Hertzel v. Town of Putnam ValleyHertzel v. Town of Putnam Valley
Motion by the respondent, inter alia, for leave to reargue stated portions of an appeal from an order of the Supreme Court, Putnam County, entered August 1, 2012, which was determined by decision and order of this Court dated October 1, 2014.
Upon the papers filed in support of the motion and the papers filed in opposition thereto, it is
Ordered that the motion is granted to the extent that reargument is granted and, upon reargument, the decision and order of this Court dated October 1, 2014 (Hertzel v Town of Putnam Val., 121 AD3d 641 [2014]), is recalled and vacated, and the following decision and order is substituted therefor, and the motion is otherwise denied:
In a hybrid action, inter alia, to recover damages for injury to property, and, in effect, proceeding pursuant to
Ordered that the notice of appeal from so much of the order as granted those branches of the defendant/respondent‘s motion which were for summary judgment dismissing the causes of action asserted, in effect, pursuant to
Ordered that the order is modified, on the law, by deleting the provisions thereof granting those branches of the defendant/respondent‘s motion which were for summary judgment dismissing the first, second, and eighth causes of action, and substituting therefor provisions denying those branches of the motion; as so modified, the order is affirmed; and it is further,
Ordered that one bill of costs is awarded to the plaintiffs/petitioners.
In April 2007, the Peekskill Hollow Brook (hereinafter the brook) flooded and damaged a retaining wall and a garage building (hereinafter the subject property) in the defendant/respondent, Town of Putnam Valley. The garage building, the rear of which bordered the brook, was occupied by an automotive repair business, the plaintiff/petitioner Kappel‘s Garage, Inc., doing business as George‘s Super Service (hereinafter Kappel‘s Garage). The subject property was owned by the
After the April 2007 flooding, the Town inspected the subject property, determined that the retaining wall and the rear portion of the garage building were unsafe, and directed Valley Corners and Hertzel to make repairs. Hertzel shored up the slab of the garage building, which had been undermined, but did not repair either the building‘s foundation or the retaining wall, despite the Town‘s repeated demands that he do so.
On May 21, 2008, the Town Board of the Town of Putnam Valley (hereinafter the Town Board), acting pursuant to the
Valley Corners and Hertzel failed to commence repairs by August 4, 2008, and, on August 5, 2008, the Town put the job out to bid. In September 2008, a contractor employed by the Town demolished the retaining wall and the rear portion of the garage building, rebuilt the retaining wall, and erected a fence and planted arbor vitae along the rear of the property adjacent to the retaining wall. Pursuant to
In the third, fourth, fifth, sixth, and seventh causes of action, the plaintiffs sought, in effect, to annul the tax assessment referable to the cost of demolition of the retaining wall and rear wall of the building and the rebuilding of the retaining wall and, by implication, sought to annul the Resolution authorizing the demolition and the assessment against the subject property. They likewise contended that the Town failed to give them proper notice and an opportunity to be heard, as required by
The Supreme Court erred, however, in granting those branches of the Town‘s motion which were for summary judgment dismissing the first, second, and eighth causes of action. These causes of action assert claims, inter alia, for damages resulting from the destruction of a portion of the garage building and the interruption of the plaintiffs’ business. Pursuant to
In light of our determination, we need not address the plaintiffs’ remaining contentions. Balkin, J.P., Dickerson, Roman and Miller, JJ., concur.