 and 2017 rates were nondiscriminatory. It reasoned that the discount merely deferred the collection of the 2016 and 2017 catch-up amounts for customers under the 2016 WPC. The board explained:
Customers under the 2002 WPC and the 2016 WPC are taking the same service from NPPD and charged
the same rate. The customers operate under two separate and differing contracts, fairly negotiated. The 2016 customers gave up some rights they had under the 2002 WPC and accepted new terms including the deferred collection of the OPEB Catch-Up amounts included in the 2016 and 2017 rates. Customers under the 2016 WPC have оver 18 years left in their comm[i]tment to NPPD, whereas [purchasers] have just over 4 years. This differentiated approach is fair and reasonable as relating to the collection of a liability that solely relates to past services.
Finally, the board determined that NPPD did not breach the 2002 WPC or the covenant of good faith and fair dealing. The board therefore denied all of purchasers’ requests and determined that the 2016 and 2017 rates met the standards established by
Purchasers appealed, and we granted their petition to bypass review by the Nebraska Court of Appeals.
III. ASSIGNMENTS OF ERROR
Purchasers assign that the arbitration board erred in (1) failing to find NPPD‘s 2016 and 2017 wholesale rate structure violated
IV. STANDARD OF REVIEW
[1,2] On an appeal from the decision of an arbitration board convened under
V. ANALYSIS
1. JURISDICTION
[3,4] Before reaching the legal issues presented for review, it is the duty of an appellate court to determine whether it has jurisdiction over the matter before it.18 Neither party challenges the arbitration board‘s jurisdiction to decide the matters presented to it. But an appellate court has an independent duty to decide jurisdictional issues on appeal, even if the parties have not raised the issue.19
[5-7] Subject matter jurisdiction is the power of a tribunal to hear and determine a case in the general class or category to which the proceedings in question belong and to deal with the general subject matter involved.20 A lack of subject matter jurisdiction may bе raised at any time by any party or by the court sua sponte.21 When a trial court lacks the power, that is, jurisdiction, to adjudicate the merits of a claim, an appellate court also lacks the power to adjudicate the merits of the claim.22 We begin by considering whether the arbitration board had subject matter jurisdiction over the issues presented to it.
The parties presented three issues to the arbitration board, and those same three issues are before us on appeal. The issues
[8] The arbitration board, as a creature of statute, has only such authority as has been conferred upon it by statute.23 Statutes have clearly empowered an arbitration board to determine a wholesale electric rate dispute.24 But it is less clear whether the arbitration board also has jurisdiction over the contractual issues presented in this case.
[9] Reading the statutes in
An arbitrated dispute may be intertwined with contractual issues. The Legislature clearly contemplated the existence of power contracts.30 Often, such contracts speak to amounts that may be charged for electricity. In order to resolve a dispute, an arbitration board may need to determine whether there was contractual compliance. The arbitration board has authority to “consider only those matters necessary for the resolution of the disputed issues” but it may “not alter or modify any existing contract.”31 We conclude that where, as here, contractual issues are intertwined with a rate dispute, such contractual issues are within the arbitration board‘s jurisdiction.
We note that no party is attacking the constitutionality of the statutes contained in
2. WHETHER RATE STRUCTURE VIOLATES § 70-655(1)
(a) Additional Evidence at Hearing
NPPD presented considerable evidence concerning its efforts to address its unfunded OPEB liability. NPPD‘s wholesale billing manager testified that if NPPD had collected the full unfunded OPEB obligation of $150 million in 1 year, it would have resulted in a rate increase of over 22 percent—a much larger rate increase than the 3.7 percent that was implemented. The manager testified as to the amounts of purchasers’ pro rata shares of OPEB that they could avoid by
NPPD‘s chief financial officer testified that in 2016, NPPD borrowed approximately $23 million on behalf of the 2016 WPC customers by issuing taxable debt to generate bond proceeds. The interest on the borrowing was capitalized through 2021. NPPD borrowed a similar amount under similar terms for the 2017 сatch-up. The chief financial officer explained that purchasers and customers under the 2016 WPC “are both being charged the exact same rate, except for the 2016 contract customers I have borrowed their pro rata share and made that deposit into the OPEB trust and I‘ve recorded a regulatory asset that says they will have to pay that beginning in 2022.” Because the rates are identical, the difference in what is charged and collected is a function of the discount. With the discount, OPEB gets paid from two sources: contributions from ratepayers and investment earnings in the trust.
According to the chief financial officer, the purpose of the discount would be “deferring the collection of that 2016 and now 2017 catch-up amount until 2022 through 2033, the same time period.” She explained that the wholesale customers would pay the same amount, but it would be collected over a different time period. In order for the delayed payments to equate to a payment today, NPPD would have to apply a discount rate between 3.37 and 3.9 percent. The chief financial officer testified that the discount was “a mechanism to fairly collect the OPEB catch-up from two different customer groups.”
Dismukes opined that the rate structure created discrimination between the two sets of customers. He explained that similarly situated customers were being assessed rates that differed for taking similarly situated services. According to Dismukes, there were no cost differences between the two groups of customers. The signing of the 2016 WPC was the only difference, and Dismukes did not believe that the execution of a new contract justified a different rate. He testified that there was no legitimate cost basis supporting the discount mechanism. Based on Dismukes’ knowledge of the industry, he believed that a discount for one subset of customers and not the other constituted rate discrimination.
From a cost-based rate-setting perspective, Dismukes disagreed with testimony to the effect that both groups would ultimately pay the same amount. He pointed out that “a dollar today is not the same as a dollar tomorrow” and that there was a benefit to not making the payment today. He testified that the timing difference created an economiс advantage of sufficient consequence to support a finding of discrimination. Thus, Dismukes opined that NPPD did not set its rates in a manner that was fair, reasonable, and nondiscriminatory.
NPPD‘s expert, Joseph Mancinelli, the general manager and president of a consulting firm specializing in management economics predominantly serving the public power market, disagreed. He opined that NPPD‘s 2016 and 2017 rates were fair, reasonable, and nondiscriminatory. In arriving at that conclusion, he looked at the unfunded accrued OPEB liability, which was incurred over a historical period and was directly attributed to the labor of retirees. He testified that it was proper to recover those costs from customers who enjoyed
Mancinelli explained that there was one rate and that the difference was the source of the funding of the OPEB liability. Because the 2016 WPC customers had a long contract, the cost was financed. But financing was not an option for the 2002 WPC customers, so the funding came out of rate revenues. He stated that the source of the funds created a difference and that difference “is the genesis of what we call the discount.”
Manсinelli believed that the cost of borrowing the money was not materially different from the discount. He testified that the discount was cost based and that it was basically the difference between funding the trust with cash from revenues or funding the trust with borrowed funds. Mancinelli was unaware of any other utility imposing a rate increase for the exclusive purpose of collecting money for an OPEB trust. Although NPPD‘s situation and solution was unique, he opined that it met the test of being fair, reasonable, and nondiscriminatory.
(b) Discussion
Purchasers contend that the rate structure for 2016 and 2017 violates
[10] Purchasers rely on McGinley v. Wheat Belt P.P. Dist.35 In that case, a wholesale distributor informed Wheat Belt
McGinley is distinguishable from the situation at hand. There, Wheat Bеlt wanted to assess the bulk of a surcharge against one class of customers. To do so, it wanted to charge different rates to similarly situated customers. Here, NPPD is charging but one rate—purchasers are charged the same rate as NPPD‘s customers under the 2016 WPC. The difference between the amounts charged to purchasers and the 2016 WPC customers is attributable to a discount for the 2016 WPC customers. Of course, under some circumstances, charging one rate but conferring a discount upon some customers could be discriminatory. But here, as discussed below, there was a reasonable basis for NPPD‘s ratemaking determination.
The discount is tied to the OPEB liability. Thаt liability relates solely to past services of NPPD employees, and purchasers received the benefit of those services. Because a specific portion of OPEB cannot be connected to any particular customer, NPPD allocated the liability on a pro rata basis. It is reasonable for purchasers to pay their pro rata share of
There is a reasonable basis for the discount. If a variance in rates is based upon a reasonable and fair difference in conditions that equitably and lоgically justifies a different rate, any discrimination is not unjust.37 Purchasers opted not to extend their contractual relationship with NPPD; thus, NPPD had a shorter period of time in which to collect purchasers’ pro rata share of the liability. On the other hand, customers under the 2016 WPC extended their relationship with NPPD for an additional 20 years, thereby giving NPPD a longer period of time over which to collect those customers’ pro rata share.
NPPD crafted a plan to collect the OPEB catch-up expense at different times. Under the plan, purchasers pay their portion of the OPEB catch-up expense over the 6 years remaining on their contract, while customers under the 2016 WPC get a discount during those years and will pay the catch-up expense between 2022 and 2033. It is the difference in the remaining terms of the contractual relationship with NPPD between purchasers and customers under the 2016 WPC that allows for the different collection of the OPEB liability. The effort to fund the OPEB trust through catch-up amounts in 2016 and 2017 was an effort to mitigate the risk of shifting the cost of the common liability onto the customers under the 2016 WPC. Under the circumstances of this case, the discount for one group of customers is not discriminatory.
The methodology assured that both classes of customers would pay an equal share of OPEB costs—the difference would be solely in the timing of the payments. Contrary to purchasers’ argument, the financing scheme imposed a future cost sufficient to remedy the advantage that the 2016 WPC customers otherwise would have had from paying their share later. In other words, an approximation of the time value of
3. WHETHER RATE STRUCTURE BREACHED 2002 WPC
Purchasers next argue that the discount constitutes a brеach of the 2002 WPC. It does not. Under the 2002 WPC, purchasers agreed to pay “amounts reasonably required to be set aside in reserves for items” such as OPEB. The catch-up amounts were reasonably within the definition of revenue requirements. This assignment of error lacks merit.
4. WHETHER RATE STRUCTURE BREACHED COVENANT OF GOOD FAITH
[11,12] Finally, purchasers argue that the discount breached the covenant of good faith and fair dealing. The implied covenant of good faith and fair dealing exists in every contract and requires that none of the parties to the contract do anything which will injure the right of another party to receive the benefit of the contract.38 The nature and extent of an implied cоvenant of good faith and fair dealing are measured in a particular contract by the justifiable expectations of the parties. Where one party acts arbitrarily, capriciously, or unreasonably, that conduct exceeds the justifiable expectations of the second party.39
[13] Purchasers claim that giving a discount to the 2016 WPC customers penalized purchasers for exercising their contractual right to purchase energy elsewhere. We disagree. The availability of the discount was not connected to whether a
VI. CONCLUSION
We conclude that NPPD‘s rate structure for 2016 and 2017 was fair, reasonable, and nondiscriminatory. We further conclude that the rate structure did not constitute a breach of either the 2002 WPC or the implied covenant of good faith and fair dealing. Accordingly, we affirm the decision of the arbitration board.
AFFIRMED.
WRIGHT and MILLER-LERMAN, JJ., not participating.
