EDWIN P. HARRISON, Plaintiff-Appellant, and UNITED STATES OF AMERICA, Party in Interest, v. WESTINGHOUSE SAVANNAH RIVER COMPANY, Defendant-Appellee.
No. 98-1037
United States Court of Appeals for the Fourth Circuit
May 17, 1999
PUBLISHED. Argued: October 28, 1998. Appeal from the United States District Court for the District of South Carolina, at Aiken. Charles E. Simons Jr., Senior District Judge. (Ca-94-2332-1-6)
Before MURNAGHAN and WILLIAMS, Circuit Judges, and BLAKE, United States District Judge for the District of Maryland, sitting by designation.
COUNSEL
ARGUED: Richard E. Miley, North Augusta, South Carolina, for Appellant. Lawrence Graeme Bell, III, CROWELL & MORING,
OPINION
MURNAGHAN, Circuit Judge:
Relator Harrison (“Harrison” or “Appellant“) brought a claim under the False Claims Act,
I.
A.
Since 1989, WSRC has been the management and operations contractor for the United States Department of Energy at the Savannah River Site (“SRS“), a nuclear facility near Aiken, South Carolina. WSRC‘s contract with the government provides that WSRC is entitled to receive the allowable costs it incurs on the project in addition to an award fee.
As a part of its contractual responsibilities, and pursuant to policy and regulations, when WSRC decides to subcontract certain tasks necessary for the operation and management of the SRS, WSRC pro-
Count 1:2 False-Statements About Need for Subcontractor and Price of Subcontract
In July 1992, WSRC identified a need for training related to in-tank precipitation process operations, known as “ITP Training” (hereinafter “ITP Training Project“). As part of its standard practice, WSRC included in the technical package that was sent to the DOE for review a “Make or Buy Analysis” (“MBA“), which analyzed the cost effectiveness of buying the ITP Training services as opposed to providing those services in-house. (Amended Complaint at ¶ 24.) The MBA stated that while WSRC had the capacity to provide the service, WSRC did not have personnel available. The MBA stated further that since the service was of a one-time variety and of a short-term nature (1.5 years), it was not practical for WSRC to hire full-time staff to meet the need.
Harrison alleges that WSRC made the following misrepresentations to the government as part of its “plan and scheme” to obtain DOE approval for WSRC‘s use of a subcontractor rather than use of WSRC‘s own personnel to develop and implement the ITP Training Project:
- That the project was “short term” such that subcontract personnel would be needed for no more than 1.5 years; WSRC knew that developing and implementing the ITP Training Project would take at least several years, (Amended Complaint ¶ 24(a));
- That providing the ITP Training was not “a continuing need” but rather was a “one time variety” project; WSRC knew that the ITP Training Project would be a continuous on-going need for many years, (Amended Complaint ¶ 24(b));
- That there was no need to hire permanent staff to fulfill the ITP Training requirement; WSRC knew that the ITP Training Project would require qualified trainers for a decade or more, (Amended Complaint ¶ 24(c);
- That “Other Costs” for such things as computers, etc., would be zero; WSRC knew that the subcontractor would need to purchase computers to perform the subcontract work, (Amended Complaint ¶ 24(e)); (See also Amended Complaint ¶ 33); and
- That the ITP Training services could be obtained on a firm-fixed price basis at a “total cost” of $2,750,000; WSRC intended to subcontract the ITP Training Project on a cost-plus-fixed-fee basis and knew that the training would cost substantially more than $2,750,000, (Amended Complaint ¶¶ 24(d), 22(a)).
Count 2: False Certification of No Conflict of Interest
General Physics Corporation (“GPC“), a subcontractor company doing business with WSRC at SRS, employed Relator Harrison as one of its vice-presidents. He worked for GPC in Aiken, directing some of GPC‘s subcontract work with WSRC at SRS. On August 12, 1992, GPC received from WSRC a RFP for the ITP Training Project.
During the next several weeks, Harrison alleges that he became aware that GPC personnel developing GPC‘s proposal were requesting and improperly receiving insider information from WSRC‘s Subcontract Technical Representative (“STR“). Harrison allegedly found that WSRC‘s STR, who would later participate in the technical evaluation of the bids on the ITP Training Project, was supplying insider information not available to other bidders. He also alleges that he learned that WSRC‘s STR had permitted GPC employees to participate in preparation of portions of the RFP.3 (Amended Complaint ¶ 28.) WSRC awarded the ITP Training subcontract to GPC.
(a) In its proposal, GPC represented that it had no conflicts of interest related to the ITP Training subcontract. This certification was submitted to the DOE by WSRC as part of the “Justification for Award” in the PUR package. Harrison alleges that (1) the contacts between WSRC and GPC violated DEAR conflict of interest regulations, (2) WSRC was obliged to comply with these regulations and to certify
(b) Harrison also alleges that WSRC had an affirmative obligation to report undisclosed conflicts of interest with its subcontractors when a subcontract was significantly increased. WSRC‘s failure to alert the DOE to these conflicts, even after Harrison had given notice to WSRC about the conflicts, allegedly makes all claims submitted under several expansions of the GPC subcontract fraudulent. (Amended Complaint ¶¶ 27 (first sentence), 36.)
Count 3: Misrepresentation of Subcontract Terms
(a) Harrison alleges that after the GPC subcontract was approved, WSRC misrepresented the scope of work for the ITP Training Project. According to Harrison, the subcontract did not set forth any requirement for subcontractor personnel to perform procedure development. Less than three months into the ITP Training subcontract, however, WSRC knowingly misrepresented to the DOE that the existing ITP Training subcontract in fact provided for procedure revision and upgrade not to exceed 5% of the total scope of work. Based upon WSRC‘s misrepresentation, the DOE approved WSRC‘s request for adding work to the subcontract on a “sole-source” basis at a cost of $880,000. (Exhibit C to Amended Complaint; Amended Complaint ¶ 22(b) and (c).)
(b) Separately, Harrison alleges that before this $880,000 procedure development cost was approved, WSRC had directed GPC to perform procedure development activities. Since at that time, these activities were allegedly not approved costs under the contract, Harrison alleges that WSRC‘s payment requests incorporating these activities were fraudulent. (Amended Complaint ¶ 34.)
Count 4: False Signature
Harrison alleges that a purchase requisition form submitted to the DOE contained “fraudulent and/or unauthorized signatures” and WSRC knew that at least one of these was fraudulent. (Amended Complaint ¶ 23.)
Count 5: Breach of Fiduciary Duty
Harrison alleges that WSRC held itself out as being experienced and qualified to maintain a nuclear facility and had contractual and fiduciary duties to act in the DOE‘s best interest. WSRC supposedly violated these duties by engaging “in a scheme and plan to increase the cost of performance and its fees under its contract, acting with actual knowledge or with reckless disregard for the truth or with deliberate ignorance.” (Amended Complaint ¶ 25(a)-(g).)
Count 6: Knowing Misrepresentation of Costs of Subcontract
In addition to the allegations under Count 1, Harrison asserts that WSRC knowingly under-estimated the cost of the GPC subcontract by allowing GPC to understate its overhead costs for GPC‘s ITP Training Project bid. The under-estimated costs were submitted to the DOE as part of the PUR package. This was done in an effort to get the DOE to approve subcontracting. (Amended Complaint ¶ 31.)
Count 7: Increased Labor Costs
Harrison alleges that GPC changed the personnel on the GPC subcontract bid in order to raise the labor costs in that bid. GPC then assigned personnel with lower salaries than those on the bid to perform under the GPC subcontract. (Amended Complaint ¶ 32.)
Count 8: Over-Charging Via “Other Direct Costs” Account
Harrison alleges that WSRC directed GPC and other subcontractors to purchase supplies and charge them to “Other Direct Costs,” when WSRC “had a duty to acquire them through its own procurement system at lower costs.” (Amended Complaint ¶ 33.) By this practice
Count 9: Lack of Management Controls
Harrison alleges that WSRC by contract and regulation was required to maintain effective systems of management to safeguard against theft, fraud, and waste and did not do so. (Amended Complaint ¶ 38.)
Count 10: Conspiracy
Though not clearly pled in his Amended Complaint, Harrison asserts in his brief that once the ITP Training subcontract was awarded, WSRC and GPC then engaged in a conspiracy to routinely “sole source” modifications of the ITP Training Project, increasing the subcontract cost from $2,461,161 to more than $9.3 million without allowing any competition for the provision of the services represented by the additional $6.9 million. (Appellant‘s Br. at 10.) (Cf. also Amended Complaint ¶¶ 27, 37.)
B.
The district court granted WSRC‘s motion to dismiss under
II.
This Court reviews de novo a district court‘s dismissal for failure to state a claim upon which relief may be granted under
A. Pleading Fraud with Particularity5
Since Appellant in this case alleges fraud, his claim is subject to
First, the rule ensures that the defendant has sufficient information to formulate a defense by putting it on notice of the conduct complained of. ... Second,
Rule 9(b) exists to protect defendants from frivolous suits. A third reason for the rule is to eliminate fraud actions in which all the facts are learned after discovery. Finally,Rule 9(b) protects defendants from harm to their goodwill and reputation.
United States ex rel. Stinson, Lyons, Gerlin & Bustamante, P.A. v. Blue Cross Blue Shield of Georgia, Inc., 755 F. Supp. 1040, 1056-57 (S.D. Ga. 1990). A court should hesitate to dismiss a complaint under
B. The False Claims Act
Originally passed during the Civil War in response to overcharges and other abuses by defense contractors, Congress intended that the False Claims Act,
- knowingly presents, or causes to be presented, [to the government] a false or fraudulent claim for payment or approval;
- knowingly makes, uses, or causes to be made or used, a false record or statement to get a false or fraudulent claim paid or approved by the Government; or
- conspires to defraud the Government by getting a false or fraudulent claim allowed or paid.
The term “knowingly” has a special meaning within the context of the False Claims Act:
“knowing” and “knowingly” mean that a person, with respect to information—
- has actual knowledge of the information;
- acts in deliberate ignorance of the truth or falsity of the information; or
- acts in reckless disregard of the truth or falsity of the information,
and no proof of specific intent to defraud is required.
Liability under each of the provisions of the False Claims Act is subject to the further, judicially-imposed, requirement that the false statement or claim be material.7 Materiality depends on “whether the
The Supreme Court has cautioned that the False Claims Act was not designed to punish every type of fraud committed upon the government. See United States v. McNinch, 356 U.S. 595, 599 (1958). In order for a false statement to be actionable under the False Claims Act it must constitute a “false or fraudulent claim.” “[T]he statute attaches liability, not to the underlying fraudulent activity or to the government‘s wrongful payment, but to the `claim for payment.‘” United States v. Rivera, 55 F.3d 703, 709 (1st Cir. 1995). Therefore, a central question in False Claims Act cases is whether the defendant ever presented a “false or fraudulent claim” to the government.
Interpreting the last word of the phrase is fairly easy. The False Claims Act states that a claim “includes any request or demand ... for money or property” where the government provides any portion of the money or property requested.
Taking the phrase “false or fraudulent claim” in its entirety, though, is more complicated, because the phrase has become a term of art.
The district court‘s narrow interpretation of the phrase “false or fraudulent claim” is incorrect. First, there are problems with the cases relied upon by the district court. McNinch was decided under a criminal version of the False Claims Act and the Court explicitly relied on a rule of lenity-type analysis in reaching its interpretation of the statute. McNinch, 356 U.S. at 598. The current statute is not criminal, and so a rule of lenity approach is no longer appropriate. Also, McNinch was a very narrow holding reflecting the facts of that case. No request for payment from the government had yet been made when McNinch was decided, and the Court left open the question whether the False Claims Act would apply if and when a claim on the government fisc was made. Id. at 599 n.6. Subsequent cases confirm that the act which did not violate the False Claims Act in the factual context of McNinch does lead to False Claims Act liability when the government fisc is finally called upon. See United States v. Rivera, 55 F.3d at 707, and cases cited therein. The second case relied upon by the district court, Thompson, had already been vacated when the district court relied upon it. See United States ex rel. Thompson v. Columbia/HCA Healthcare Corp., 125 F.3d 899 (5th Cir. 1997), aff‘g in part and vacating in part 938 F. Supp. 399 (S.D. Tex. 1996).
Second, and more importantly, the district court‘s approach is in contradiction to the legislative history of the statute and to many courts, including the Supreme Court, that have addressed the issue.
According to Congress, after the 1986 amendments the False Claims Act should be broadly construed:
each and every claim submitted under a contract, loan guarantee, or other agreement which was originally obtained by
means of false statements or other corrupt or fraudulent conduct, or in violation of any statute or applicable regulation, constitutes a false claim.
S. Rep. No. 99-345, at 9, reprinted in 1986 U.S.C.C.A.N. at 5274 (emphases added). The courts have implemented the principles embodied in the above-quoted passage in a variety of ways.
1. False Certification Cases
A number of courts in a variety of contexts have found violations of the False Claims Act when a government contract or program required compliance with certain conditions as a prerequisite to a government benefit, payment, or program; the defendant failed to comply with those conditions; and the defendant falsely certified that it had complied with the conditions in order to induce the government benefit. Courts have allowed False Claims Act claims to go forward based on false certifications with respect to compliance with environmental standards, see United States ex rel. Fallon v. Accudyne Corp., 880 F. Supp. 636, 638 (W.D. Wis. 1995); false certifications of compliance with the non-discrimination requirements of the Fair Housing Act and with an affirmative action plan, see United States v. Incorporated Village of Island Park, 888 F. Supp. 419, 434-36, 440-41 (E.D.N.Y. 1995); false certifications of compliance with the Medicare anti-kickback and anti-self-referral statutes, see United States ex rel. Thompson v. Columbia/HCA Healthcare Corp., 125 F.3d 899, 902; United States ex rel. Pogue v. American Healthcorp., Inc., 914 F. Supp. 1507, 1509 & 1513 (M.D. Tenn. 1996); and false certifications of compliance with rules for continuing adherence to the requirements of a Small Business Administration minority contracting program, see Ab-Tech Construction, Inc. v. United States, 31 Fed. Cl. 429 (1994), aff‘d, 57 F.3d 1084 (Fed. Cir. 1995).8 The courts in these
2. Fraud-in-the-Inducement Cases
Another set of cases involves False Claims Act liability for claims that would not be false under the district court‘s interpretation of the statute -- the fraud-in-the-inducement10 cases. In these cases, courts,
This fraud did not spend itself with the execution of the contract. Its taint entered into every swollen estimate which was the basic cause for payment of every dollar paid by the [government] . . . . The initial fraudulent action and every step thereafter taken, pressed ever to the ultimate goal--payment of government money to persons who had caused it to be defrauded.
Id. at 543-44. Based on this language, courts have found False Claims Act violations in other bid-rigging situations, see, e.g., United States v. CFW Construction Co., Inc., 649 F. Supp. 616, 618 (D.S.C. 1986), dismissed on other grounds, 819 F.2d 1139 (4th Cir. 1987); when a contract was originally obtained based on false information or fraudulent pricing, see United States ex rel. Hagood v. Sonoma County Water Agency, 929 F.2d 1416, 1420 (9th Cir. 1991); United States ex rel. Windsor v. Dyncorp, Inc., 895 F. Supp. 844, 850-51 (E.D. Va. 1995); United States v. General Dynamics Corp., 19 F.3d 770, 772 & 775 (2d Cir. 1994) (defendant liable for submitting inflated cost estimates in subcontract submitted for approval to government); or when a contract was obtained by a false representation about the ability to perform the contract, cf. United States ex rel. Schwedt v. Planning Research Corp., 59 F.3d 196, 199 (D.C. Cir. 1995) (court did not reach the question, but suggested it would have upheld such a theory had it been properly presented). But see United States v. Shaw, 725
Contrary to the district court‘s decision, in many of the cases cited above the claims that were submitted were not in and of themselves false. In each of the false certification cases the actual “claim” submitted was not false. In Island Park the HUD housing was actually constructed at fair cost and HUD-qualified purchasers actually moved in; and in Thompson and Pogue the medical services were actually necessary and provided at fair costs. In Marcus, CFW, and Dyncorp, the work contracted for was actually performed to specifications at the price agreed. False Claims Act liability attached, however, because of the fraud surrounding the efforts to obtain the contract or benefit status, or the payments thereunder.
As the above cases illustrate, the district court‘s interpretation of the phrase “false or fraudulent claim” was erroneous. The phrase “false or fraudulent claim” in the False Claims Act should be construed broadly. The False Claims Act is “intended to reach all types of fraud, without qualification, that might result in financial loss to the Government. ... [T]he Court has consistently refused to accept a rigid, restrictive reading ....” United States v. Neifert-White Co., 390 U.S. 228, 232 (1968) (citation and footnotes omitted). The False Claims Act “reaches beyond `claims’ which might be legally enforced, to all fraudulent attempts to cause the Government to pay out sums of money.” Id. at 233. Thus, any time a false statement is made in a transaction involving a call on the U.S. fisc, False Claims Act liability may attach. The test for False Claims Act liability distilled from the statute and the sources discussed above is (1) whether there was a false statement or fraudulent course of conduct; (2) made or carried out with the requisite scienter; (3) that was material; and (4) that caused the government to pay out money or to forfeit moneys due (i.e., that involved a “claim“).
III.
Count 3: In Count 3(a), Harrison alleges that WSRC lied about the scope of the GPC subcontract in order to get the DOE to approve a sole-source extension of the subcontract for $880,000. In Count 3(b),
WSRC challenges these claims on several bases. First, WSRC notes that the DOE was in possession of a copy of the GPC contract when WSRC submitted the claims in Count 3(b) and the contract extension proposal in Count 3(a) and was thus fully capable of agreeing or disagreeing with WSRC‘s interpretation of the contract terms. WSRC also argues that these misstatements do not meet Berge‘s materiality requirement.
A close reading of the materials relied upon by Harrison leads to the conclusion that all of Count 3 must be dismissed. The DOE‘s approval statement indicates that even if WSRC had lied, this was immaterial to the DOE‘s sole-source extension. The DOE granted a sole source extension of $880,000 for procedure development because it was convinced that changes in the “expectations and regulatory requirements” forced a “complete upgrade of the ITP procedure system.” (J.A. at 48.) The DOE did cite to the allegedly false inclusion of 5% procedure development in the GPC subcontract when it approved the $880,000 sole-source extension. (J.A. at 49). But its approval was for much more than a 5% extension; the DOE was specifically altering the original scope of work to meet the changed circumstances. Whether the original GPC subcontract had contained a provision for zero or 5% procedure development was simply immaterial to the DOE‘s decision.
As for Count 3(b), WSRC‘s argument is persuasive. The DOE was aware of the terms of the contract -- it could have objected to the inclusion of procedure development costs if it had believed that such work was not authorized. Harrison does not allege that WSRC tried to conceal the nature of the work. Thus, Counts 3(a) and (b) do not involve any material falsity, if any falsity at all.
Count 4 was properly dismissed. Harrison does not state which signature was fraudulent or unauthorized, nor who perpetrated the fraud, nor how the signature was fraudulent. He thus fails
Also, even if Harrison had pled fraud with the requisite particularity, a falsified signature on a form, not itself a claim for payment, not
Count 5 was properly dismissed. The allegations of breaches of contractual and fiduciary duty amount to no more than allegations of poor and inefficient management of contractual duties. The district court was correct in holding that poor, or to use Harrison‘s term, “non-cost-effective,” (Amended Complaint ¶ 25(f)), management is not actionable under the False Claims Act. Moreover, Harrison does not describe with particularity who made misrepresentations, when they made them, nor the manner in which they were made. These are general allegations and fail
Count 7 was properly dismissed. Count 7, read in the most charitable light, alleges that WSRC and GPC conspired to replace two lower salaried workers with two higher salaried workers so that they could charge the DOE more money for the subcontract. Count 7 fails for a number of reasons. First, Count 7 does not plead an intent to defraud -- nowhere does Harrison assert that WSRC and GPC originally intended to use the removed lower-salaried workers on the subcontract; Harrison alleges merely that they were in fact used. Staffing changes are common, and we should be very hesitant to allow such a claim to stand lest we impose unnecessary regimentation on government contractor staffing decisions. Second, Harrison in fact pleads no facts that could amount to fraud -- the higher salaried workers used for the bid proposal were actually staffed on the GPC subcontract.
Count 8 was properly dismissed. Count 8 utterly fails
Count 9 was properly dismissed. This allegation simply does not state a violation of the False Claims Act. Nowhere does it state that a claim of any sort was presented to the DOE or that payments were made contingent upon representations by the Defendant or upon compliance with the “conditions” in the regulation cited by Harrison. Again, this count amounts to no more than an allegation of poor management, which, as the district court noted, is not cognizable under the False Claims Act.
Count 10 was also properly dismissed. Count 10 alleges a conspiracy to routinely “sole source” modifications of the ITP Training Project contract, in violation of the DOE regulations requiring competitive bidding. First, Harrison raises this claim only in his brief. Harrison argues that the claim was always there in the documents filed with the complaint and that a court can consider these documents. See Lovelace v. Software Spectrum Inc., 78 F.3d 1015, 1017 (5th Cir. 1996); United States ex rel. McCoy v. California Medical Review, Inc., 723 F. Supp. 1363, 1367 (N.D. Cal. 1989). Even so, a court cannot be expected to parse through 1400 pages of documents, as Harrison submitted to the district court below, in order to invent a claim whole cloth for the plaintiff. Second, to the extent that an allegation of a conspiracy to fraudulently sole source can be gleaned from his complaint (cf. Amended Complaint ¶¶ 27, 37), this allegation fails
The remaining claims need a closer analysis.
Count 1 and Count 6 will be treated together since they revolve around the same issues.12 Counts 1 and 6 basically allege that WSRC
Relying on a mixture of false certification and fraud-in-the-inducement cases discussed in section II(B), supra, Harrison asserts that because of these fraudulent misrepresentations to the DOE, WSRC obtained a “fraudulent approval” for the subcontract and therefore all demands for payments made under the subcontract were false claims. Stated in its strongest form, Harrison alleges that WSRC misrepresented the need for and costs of subcontracting in order to convince the DOE to approve funding for a subcontractor, and this funding was in excess of what the government would have legitimately incurred if WSRC had not made the misrepresentations. Harri-
Under the test developed in section II(B), supra, these alleged falsities are sufficient grounds for a False Claims Act claim to survive a
1) False statement. Given that we are reviewing a decision to grant a
2) Requisite scienter. Again, we must take Harrison‘s allegations as true, that WSRC in fact knew that the above statements were false.
3) Materiality. Harrison argues that WSRC‘s false statements meet Berge‘s test for materiality in that they would have a “natural tendency to influence” the DOE‘s decision whether to approve the subcontract. See Berge, 104 F.3d at 1459.
WSRC argues that the allegedly false statements in Counts 1 and 6 were immaterial to the DOE‘s decision to pay for the ITP Training Project. First, WSRC argues that (1) Harrison‘s own allegations show that ITP Training was necessary to WSRC‘s contract with the DOE; (2) the DOE was bound by the contract to pay WSRC‘s costs in performing tasks necessary to that contract; therefore (3) the allegedly false statements could not have been material to the DOE‘s decision to pay. This argument by WSRC misconstrues Harrison‘s complaint, however. Harrison does not argue that any claim submitted by WSRC for ITP Training would be a false claim. Harrison argues that when a contractor knowingly makes a misrepresentation to the government about the need to hire, and the cost of hiring, a subcontractor to perform a particular service, and the government is induced by these misrepresentations ultimately to pay more than it otherwise would have for the service, then the claims for payment to the subcontractor are false claims. Under this theory, the false statements were material to the government‘s decision to pay a higher price for a subcontractor than it would have had to pay to WSRC.
The above argument by WSRC misses its mark. Even if the DOE‘s decision to allow subcontracting was only predicated on WSRC‘s alleged lack of personnel, and even if WSRC actually lacked personnel (Harrison never alleges otherwise), Harrison has still alleged material falsities. WSRC submitted to the DOE that, even though subcontracting was more expensive than performing the task in-house, WSRC did not currently have the personnel. To make its request more persuasive, WSRC allegedly low-balled the cost of hiring a subcontractor. WSRC stated to the DOE that subcontracting rather than hiring more staff (which would have been cheaper) was necessary for two reasons: (1) because of the short-term nature of the ITP Training Project, permanent staff should not be hired, and (2) in order to prevent interruptions in training. The only rational reason why the DOE would have approved paying a higher price to a subcontractor is that it believed at least one of the two reasons offered by WSRC.
Harrison has alleged only that the first of these two reasons was false. Berge indicates that questions of materiality “partak[e] of the character of a mixed question of fact and law.” 104 F.3d at 1460. On the pleadings, it is difficult to say whether or not WSRC‘s allegedly false statement was material to the DOE‘s funding decision, since there was another potential basis for the DOE to rely upon in making its decision. At the very least, however, at this
Finally WSRC argues that WSRC‘s statements cannot create False Claims Act liability because they were only estimates. Expressions of
4) Involved a claim. WSRC submitted numerous invoices for reimbursement of the amounts it paid out to the subcontractor for the ITP Training Project, each of which constitutes a “claim” under the False Claims Act. The fraud-in-the-inducement cases discussed in section II(B), supra, provide sufficient legal precedent for Harrison‘s complaint in Counts 1(a)-(d) and 6 to survive the
[the] fraud did not spend itself with the execution of the contract. Its taint entered into every swollen estimate which was the basic cause for payment of every dollar paid by the [government].
United States ex rel. Marcus v. Hess, 317 U.S. at 543. Therefore, the district court‘s decision with respect to Counts 1(a)-(d) and 6 must be reversed and the case remanded for further proceedings on these claims.
Count 2. We dispose of Count 2(b) first. In Count 2(b), Harrison asserts essentially that WSRC was under a continuing duty to report undisclosed conflicts of interest to the DOE when the GPC subcontract was expanded. WSRC argues that there was no duty, particularly in the absence of a request from the DOE. We affirm the district court‘s dismissal of Count 2(b). Harrison has not alleged that the DOE made any requests for further certifications or that WSRC actually made such certifications. Nor has Harrison alleged that the DOE conditioned approval of later extensions of the GPC subcontract, or payments thereunder, upon continuing conflicts disclosures. To the extent that Harrison is asserting an implied certification by silence, see note 8, supra, Harrison‘s claim fails on the pleadings because he has never asserted that such implied certifications were in any way related to, let alone prerequisites for, receiving continued funding. See Thompson, 125 F.3d at 902; Joslin, 984 F. Supp. at 383-84.
In Count 2(a), Harrison asserts that WSRC falsely certified that there were no conflicts of interest between GPC and WSRC. This claim fits squarely into the false certification cases discussed in section II(B), supra, and will be discussed further below.
1) False Statement. Taking Harrison‘s allegations as true, there was a false statement made to the DOE about a lack of conflicts of
2) Requisite Scienter. Taking Harrison‘s allegations as true, when WSRC adopted GPC‘s certification, this act was undertaken with the requisite scienter.
3) Materiality. The prerequisite standard in the false certification cases is essentially a heightened materiality requirement: the government must have conditioned payment of the claim upon certification of compliance with the provision of the statute, regulation, or contract at issue. See Thompson, 125 F.3d at 902; Joslin, 984 F. Supp. at 383-84. Fairly read in the light most favorable to Harrison, see Mylan Laboratories, Inc., 7 F.3d at 1134, Harrison‘s complaint asserts that WSRC was required to certify that there was no conflict of interest in order to obtain the DOE‘s approval for the GPC subcontract. On review of the district court‘s
4) Involved a Claim. If Harrison‘s allegations in Count 2(a) are true, then WSRC could face False Claims Act liability for each claim submitted as a result of the false certification. The logic, a combination of the false certification and fraud in the inducement theories, would be as follows: This false certification was a pre-requisite to approval of the subcontract. Each claim for payment under the subcontract was therefore submitted under a contract which was fraudulently approved. So, WSRC could face False Claims Act liability for each claim for payment under the GPC subcontract.
CONCLUSION
Although Harrison may ultimately lack the ability to prevail on the evidence, we do think he has stated potential claims under Counts
AFFIRMED IN PART; REVERSED IN PART; AND REMANDED FOR PROCEEDINGS CONSISTENT WITH THIS DISPOSITION
