Case Information
*3
KOZINSKI, Circuit Judge:
Operated by the Army Corps of Engineers (Corps), the Albeni Falls Dam helps provide power to the Pacific Northwest. The Bonneville Power Administration (BPA) is charged with marketing the power generated from the dam. In 2011, the agencies decided to change how they operated the dam during the winter months. We consider whether they complied with the National Environmental Policy Act (NEPA) when they finalized this decision without preparing an environmental impact statement.
FACTS
The Albeni Falls Dam straddles the Pend Oreille River, which connects Lake Pend Oreille and the Columbia River. Completed in 1957 as part of the Federal Columbia River Power System, it is jointly managed by the Corps, BPA and the Bureau of Reclamation. Like other dams in the System, the Albeni Falls Dam is operated to balance a variety of competing objectives, such as flood control, power generation, navigation and wildlife conservation.
Lake Pend Oreille serves as the dam’s reservoir. When water is released from the lake, it drives turbines that generate electricity. This decreases the reservoir’s depth and causes its shoreline to recede. For decades, the Corps maintained the flexibility to generate power during the winter months. In the *4 initial winters of the dam’s operation, starting in the late 1950s, the Corps fluctuated the level of the lake to generate power as needed. In some years, however, the Corps held the lake’s level constant, often near 2051 feet.
In 1995, the Corps determined that allowing the lake’s elevation to drop during the winter months had adverse effects on the kokanee salmon population and so beginning in 1997 began holding the lake’s elevation constant. But in 2009, BPA urged the Corps to return to a more flexible approach to winter dam management. After two years of discussions and a public comment period, the agencies confirmed in a 2011 environmental assessment (EA) that they planned to follow through with BPA’s proposal. The plan for “flexible winter power operations” gives the Corps the option each winter to store water in the reservoir and then release it through the dam according to power needs. Thus, instead of keeping the lake’s level constant, the Corps may allow it to rise and fall by as much as five feet during the winter.
The EA concludes that the proposed winter fluctuations will have no significant environmental impact. Accordingly, the agencies decided to move forward with the proposal without preparing an environmental impact statement (EIS). 40 C.F.R. §§ 1501.4(b)–(c), 1508.9. Petitioner challenges this decision as a violation of NEPA and asks us to require BPA to prepare an EIS. We have original jurisdiction pursuant to the Northwest Power Act. 16 U.S.C. § 839f(e)(5).
DISCUSSION
NEPA, which applies to all federal agencies, 42 U.S.C. § 4332, doesn’t dictate particular policy outcomes; instead, it regulates the manner in which agencies arrive at them. Specifically, for all “major Federal actions significantly affecting the quality of the human environment,” the agency must prepare an EIS, which is a detailed study examining the environmental consequences of its decision. Id. *5 6 I DAHO C ONSERVATION L EAGUE V . BPA § 4332(2)(C). An EA is meant to briefly document the reasons for the agency’s determination whether an EIS is required. 40 C.F.R. § 1508.9; see Cascadia Wildlands v. Bureau of Indian Affairs , 801 F.3d 1105, 1111 (9th Cir. 2015). The EA here concludes that no EIS is required because the proposed action will not “result in any new significant impacts to the human environment.”
1.
NEPA only requires the preparation of an EIS when a
proposed federal action is major.
Upper Snake River
Chapter of Trout Unlimited
v.
Hodel
,
Upper Snake River
involved a challenge to the Bureau of
Reclamation’s management of the Palisades Dam.
Upper
Snake River
,
If the agencies in our case have consistently fluctuated winter lake levels, formalizing that approach would not be a major federal action because the agencies would be “doing nothing new, nor more extensive, nor other than that contemplated when the [Albeni Falls Dam] was first operational.” Id. at 235. The Corps fluctuated the elevation of Lake Pend Oreille in many winters prior to 1997, and various dam management strategies considered in a 1995 EIS included elements of what is now the proposal for flexible winter operations. Accordingly, the question is whether holding lake levels constant from 1997 to 2011 changed the status quo. If not, then reverting to the previous regime doesn’t change the status quo either.
The Corps discussed holding winter lake levels constant
in an EA published in 1995. This document reviewed a
proposal for a three-winter test to hold the lake at a high
minimum and found that doing so would have no significant
environmental impacts. BPA and the Corps subsequently
published Records of Decision putting this plan into action.
We have explained that the time for an EIS is when an agency
undertakes a “significant shift of direction in operating
policy.”
Grand Canyon Trust
v.
U.S. Bureau of Reclamation
,
Actions taken with respect to winter dam management since 1995 reinforce the conclusion that there was no change to the status quo. As mentioned, the plan to hold winter lake levels constant began as a three-year test. The agencies managing the dam twice decided to carry forward this management strategy at the urging of the U.S. Fish and Wildlife Service. It’s also notable that, since 2000, an interagency team has met each year to recommend the lake’s constant elevation for the coming winter. In four winters from 1996 to 2011, Lake Pend Oreille was held near 2051 feet; the lake was also held near that elevation in eight winters between 1980 and 1995. Upper Snake River *7 921 F.2d at 235 (finding that even if an agency had only engaged in a proposed action sporadically in the past, that was enough to show that repeating that action did not change the status quo). As in Upper Snake River , the agencies here considered each year how to manage the Albeni Falls Dam based on that year’s conditions. The Corps never relinquished its authority to fluctuate the lake’s elevation in response to power demands: The Corps’ 2002 Water Control Manual notes that Lake Pend Oreille “is usually operated” within a one-foot range above the winter minimum, but that “storage above [that minimum] may be used for . . . unscheduled hydropower operations.” Thus, from 1997 to 2011, the agencies maintained the discretion they have always had to respond annually to changing conditions. See id. Continuing to do so did not change the status quo.
Because the period when the agencies held winter lake
levels constant did not change the operational status quo,
neither does the decision to revert to flexible winter
operations. Power generation has always been among the
central concerns in operating the dam. For example, a 1948
Army report on plans for the dam explained that, “[d]uring
the fall and winter period when regional power supply is
lowest and power loads are greatest, the stored water [at Lake
Pend Oreille] will be drawn upon for power purposes.” The
EA echoes that report, noting that “[t]he purpose of [flexible
winter operations] is to more efficiently use the available
water storage capabilities at AFD to generate power during
the winter” and that “[s]toring water in the near term will
provide power benefits at a future date when that water is
released[,] . . . depend[ing] on power prices, load demand,
and conditions at [another dam].” As the EA further
explains: “Historically, winter power operations have been
associated with [releasing] water for power. Water was
stored for power operations during the winter in the 1980s
and early 1990s.” Thus, in some winters the lake has
fluctuated, and in others it hasn’t. Accordingly, the agencies
will be doing “nothing new, nor more extensive, nor other
than that contemplated when the project was first
operational.”
Upper Snake River
,
Petitioner argues
that
Upper Snake River
is
distinguishable because “[u]nder existing operations, the
Corps maintains steady lake levels throughout winter,” while
under flexible winter operations, “lake levels would be raised
and lowered over a five-foot range up to three times every
winter for the life of the Dam.” But Petitioner’s view of
*8
10
I DAHO C ONSERVATION L EAGUE V . BPA
“existing operations” is incorrectly limited to operations since
the publication of the 1995 EA. Moreover, Petitioner
mischaracterizes the proposal. According to the current EA,
it’s “unlikely” that lake levels would rise and fall over a five-
foot range three times every winter—a variety of factors, such
as power demand and weather conditions, will influence how
the agencies operate the dam each year. Additionally, there
may still be winters where the agencies hold the lake’s level
constant in order to facilitate kokanee reproduction. Thus,
the flexible winter operations proposal comprises elements of
both earlier and more recent management strategies. These
details support the conclusion that the agencies charged with
operating the Albeni Falls Dam will do so in accordance with
the status quo.
Id.
;
see also Grand Canyon Trust
,
Petitioner finally argues that implementing flexible winter
operations requires an EIS because the continued operation of
the Albeni Falls Dam is itself a major federal action that
significantly affects the human environment. 40 C.F.R.
§ 1508.18(a) (“Actions include new and continuing activities
. . . .”). But decisions made as a part of the ongoing operation
of a federal project must themselves “rise to the level of
major federal actions to warrant preparation of an EIS.”
Upper Snake River
,
*9 2. Petitioner claims the EA arbitrarily concludes that
flexible winter operations will have only an incremental
impact on the spread of the flowering rush, an invasive
species that was discovered around Lake Pend Oreille in
2008. Because the decision adopting flexible winter
operations doesn’t trigger NEPA’s requirement to publish an
EIS, this and Petitioner’s other challenges to the EA’s finding
of no significant impact are moot.
Upper Snake River
Petitioner also argues in passing that, because the
flowering rush has never been considered in a NEPA
document, “BPA arbitrarily limited its analysis of flowering
rush impacts to only the incremental impacts attributable to
the new winter fluctuations; BPA never considered the
significance of the spread of flowering rush in relation to the
Dam’s year-round operation.” Agencies have a continuing
duty to “prepare supplements to . . . final environmental
impact statements”
if
there are “significant new
circumstances or information relevant to environmental
concerns” that were not considered in an earlier EIS.
40 C.F.R. § 1502.9(c)(1);
Marsh
,
Petitioner may well have a colorable claim that the
agencies managing the Albeni Falls Dam must supplement
the SOR EIS with an analysis of how year-round dam
operations, as compared with flexible winter operations
specifically, affect the “seemingly inevitable spread of this
invasive species.” But this question is outside the scope of
this case; Petitioner sought review of “the final decision . . .
adopting the ‘Flexible Winter Power Operations’ at Albeni
Falls Dam.” Petitioner’s opening brief similarly frames the
issue as whether BPA violated NEPA by “approving the new
winter operations without preparing an up-to-date EIS” and
concludes by asking us to “reverse and remand the . . . EA
*10
approving the Flexible Winter Operations.” Petitioner only
mentions in a footnote that BPA might need to prepare a
supplemental EIS addressing the impact of year-round dam
operations on the flowering rush. We do not “ordinarily
consider matters on appeal that are not specifically and
distinctly argued” in an opening brief,
Laboa
v.
Calderon
We address Petitioner’s remaining claims in a memorandum disposition filed concurrently herewith.
DENIED .
