CALIFORNIA SUITES, INC., Appellant, v RUSSO DEMOLITION INC. et al., Defendants, and CITY OF NEW YORK et al., Respondents.
Supreme Court, Appellate Division, First Department, New York
May 31, 2012
95 A.D.3d 144 | 946 N.Y.S.2d 55
Altman Schochet LLP, New York City (Irina Fulman, Zalman Schochet and Michael A. Valentine of counsel), for appellant.
Michael A. Cardozo, Corporation Counsel, New York City (Victoria Scalzo, Stephen J. McGrath and Karen Selvin of counsel), for respondents.
OPINION OF THE COURT
Tom, J.P.
In September 2006, plaintiff, the owner of a six-story hotel located at 610 West 111th Street in Manhattan, known as the Ellington Hotel, was issued a building permit by the Department
In November 2006, the DOB notified plaintiff of its intent to revoke the permit based on the objections raised on the audit unless plaintiff demonstrated why the permit should not be revoked. In May 2007, the DOB revoked all permits and directed that all work cease. In June 2008, the DOB conducted a structural integrity assessment of the illegally altered building and concluded that due to improper construction, the “structural stability of the building [hotel] is affected,” and a “[l]ife-safety risk is present due to the lack of required egress from the building—accesses to the roof and exits from the roof.” The DOB issued an “Emergency Declaration” dated June 23, 2008, informing plaintiff that the “building, or [a] portion thereof, has been declared unsafe and in imminent peril,” that “because of the severity of the condition,” the structure “must be repaired or demolished immediately” and that “responsibility to take such action is yours.” The emergency declaration further states that the City would perform the necessary remedial work at plaintiff‘s expense if plaintiff failed to cure the defects. The New York City Department of Housing Preservation and Development (DHPD) sent plaintiff an “Urgent Notice,” dated July 14, 2008 advising that it would retain a contractor, at plaintiff‘s expense, to cure the emergency condition unless plaintiff acted immediately. Plaintiff failed to respond, and DHPD engaged defendant Russo Demolition Inc. to conduct remedial work. Between August 18 and August 25, 2008, Russo Demolition undertook and completed the demolition of the steel structure erected on the roof of the premises.
On August 26, 2008, plaintiff commenced this action against Russo Demolition alleging trespass, conversion and negligence. The complaint has since been amended, first to add the municipal defendants and, again, to name a second Russo defendant, A. Russo Wrecking, Inc. (collectively, Russo). The second amended complaint asserts that on or about August 19, 2008, Russo, acting on behalf of the municipal defendants, unlawfully entered onto plaintiff‘s hotel property and removed the steel structure from the roof. The complaint further asserts that Russo failed to provide any evidence of its authority to remove the steel structure despite plaintiff‘s repeated requests.
As noted, the original complaint, which had alleged trespass and conversion, named only Russo Demolition as defendant.
It may be fairly inferred from the second amended complaint that plaintiff alleges Russo lacked lawful authority to remove the steel structure from the roof of plaintiff‘s hotel because DHPD likewise lacked lawful authority to direct Russo to perform the necessary demolition work. However, the issue of lack of notice was first raised in plaintiff‘s opposition papers to defendant‘s dismissal motion, which, relying on Calamusa v Town of Brookhaven (272 AD2d 426 [2000]) and Scott v Town of Duanesburg (176 AD2d 989 [1991]), advanced the theory that the municipal defendants’ failure to provide notice and opportunity to be heard before the demolition work was performed “is a violation of due process rights for which liability will attach” (internal quotation marks omitted). Therefore, by way of cross motion, plaintiff sought to amend the complaint to allege explicitly that the demolition work was performed “without providing to Plaintiff notice of the Municipal Defendants’ intent to demolish the steel structure and an opportunity to cure the existing condition, to the extent such condition was dangerous or unsafe.”
Defendants’ motion to dismiss asserted that the complaint fails to state a cause of action for conversion, trespass or negligence, arguing that absolute immunity extends to acts within the exercise of administrative discretion—here, the determination that removal of the steel structure was warranted. Furthermore, the municipal defendants alleged that plaintiff had received the requisite notice of the proposed removal of the dangerous offending structure by certified mail.
In opposition, plaintiff contended that it “never received such notice.” The opposing papers included the affidavit of Alan Lapes, the owner of the property, who stated, “I never received these notices. Moreover, no agent of California Suites Inc. ever signed any ‘certified mail’ receipt allegedly delivered with said notice.”
In reply, the City agencies furnished affidavits by their employees attesting to their regular business practice in issuing
In further opposition to the motion (denominated “surreply“), plaintiff submitted another affidavit from Alan Lapes stating that “the Secretary of State was directed to forward process it accepted on behalf of the corporation to 610 West 111th Street” and that the Department of Buildings had previously “mailed all notices relating to the condition of the building to the 610 address.” Lapes did not deny that plaintiff maintains an office at 850 West End Avenue, where notices were sent by the municipal defendants; remarkably, he stated that plaintiff “has used the 850 address to receive financial and tax information from the Department of Finance in connection with the subject building . . . and for no other purpose.” Nor did Lapes offer any explanation why Samal Nur should not be regarded as plaintiff‘s agent or employee despite having signed for the certified mailing on behalf of plaintiff in that capacity. Nowhere in Lapes‘s affidavit does he deny that Samal Nur was plaintiff‘s employee. The Lapes affidavit was accompanied by the affirmation of counsel raising, for the first time, the contention that notice of the proposed demolition was required to be given “in accordance with the civil practice law and rules of the state of New York” (citing
This matter is now before us on plaintiff‘s appeal from the award of summary judgment dismissing the action as against the municipal defendants (
Plaintiff cites Calamusa (272 AD2d 426) and Scott (176 AD2d 989), in support of its contention that its constitutional rights to due process were violated because the municipal defendants failed to provide notice to plaintiff of the demolition and an opportunity to cure the defective condition. Although the cited cases are facially similar to this matter, they involve different statutes and the particular factual and procedural context is unclear.
“A municipality may demolish a building without providing notice and an opportunity to be heard if there are exigent circumstances which require immediate demolition of the building to protect the public from imminent danger. In this case, immediate action was not required and there was time to provide notice and an opportunity to be heard. Therefore, the failure to provide the same is a violation of due process rights for which liability will attach” (Calamusa, 272 AD2d at 427 [citations omitted]).
In Scott, as in the instant matter, the complaint alleged trespass, negligence and intentional destruction of property (but not conversion). The Third Department held that “defendant did not properly act according to its police powers in demolishing plaintiff‘s campsite structure because it failed to comply with plaintiff‘s statutory and due process rights to notice and an opportunity to be heard before the structure was declared unsafe” (Scott, 176 AD2d at 991). The Court rejected the defense of immunity, stating, “The decision to demolish without giving notice and an opportunity to be heard cannot be classified as a discretionary decision as fundamental due process compels the result . . . removing discretion” (id. at 992).
These cases both involve the issue alluded to by the second amended complaint—the lack of authority to exercise emergency powers without giving notice of the proposed demolition—but the result in each case appears to rest on the failure to give the plaintiff any notice at all that such action was imminent.
To satisfy the constitutional requirement of due process, notice need only be “reasonably calculated, under all the circumstances, to apprise interested parties of the pendency of the action and afford them an opportunity to present their objections” (Mullane v Central Hanover Bank & Trust Co., 339 US 306, 314 [1950]). The record amassed before the motion court amply demonstrates plaintiff‘s awareness that the condition of its building was regarded as unsafe by the DOB. Furthermore, notices issued by the Department prior to directing removal of the steel structure from plaintiff‘s premises were directed to an address where plaintiff concedes that it maintains an office, and a certified mailing receipt confirms that plaintiff received notice
The record in this matter reflects that plaintiff, its agents and employees, were apprised of every aspect of the municipal defendants’ administrative actions taken in regard to the property. In late September 2006, plaintiff obtained a building permit to expand its hotel by adding a five-story addition to the roof of the building. In mid-October, the Department issued a stop-work order, followed by an audit of the building site, after which the Department sent an extensive list of objections to the project‘s architect. A notice of intent to revoke the building permit was issued in late November, and the permit was ultimately revoked in May 2007.
A year later, two DOB representatives conducted an inspection of the premises, accompanied by Alan Lapes. The resulting special report dated June 19, 2008 found, among other items, that the requisite access to and egress from the roof were lacking because the doors from the stairs to the roof were blocked by the installed steel structures; the mandatory three-foot-six-inch-high parapet wall was partially demolished for the installation of the steel beams; and there were 18 outstanding DOB violations against the premises. The engineer‘s report noted the building permit issued to plaintiff in this case anticipated that the structural steel for the proposed five-story addition would consist of “14-inch W-beams” that would “bear on the 13-inch existing exterior wall of the building.” Instead, the engineer observed that only 12-inch beams had been installed and that “the existing 8-inch parapet wall is being used as a bearing wall,” rather than the 13-inch exterior wall, the condition of which he noted to be “questionable due to weathering and mortar deterioration,” affecting the building‘s structural stability. The engineer further noted, as a life-safety risk, that “both doors from the stair bulkhead to the roof and accesses to both fire escapes . . . are blocked by installed steel structures.”
A subsequent notice dated July 14, 2008 informed the owner that the DHPD “will engage a contractor to cure the emergency condition unless you act immediately to correct the condition.” This notice was sent by certified mail and signed for by Samal Nur. These 2008 notices, submitted by the municipal defendants in connection with their motion, were mailed to plaintiff at 850 West End Avenue in Manhattan. In support of the motion, the municipal defendants submitted documents sent to plaintiff at the 850 West End Avenue address. Included were notices sent by the Department of Finance, as well as copies of an indenture and a mortgage stating plaintiff‘s office address to be 850 West End Avenue. Also submitted was a copy of the building permit for the project showing that it was issued to Alan Lapes, identified as the general contractor and conducting business as Metro Maintenance Corporation. The certified mailing of notice of the imminent demolition (documented by a signed receipt and tracking notice), with plaintiff‘s admission that it maintains an office at the address where the mailing was received, together with other notices mailed to the same location, and evidence of the agencies’ mailing procedures establish due notice (see Matter of Cruz v Wing, 276 AD2d 307 [2000], lv denied 96 NY2d 702 [2001]), which the bare denial of plaintiff‘s principal is insufficient to rebut (see Nassau Ins. Co. v Murray, 46 NY2d 828, 829-830 [1978]; Northern v Hernandez, 17 AD3d 285, 286 [2005]).
The substance of plaintiff‘s opposition to the dismissal motion was that the Department of Buildings made the determination to remove the steel structure on the roof of plaintiff‘s hotel and forwarded a memorandum to that effect to DHPD without first affording plaintiff notice. Between the time opposing papers and the surreply were filed, plaintiff changed its argument from an assertion that it received no notice of the proposed agency action to the assertion that it did not receive what it now contends is the proper notice of such action, that is, notice mailed to the address on file with the Secretary of State. While the lack of any notice implicates a constitutional violation of plaintiff‘s due process rights, the lack of proper notice merely implicates a “violation of lawful procedure” (
By invoking a constitutional basis for its claim against the municipal defendants, the complaint seeks to obviate plaintiff‘s failure (1) to pursue its administrative remedies and (2) to observe the time limitation of
As the Court of Appeals remarked, “[W]hen the claim is one against a governmental body or officer, the form of action that immediately springs to mind is a proceeding brought under CPLR article 78, a traditional, and surely the most common, vehicle for challenging a governmental decision or action” (McBarnette, 84 NY2d at 201). If, as plaintiff contends, its due process rights were violated by the absence of administrative notice of the proposed demolition of its property, its claim has a constitutional basis, and plaintiff is thereby relieved of the general requirement to proceed administratively (see Watergate II Apts. v Buffalo Sewer Auth., 46 NY2d 52, 57 [1978]). If, however, the constitutional claim fails (because it can be established that plaintiff had received administrative notice of the proposed demolition), the second amended complaint must then be read to allege that the City agencies exceeded their jurisdiction (
Since the record conclusively establishes that plaintiff received notice of the proposed demolition, its due process claim is without foundation. Divested of its constitutional predicate, the complaint merely alleges that the municipal defendants failed to follow proper procedure in arriving at the determination to demolish the steel structure erected on the roof of plaintiff‘s premises and, in view of that omission, exceeded their authority in undertaking the demolition work. As discussed, these issues must be raised in a special proceeding under
It bears emphasis that permitting plaintiff to avoid the need to pursue and exhaust its administrative remedies by resorting to the simple expedient of refusing to respond to notice of pending administrative action and claiming a denial of due process
Due process is not a sword to be wielded offensively to thwart the legitimate government interest in ensuring public safety but a shield to guard against the unjustified taking of property. To rule that plaintiff should be given the opportunity to seek monetary damages for its intentional failure to appear in pursuance of its due process rights makes a mockery of the concept.
It is axiomatic that “discretionary municipal acts may never be a basis for liability, while ministerial acts may support liability only where a special duty is found” (McLean v City of New York, 12 NY3d 194, 202 [2009]). Discretionary acts “involve the exercise of reasoned judgment which could typically produce different acceptable results whereas a ministerial act envisions direct adherence to a governing rule or standard with a compulsory result” (Tango v Tulevech, 61 NY2d 34, 41 [1983]; see also Arteaga v State of New York, 72 NY2d 212 [1988]). Here, defendants’ determination that the situation constituted an emergency condition either under
Finally, plaintiff‘s contention that Supreme Court erred in treating the municipal defendants’ application as a motion for summary judgment without first informing the parties (
Here, both sides submitted evidentiary material to the motion court bearing on the question of notice. The municipal defendants provided extensive documentary evidence and affidavits to show that notices were mailed and received by plaintiff, and plaintiff submitted multiple affidavits by its principal disputing the same. Plaintiff even went so far as to intimate, in its surreply, that the motion must be denied because the documentary evidence was contradicted by the affidavit of Alan Lapes, thereby precluding summary disposition. Having laid bare their proof on the issue of notice by presenting opposing evidence and disputing its import and effect, the parties clearly invited the motion court to resolve the question based on their submissions (see e.g. Mic Prop. & Cas. Ins. Corp. v Custom Craftsman of Brooklyn, 269 AD2d 333 [2000]). While the municipal defendants’ motion was directed at the sufficiency of the pleadings (
Accordingly, the order of the Supreme Court, New York County (Cynthia S. Kern, J.), entered May 24, 2010, which granted the City defendants’ motion to dismiss the complaint as
Saxe, Sweeny, Richter and Manzanet-Daniels, JJ., concur.
Order, Supreme Court, New York County, entered May 24, 2010, affirmed, without costs.
