HIP HEIGHTENED INDEPENDENCE AND PROGRESS, INC., a New Jersey Not-for-Profit Corporation; Peter Gimbel; United Spinal Association, a New York Not-for-Profit Corporation, Appellants in No. 11-3799 v. The PORT AUTHORITY OF NEW YORK AND NEW JERSEY, Appellant in No. 11-3673.
Nos. 11-3673, 11-3799.
United States Court of Appeals, Third Circuit.
Argued May 23, 2012. Filed: Sept. 11, 2012.
695 F.3d 262
IV. Conclusion
Because the BIA answered the wrong question and applied an incorrect legal standard in reviewing Roye‘s claims for deferral of removal under the CAT, we will grant his petition for review, vacate the BIA‘s May 14, 2011 opinion and order, and remand the matter to the BIA. On remand, the BIA should review the IJ‘s conclusion that the evidence of record demonstrates that Roye‘s persecutors will physically and sexually abuse him in a manner that rises to the level of torture under the CAT, and decide whether Jamaican public officials will consent to or acquiesce in any such abuse.
David J. Popiel, Esq. [Argued], Community Health Law Project, South Orange, NJ, Michael H. Isaac, Esq., Robert B. Stulberg, Esq. [Argued], Broach & Stulberg, New York, NY, Attorneys for Appellees/Cross-Appellants.
Frank C. Morris, Jr., Esq. [Argued], Epstein, Becker & Green, Washington, DC, David W. Garland, Esq., Epstein, Becker & Green, Newark, NJ, George P. Cook, Esq., Jason T. Watson, Esq., Port Authority of New York & New Jersey, Jersey City, NJ, Megan Lee, Esq., Port Authority of New York & New Jersey, New York, NY, Attorneys for Appellant/Cross-Appellee.
Before: RENDELL, FUENTES and HARDIMAN, Circuit Judges.
OPINION OF THE COURT
HARDIMAN, Circuit Judge.
The Port Authority of New York and New Jersey (Authority) appeals the District Court‘s summary judgment, which orders the Authority to make modifications to its Grove Street Station to bring it into compliance with the Americans with Disabilities Act (ADA) of 1990,
I
A
The Authority‘s wholly owned subsidiary, the Port Authority Trans-Hudson Corporation (PATH), operates the Grove Street Station in Jersey City, New Jersey, which is the subject of this lawsuit. The Station has three levels—street, mezzanine, and platform—and two street-level entrance sides—east and west. The Station can serve an eight-car train. The mezzanine is not connected between the east and west sides. One staircase connects the east mezzanine to a platform-level corridor, which leads out to the platform itself.
The Station was built in 1910, and in the 1970s PATH closed the east entrance and constructed two entrances on the west side. As reflected in a 2001 report, in 2000 PATH planned to expand the Station to accommodate ten-car trains and persons with disabilities, a project that would have involved the construction of a new entrance and two elevators on the west side. After September 11, 2001, and the resulting closure of two of the Authority‘s stations—Exchange Place in New Jersey and World Trade Center in Manhattan—ridership increased at the Grove Street Station. Citing concerns about congestion and safety, PATH scrapped its renovation plans and undertook a different “fast track” project to reopen the east entrance.
Construction began in 2002 and concluded in 2005. The project involved building a new street-level pavilion and focused on renovating the connections between the street and mezzanine levels on the east side only. The pavilion was built four inches above the sidewalk to comply with flood-plain construction requirements, and
In 2006, after PATH had finished construction, its engineering department concluded that elevator installation was feasible only on the west side of the Station. PATH believed that the east-side platform would be too crowded with an elevator, leading to safety concerns, and that construction on the east side would result in service disruption and possible flooding.
B
Plaintiffs filed this lawsuit in state court in 2007, and the Authority removed the case to the District Court. The complaint alleges that the Grove Street Station renovations triggered an obligation under the ADA to make the Station accessible to handicapped persons. It also alleges violations under New Jersey‘s Law Against Discrimination and certain New Jersey construction code provisions. The District Court dismissed the state-law claims, reasoning that, under the terms of the interstate compact that created the Authority, one state cannot unilaterally regulate the joint entity. See hip, Inc. v. Port Auth. of N.Y. & N.J. (hip I), No. 07-2982, 2008 WL 852445, at *4-6 (D.N.J. Mar. 28, 2008). Following further proceedings and failed settlement attempts, the parties filed cross-motions for summary judgment.
The District Court entered summary judgment for Plaintiffs. During discovery, five schemes for making the east entrance ADA-compliant were produced, and the Authority‘s engineering department evaluated each of those schemes. The Court held that of the five, two—Schemes 4 and 5, which propose installation of a mezzanine-to-platform Limited Use Limited Access (LULA) elevator—are feasible. Consequently, the Court ordered the Authority to make the east entrance accessible. hip, Inc. v. Port Auth. of N.Y. & N.J. (hip II), No. 07-2982, 2011 WL 3957532, at *3-5 (D.N.J. Sept. 6, 2011). The parties timely filed notices of appeal.
II
The ADA is a complex law codified in numerous statutes in the United States Code. Regulations have been promulgated by the Department of Transportation to implement those statutes. And pursuant to
For example, and as a preliminary matter, the regulations and the ADAAG impose different obligations on different kinds of construction projects. “New facility” construction is distinguished from the “alteration” of existing facilities. See
The District Court treated the Station renovations as an alteration but recognized that they “may also qualify as new con
Second, we think the District Court‘s characterization of the construction project as an alteration was sound. The regulations clearly distinguish between new construction and alterations, and because the obligations of the builder under each scheme are different, a given construction project must be classified as one or the other. An alteration is “a change to an existing facility, including, but not limited to, remodeling, renovation, rehabilitation, reconstruction, historic restoration, changes or rearrangement in structural parts or elements, and changes or rearrangement in the plan configuration of walls and full-height partitions.”
As noted, this case comes to us on the appeal of an order resolving cross-motions for summary judgment. “When reviewing a district court‘s summary judgment decision in an ADA case, we exercise plenary review, applying the same standard as the district court.” Sulima, 602 F.3d at 184 (citing Turner v. Hershey Chocolate USA, 440 F.3d 604, 611 (3d Cir. 2006)). “Summary judgment is appropriate if, viewing the record in the light most favorable to the non-moving party, there are no genuine issues of material fact and the moving party is entitled to judgment as a matter of law.” Id.; accord
III
The touchstone of our analysis in this appeal is the Authority‘s obligation—triggered because it altered the Station—to make the Station accessible “to the maxi
As used in this section, the phrase to the maximum extent feasible applies to the occasional case where the nature of an existing facility makes it impossible to comply fully with applicable accessibility standards through a planned alteration. In these circumstances, the entity shall provide the maximum physical accessibility feasible. Any altered features of the facility or portion of the facility that can be made accessible shall be made accessible. If providing accessibility to certain individuals with disabilities (e.g., those who use wheelchairs) would not be feasible, the facility shall be made accessible to individuals with other types of disabilities (e.g., those who use crutches, those who have impaired vision or hearing, or those who have other impairments).
Having discerned the appropriate regulatory framework that governs this appeal, we turn to the substantive disputes. The Authority proffers five reasons why it is entitled to summary judgment or, alternatively, summary judgment was wrongly entered for Plaintiffs. Two of these arguments—that the ADA did not require the Authority to make the platform accessible because it was not an “altered portion[]” of the facility,
In considering the parties’ arguments under the ADA, it is important to bear in mind that the ADA‘s obligations are triggered at the time the construction
A
The Authority‘s first preserved argument is that the ADA does not and cannot mandate a public transit authority to purchase subterranean property rights held by another party, which it would be required to do under Schemes 4 and 5. It frames this argument under
In Disabled in Action of Pennsylvania v. Southeastern Pennsylvania Transportation Authority (DIA v. SEPTA), 635 F.3d 87 (3d Cir.2011), we considered a similar issue regarding whether a district court can order ADA compliance notwithstanding the fact that the defendant does not presently possess property rights necessary to make the ordered modifications. In that case, DIA sued SEPTA and the City of Philadelphia over accessibility barriers at two subway access points, the 15th Street Courtyard and City Hall Courtyard. Id. at 91. Early in the litigation, the city and DIA reached a settlement in which the city agreed to allow SEPTA to build an elevator on its property at the 15th Street Courtyard and was dismissed from the suit as a result. Id. We affirmed the district court‘s order that SEPTA make both courtyards accessible. Id. at 97. Because compliance at the City Hall Courtyard also
Of course here, unlike DIA, we have less of a clear indication that Jersey City is willing to cooperate with the Authority in making the station accessible. Though Plaintiffs have presented evidence that the mayor has indicated that the City could allow access to the property, it is the City Council that must vote on any such matter. Because we lack any similar indication from the City Council, we cannot assume that the Authority will be able to acquire the land rights it needs to implement Scheme 4 or 5. Accordingly, summary judgment need not be entered for the Authority, either.
As we see it, the mere fact that the Authority would now have to acquire land from a third-party is not sufficient to render the proposed accommodations per se infeasible. Indeed, in considering feasibility, as we must, as of the time of the original construction, the Authority may have been able to negotiate for the use or ownership of the relevant land in the manner it had to facilitate construction of the headhouse for the east entrance. In light of the mayor‘s letter to the Plaintiffs, this may still be the case. There is, however, an open factual question as to whether the relief ordered by the District Court would now be ineffective because the City Council might refuse to negotiate a subterranean easement or sale to the Authority. On this point, we remand for further development of the record.
While it may be the case that joinder of the City becomes appropriate, as we see it, this issue can just as easily be resolved by introducing evidence of the City Council‘s intent to approve or deny the Authority‘s use or acquisition of the land required under Schemes 4 and 5. Until the Authority has demonstrated that the Council will not allow it to use the land, we cannot conclude that the proposed accommodations are infeasible within the meaning of the ADA.
B
The next two issues focus on the consequences of implementing Schemes 4 and 5. Because the appropriate inquiry under the ADA is backward-looking, and because Schemes 4 and 5 have been presented as prospective possibilities, those schemes may not be identical to those asserted by Plaintiffs at trial on remand. However, we recognize that the proposed modifications that might have been feasible between 2002 and 2005 may closely resemble the concept behind Schemes 4 and 5—LULA elevators to the platform—and therefore we proceed to address the feasibility concerns raised by the parties with respect to those schemes.
The parties dispute whether both of the schemes found feasible by the District Court require the removal of a load-bearing part of the Station or are otherwise technically infeasible. In addition to the definition set forth above, technical infeasibility exists where the modification “has little likelihood of being accomplished because existing structural conditions would
The parties did not develop a good factual record on this issue below. The Authority argues that “a roof structure” would need to be removed in Scheme 4 and avers there were “[f]actual conflicts” over the load-bearing-member issue in the District Court. Authority Br. 23-24. The Authority‘s reply brief provides further citations to record evidence that suggests, but stops short of explicitly stating, that in order to implement Schemes 4 or 5 the Station‘s “structural conditions would require removing or altering a load-bearing member which is an essential part of the structural frame.” See Authority Reply Br. 16-18 (citing JA 415, 810, 1601-02). To offer just one example, the Authority‘s feasibility report on Plaintiffs’ proposed Schemes 4 and 5 notes that those schemes “[m]ay require structural modifications to ‘pressure slab’ below stair at station entrance.” (JA 1601-02.) The Authority claims this “pressure slab” is a load-bearing member falling within the technical infeasibility exception.
By contrast, Plaintiffs assert there is no record evidence that the removal of a load-bearing member would be necessary under either scheme and they present an expert who opines that Schemes 4 and 5 are feasible. The Authority counters that Plaintiffs’ expert does not understand the meaning of technical infeasibility.
The lack of clarity in the record indicates there is a genuine dispute of material fact over whether a load-bearing member would need to be removed to make the east side accessible, whether Schemes 4 and 5 are otherwise technically infeasible, and whether they would have been infeasible had they been incorporated into the original construction plans. Therefore, these issues must be submitted for trial.
C
Finally, the Authority contends that because Schemes 4 and 5 do not pass scrutiny under a fire-safety standard (NFPA 130), their implementation would not be “feasible” under the ADA. NFPA 130, titled “Standard for Fixed Guideway Transit and Passenger Rail Systems,” contains numerous recommendations for designing rail systems to minimize risks associated with fire. The Authority highlights two of these recommendations as relevant to Schemes 4 and 5. First, as the District Court put it, “a bidirectional corridor must be at least 44 inches wide to ensure safe ingress and egress.” hip II, 2011 WL 3957532, at *4. Second, according to the Authority, evacuation must be possible “from the most remote point on the platform to a point of safety in six minutes or less.” Authority Br. 25. The District Court held that the corridor width in Schemes 4 and 5 exceeded the 44-inch minimum but the Court did not address the egress time restriction.
The parties disagree about the deference owed to NFPA 130 under the ADA‘s framework. Plaintiffs characterize it as a
We believe the “maximum extent feasible” test can account for such safety standards. “[T]he phrase to the maximum extent feasible applies to the occasional case where the nature of an existing facility makes it impossible to comply fully with applicable accessibility standards through a planned alteration.”
We cannot discern the significance of NFPA 130 from the record before us, in large part because of the manner in which the issue was presented by the Authority to the District Court. The Authority did not raise NFPA 130 until after the Court heard argument on the motions for summary judgment (even if it did raise evacuation concerns more broadly), and the expert affidavits it submitted generically reference exit time but do not squarely address the six-minute limitation. Highly technical arguments require specificity in presentation, and while we cannot say that the Authority failed to raise this argument before the District Court, we understand why the District Court believed the corridor-width issue to be the only one presented by NFPA 130. At the same time, Plaintiffs’ expert was unfamiliar with NFPA 130 and offered no opinion on the Station‘s egress capacity. On this record, both the nature of the NFPA 130 requirement and whether Schemes 4 or 5 satisfy it are unclear and may be addressed by the District Court on remand.
In sum, there are three triable issues of fact related to the feasibility of Schemes 4 and 5 under
IV
Plaintiffs’ cross-appeal concerns the District Court‘s dismissal of their state-law claims on the basis that the application of state law to an agency operating under an interstate compact is permissible only if provided for in the compact. Because the Authority‘s compact does not so provide, we will affirm.
“A bi-state entity, created by compact, is ‘not subject to the unilateral control of any one of the States that compose the federal system.‘” Int‘l Union of Operating Eng‘rs, Local 542 v. Del. River Joint Toll Bridge Comm‘n, 311 F.3d 273,
In Delaware River, we considered a compact that did not contain the “concurred in” language that is frequently found in interstate compacts to allow a state to modify a compact with legislation, provided its partner state passes similar legislation. Id. Finding the absence of that language significant, we nonetheless reviewed various approaches taken by federal and state courts interpreting “concurred in” clauses in compacts. Some courts require an express statement of intent by both state legislatures to modify the compact, and other courts permit “complementary or parallel” actions of two state legislatures to imply the intent to modify the compact. Id. at 276-79. Ultimately we applied the “express intent standard” and found there was no evidence of intent by the states “to amend the Compact or apply their collective bargaining laws to the” bi-state entity. Id. at 280.
The compact between New York and New Jersey that created the Authority provides that “[t]he port authority shall have such additional powers and duties as may hereafter be delegated to or imposed upon it from time to time by the action of the legislature of either state concurred in by the legislature of the other.”
Instead, relying on New York case law, Plaintiffs urge the panel to distinguish between “internal operations” and “external conduct” of the Authority in applying these compact principles. See Agesen v. Catherwood, 26 N.Y.2d 521, 311 N.Y.S.2d 886, 260 N.E.2d 525, 526-27 (1970); see also Dezaio v. Port Auth. of N.Y. & N.J., 205 F.3d 62, 65 (2d Cir.2000) (discussing Agesen but declining to apply New York state employment discrimination laws to the Authority, implicitly assuming that employment matters relate to the internal operation of the Authority). Specifically, Plaintiffs claim that while a state cannot regulate the Authority‘s internal operations on its own, it can regulate the external conduct of the agency. Plaintiffs define external conduct as actions relating to “health and safety.” See Agesen, 260 N.E.2d at 526-27.
There is no basis in Third Circuit precedent for the internal-external distinction, nor would such a distinction necessarily be well-founded.3 But we need not consider
Plaintiffs also contend that “the Compact contains no express surrender of state sovereignty regarding external relations, including, among other things, barrier-free construction codes and related civil rights statutes,” the subjects of Plaintiffs’ state-law claims, meaning the Authority lacks the power to avoid the reach of these New Jersey laws. Plaintiffs Br. 34. This argument misapprehends the notion of sovereignty surrender discussed in Hess and Delaware River. While a court must be hesitant to find a surrender of sovereignty where it is ambiguous, here there is no question the states intended to create the Authority, and such surrender has already been recognized by numerous courts, including the United States Supreme Court in Hess. By expressly creating the bi-state entity, New York and New Jersey relinquished all control over the Authority unless otherwise stated in the compact. Under Delaware River, that autonomous entity cannot be unilaterally regulated by New Jersey.
V
For the foregoing reasons, we will vacate the summary judgment of the District Court, we will affirm its dismissal of the state-law claims, and remand for further proceedings consistent with this opinion.
