826 F.3d 1173
9th Cir.2016Background
- Albeni Falls Dam (managed by Army Corps, BPA, and Bureau of Reclamation) has historically been operated to balance flood control, power generation, navigation, and wildlife; Lake Pend Oreille is its reservoir.
- From dam completion through the early 1990s, the Corps sometimes fluctuated winter lake levels to generate power; beginning in 1997 the Corps adopted a winter policy of holding lake levels constant to protect kokanee salmon.
- In 2011 BPA and the Corps issued an Environmental Assessment (EA) adopting “flexible winter power operations,” restoring the Corps’ discretion to store and release water in winter (allowing up to ~5 feet of fluctuation) and concluded no Environmental Impact Statement (EIS) was required.
- Petitioner (Idaho Conservation League) challenged the decision under NEPA, seeking an order requiring BPA to prepare an EIS; this court has original jurisdiction under the Northwest Power Act.
- The EA acknowledged the spread of an invasive plant (flowering rush) as new information but did not prepare a supplemental EIS addressing year‑round dam operations; petitioner raised that issue but only fleetingly and primarily challenged the EA approving flexible winter operations.
Issues
| Issue | Plaintiff's Argument | Defendant's Argument | Held |
|---|---|---|---|
| Whether agencies’ adoption of flexible winter operations required preparing an EIS under NEPA | Reverting to multi‑foot winter fluctuations is a major federal action with significant environmental impacts (so an EIS is required) | The decision merely returns to operational flexibility within the range historically available; it does not change the status quo and thus no EIS is required | The court held no EIS required; the change is within the project’s historic operational range and not a major new action |
| Whether the 1997–2011 period of steady winter levels altered the operational status quo such that reverting is a major change | Steady levels since 1997 made current operations the status quo; reverting is a new, long‑term shift | Historic practice (pre‑1997 fluctuations, EAs and RODs contemplating both approaches, and retained discretionary authority) shows no change to the underlying status quo | The court held the 1997–2011 practice did not convert historical flexibility into a permanently different baseline; reverting is consistent with the status quo |
| Whether the EA’s conclusion of only incremental impacts (e.g., on flowering rush) was arbitrary | EA arbitrarily limited analysis to incremental effects and ignored need for a supplemental EIS on flowering rush spread | Because the decision did not trigger an EIS, challenges to the EA’s FONSI are moot; supplemental EIS claim was not timely or properly raised on appeal | The court found these claims moot in this challenge and declined to consider the supplemental‑EIS argument raised only in a footnote; petitioner may raise it later against a different agency action |
| Whether ongoing operation of the dam itself requires an EIS for each operational decision | The dam’s continued operation significantly affects the environment, so EIS required for this operational change | Routine operational decisions consistent with past conduct do not each require an EIS; only major operational shifts do | The court rejected the argument that every operational decision requires an EIS and stressed practicality: routine, historically consistent decisions need not trigger an EIS |
Key Cases Cited
- Cascadia Wildlands v. Bureau of Indian Affairs, 801 F.3d 1105 (9th Cir. 2015) (EA documents the agency’s determination whether an EIS is required)
- Upper Snake River Chapter of Trout Unlimited v. Hodel, 921 F.2d 232 (9th Cir. 1990) (operating within the range originally available to an agency does not constitute a major federal action requiring an EIS)
- City of Davis v. Coleman, 521 F.2d 661 (9th Cir. 1975) (‘‘major’’ in NEPA context reinforces but does not have independent meaning from ‘‘significantly’’)
- Grand Canyon Trust v. U.S. Bureau of Reclamation, 691 F.3d 1008 (9th Cir. 2012) (an EIS is required for a significant shift in operating policy)
- San Luis & Delta‑Mendota Water Auth. v. Jewell, 747 F.3d 581 (9th Cir. 2014) (discussing when changes trigger NEPA’s EIS requirement)
- Marsh v. Oregon Natural Resources Council, 490 U.S. 360 (1989) (agencies need not issue a supplemental EIS for every new piece of information; requiring one for every change would make decisionmaking intractable)
- Laboa v. Calderon, 224 F.3d 972 (9th Cir. 2000) (appellate courts generally do not consider arguments not presented in the opening brief)
