GREENLAND CONTRACTORS I/S, Plaintiff, v. UNITED STATES, Defendant, and Exelis Services A/S, Defendant-Intervenor.
No. 15-272C
United States Court of Federal Claims.
April 4, 2017
Reissued: April 12, 2017
131 Fed. Cl. 216
LETTOW, Judge.
Filed Under Seal: April 4, 2017
William P. Rayel, Trial Attorney, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, D.C., for defendant. With Mr. Rayel on the briefs were Chad A. Readler, Acting Assistant Attorney General, Civil Division, Benjamin C. Mizer, former Principal Deputy Assistant Attorney General, Civil Division, and Robert E. Kirschman, Jr., Director, Scott D. Austin, Assistant Director, and Douglas K.
Kevin P. Connelly, Vedder Price P.C., Washington, D.C., for defendant-intervenor. With Mr. Connelly on the briefs were Eric J. Marcotte, Marques O. Peterson, Kelly E. Buroker, and Caroline A. Keller, Vedder Price P.C., Washington, D.C.
Post-award bid protest; issues previously reserved by the court and not addressed by the Federal Circuit on appeal from the court‘s earlier judgment
OPINION AND ORDER1
LETTOW, Judge.
This post-award bid protest arises from a solicitation by the United States Air Force (“Air Force” or “government“) for the operation, maintenance, and support of Thule Air Base, an Air Force Base located in northwestern Greenland. On October 31, 2014, the Air Force notified Exelis Services A/S (“Exelis Services“) that it was receiving the contract award based upon the Air Force‘s determination that Exelis Services offered the lowest-priced, technically acceptable proposal. The other three competing offerors, Per Aarsleff A/S (“Per Aarsleff“), Copenhagen Arctic A/S (“Copenhagen Arctic“), and Greenland Contractors I/S (“Greenland Contractors“), the incumbent contractor, each filed protests in this court to challenge the contract award. After consolidating the three protests, the court granted the protesters’ motions for judgment on the administrative record and set aside the Air Force‘s award, finding that Exelis Services was ineligible to receive a contract award under the terms of the solicitation. See generally Per Aarsleff A/S v. United States, 121 Fed. Cl. 603 (2015) (”Per Aarsleff I“), rev‘d, 829 F.3d 1303 (Fed. Cir. 2016) (”Per Aarsleff II“).2 The Federal Circuit then reversed the court‘s judgment, holding that Exelis Services was eligible for and lawfully received the contract award. Per Aarsleff II, 829 F.3d at 1316.
In accord with the mandate from the court of appeals, the court vacated its prior judgment and dismissed all three protesters’ claims. Subsequently, Greenland Contractors filed a motion for reconsideration and to amend the judgment, noting that the court had expressly reserved ruling on two of Greenland Contractors’ protest grounds in its prior disposition, and that these issues had not been addressed by the Federal Circuit. The court granted the motion, vacated the dismissal of Greenland Contractors’ claims, and severed Greenland Contractors’ case from the consolidated cases.3 The parties were given the opportunity to submit supplemental briefs and responses, and Greenland Contractors, Exelis Services, and the government have done so. As a consequence, pending before the court are the two remaining claims that Greenland Contractors raised in its previous motion for judgment on
For the reasons stated, Greenland Contractors’ motion for judgment on the administrative record with respect to its two remaining claims is denied, and the government‘s and Exelis Services’ cross-motions are granted.
BACKGROUND AND FACTS4
A. Thule Air Base
Thule Air Base is located in a remote area of northwestern Greenland. Per Aarsleff I, 121 Fed. Cl. at 607. This location provides “strategic military advantages in the Arctic region” for the Air Force. Id. at 607. The Arctic environment, however, also provides “profound logistical challenges ... in supplying fuel, materials[,] and non-perishable items to individuals working and living on Thule Air Base.” Id. at 608. The base was initially proposed during World War II, initiated in 1946-1951, and reconstructed in 1951-53 upon the adoption by the United States and the Kingdom of Denmark of the 1951 Defense of Greenland Agreement. Id. Greenland is primarily a self-governing entity of the Kingdom of Denmark, but the Danish government controls Greenland‘s foreign policy and defense. Id. “Since the inception of Thule Air Base, the United States and Danish governments have engaged in negoti-
ations regarding contractual opportunities to support the base.” Id. In June 1962, an Aide Memoire prepared by the United States Department of State (“State Department“) explicated certain provisions of the 1951 Agreement, particularly with regard to “Danish participation in work in United States defense projects in Greenland.” Id. at 609 (quoting AR 20zf-1465). Then in 1991, the two countries adopted a Memorandum of Understanding, later amended in 2008 and 2009, which emphasized procurement of goods and services from Danish or Greenlandic sources if feasible:
In accordance with their respective laws and regulations, either [p]arty may award contracts to commercial enterprises for goods and services, including construction projects, in Greenland, and shall procure directly from Danish/Greenlandic sources. When procurement from such sources is not feasible, U.S. requirements may be satisfied by procurement from U.S. or other sources. Either [p]arty may use its own military or civilian personnel to perform services or construction projects.
Id.
B. The Thule Air Base Procurement
1. The solicitation.
In 2013, the Air Force and the State Department entered into discussions with the Danish Ministry of Finance regarding eligibility criteria for a solicitation for a contract to support Thule Air Base, and the parties ultimately reached an agreement in December 2013. See Per Aarsleff I, 121 Fed. Cl. at 609-11.5 On March 28, 2014, the Air Force
2. The evaluations and award.
Four offerors submitted proposals in response to the Thule Air Base solicitation: Exelis Services, Per Aarsleff, Copenhagen Arctic, and Greenland Contractors, the incumbent and current contractor for the base. Per Aarsleff I, 121 Fed. Cl. at 615. The Air Force initially evaluated all four proposals as technically unacceptable, but also included each proposal in the competitive range. Id. at 616. After issuing numerous evaluation notices and holding oral discussions with each of the offerors, the Air Force determined that Greenland Contractors’ proposal was
technically acceptable. Id. The Air Force then held a second round of discussions, and subsequently found that all four proposals were technically acceptable. Id. Exelis Services proposed the lowest price and received the contract award. Id. at 617. Per Aarsleff submitted the second-lowest price, Copenhagen Arctic submitted the third-lowest price, and Greenland Contractors submitted the fourth-lowest price. Id.7
C. GAO Protests
Per Aarsleff, Copenhagen Arctic, and Greenland Contractors each filed protests in November 2014 at the Government Accountability Office (“GAO“) to challenge the Air Force‘s contract award to Exelis Services. Per Aarsleff I, 121 Fed. Cl. at 618. The primary issue before GAO was whether Exelis Services was ineligible for the award under the terms of the RFP on the ground that Exelis Services was “a subsidiary of a foreign (United States) company.” Id. at 619 (quoting Per Aarsleff A/S, B-410782 et al., 2015 WL 1004252, at *5 (Comp. Gen. Feb. 18, 2015) (”Per Aarsleff (GAO)“)). GAO rejected the protesters’ claims and determined that Exelis Services was eligible. Per Aarsleff (GAO), 2015 WL 1004252, at *9.
Additionally, GAO addressed Greenland Contractors’ assertion that “the Air Force failed to evaluate whether Exelis Services’ proposed price was too low, and ... that the
D. Prior Decisions Addressing This Procurement
In March 2015, Per Aarsleff, Copenhagen Arctic, and Greenland Contractors each filed suit in this court to challenge the Air Force‘s contract award to Exelis Services. Per Aarsleff I, 121 Fed. Cl. at 620. The court consolidated the three cases and “ordered that the disposition of the motions for preliminary injunction be consolidated with the merits pursuant to
The court found that “the agency‘s decision to award Exelis Services the Thule Contract was arbitrary and capricious and not in accord with federal procurement law.” Per Aarsleff I, 121 Fed. Cl. at 630 (citing
The court set aside the award to Exelis Services after finding that the protesters were sufficiently prejudiced by the agency‘s error and that the “requirements for issuance of equitable relief [had] been satisfied.” Id. at 634, 636. Even so, the court rejected Greenland Contractors’ and Copenhagen Arctic‘s argument “that the Air Force failed to evaluate the proposals in accord with Section H-6 and [performance work statement] 3.1.16 of the Solicitation, which required offerors to ‘[m]aximize ... contract-related purchases and subcontracts from Danish and Greenlandic sources’ and to ‘[d]ocument and justify any exceptions.‘” Id. at 631 (quoting AR 88-5227, -5279). The court instead held that “the RFP provisions cited by Greenland Contractors and Copenhagen Arctic establish post-award performance standards that pertain to administration of the contract and do not create a supplementary evaluation criterion.” Id.
On appeal, the Federal Circuit reversed the court‘s decision, disagreeing with the court‘s findings regarding the eligibility of Exelis Services. Per Aarsleff II, 829 F.3d at 1306. The court of appeals determined that the eligibility provision in the solicitation was ambiguous, and the Air Force had clarified the meaning of that provision, albeit wrongly in light of the translation error, through questions and answers during the procurement. Id. at 1310-11. Under the interpretation of the solicitation set forth by the Air Force‘s clarification, Exelis Services, as a Danish company, was eligible for the contract award at Thule Air Base even though it was a wholly-owned entity of a foreign, i.e., U.S., company. Id. at 1311-12. Further, the court of appeals found that the ambiguity due to the mistaken belief about registration of foreign-owned subsidiaries was patent rather than latent, and that Greenland Contractors and Copenhagen Arctic had therefore waived the right to object to the eligibility provision because both had failed to raise the issue before the close of the bidding process. Id. at 1312-14. On the other hand, the Federal Circuit agreed with this court‘s finding regarding the RFP‘s reference to Danish and Greenlandic sources, stating that the cited provisions “refer to contract performance, not eligibility criteria.” Id. at 1314-16.
E. Greenland Contractors’ Remaining Claims
After receiving the Federal Circuit‘s reversal mandate, the court vacated the previous judgment in favor of the three protesters and dismissed each protester‘s case. Order of Oct. 18, 2016, No. 15-215C (consolidated), ECF No. 108. Greenland Contractors subsequently filed a motion for reconsideration and to amend the judgment, relying on the fact that it had raised two protest grounds that were not addressed in the courts’ prior opinions. See generally Pl. Greenland Contractors I/S‘s Mot. for Recons. and to Amend the Judgment, No. 15-215C (consolidated), ECF No. 110. In its previous decision regarding this procurement, the court had identified Greenland Contractors’ further claims but noted that it was not necessary to resolve them:
Greenland Contractors raises two additional claims, viz., that (1) the Air Force engaged in misleading discussions related to Greenland Contractors’ proposed pricing, and (2) that the Air Force was obliged to evaluate whether the other offerors had justified their lower pricing. ... In light of the court‘s rulings on other issues and considering also the court‘s disposition of the cases, a ruling on Greenland Contractors’ further issues is unnecessary.
Per Aarsleff I, 121 Fed. Cl. at 634 n.44; see also Mem. of Pl. Greenland Contractors I/S in Support of Its Mot. for Judgment on the Administrative Record (“Greenland Contractors’ Mot.“) at 22-34, No. 15-215C (consolidated), ECF No. 62-1 (explicating the two claims unaddressed by this court). The Federal Circuit also had not considered these additional claims. See generally Per Aarsleff II, 829 F.3d 1303.
Accordingly, on January 31, 2017, the court granted Greenland Contractors’ motion, vacated the previous judgment against the protesters insofar as Greenland Contractors was concerned, and severed Greenland Contractors’ case from the consolidated cases. Order of Jan. 31, 2017, No. 15-215C (consolidated), ECF No. 115. Although Greenland Contractors’ two remaining claims had been briefed in the parties’ previous motions and cross-motions for judgment on the administrative record, the court allowed any of the parties, including the four offerors and the government, to submit supplemental briefs and responses. Id. Greenland Contractors, Exelis Services, and the government chose to do so. In its supplemental brief, Greenland Contractors restates its previously unaddressed protest grounds, asserting that (1) “the Air Force engaged in misleading discussions with Greenland Contractors concerning its proposed pricing,” and (2) “the Air Force failed to adhere to the terms of this procurement‘s price evaluation scheme by not evaluating whether the other three offerors ... had justified their ‘significantly lower pricing.‘” Suppl. Br. of Pl. Greenland Contractors I/S (“Greenland Contractors’ Suppl. Br.“) at 1, No. 15-272C, ECF No. 22.
JURISDICTION
A. 28 U.S.C. § 1491(b)(1)
The Tucker Act, as amended, provides this court with jurisdiction to “render judgment on an action by an interested party objecting to a solicitation by a Federal agency for bids or proposals for a proposed contract or to a proposed award or the award of a contract or any alleged violation of statute or regulation in connection with a procurement or a proposed procurement.”
B. Standing
To have standing in a bid protest, the protester bringing suit must be an “interested party.” See
This court previously found that the protesters had standing to challenge the Air Force‘s award and specifically rejected Exelis Services’ contention that Greenland Contractors lacked standing:
Greenland Contractors has plausibly alleged that the Air Force committed errors by failing to adhere to various criteria set forth in the RFP and by engaging in misleading discussions regarding pricing. See Greenland Contractors’ Mot. at 5-6 (“[A]bsent the Air Force‘s eligibility and technical acceptability errors, Greenland Contractors would have been the only technically acceptable offeror. Moreover, the Air Force‘s flawed pricing evaluation left Greenland Contractors’ unreasonably high prices uncorrected and allowed the three lower-priced offerors to propose unjustified lower pricing.“). Contrary to Exelis Services’ position, if the court finds Greenland Contractors’ protest grounds to be persuasive, it would have a substantial chance to receive the award because the offers submitted by the other bidders would have been found to be flawed. See Hyperion, 115 Fed. Cl. [at] 550 (holding that the fourth-lowest bidder in a LPTA procurement had been sufficiently prejudiced to satisfy the requirement of ... standing, in a circumstance where the three lower offerors each failed to comply with applicable limitations on subcontracting). Exelis Services’ arguments to the contrary concern the merits of Greenland Contractors’ contentions. ...
Per Aarsleff I, 121 Fed. Cl. at 623. The court‘s reasoning and conclusion in this respect continue to apply. Although Greenland Contractors’ claims regarding eligibility and the use of Danish and Greenlandic sources have been rejected, see generally Per Aarsleff II, 829 F.3d 1303, it still has two remaining protest grounds. If the court accepts Greenland Contractors’ claims that the Air Force engaged in misleading discussions and failed to properly evaluate the pricing of the other offerors, the Air Force‘s evaluation of both Greenland Contractors’ proposal and the other three proposals would be flawed. Under these circumstances, Greenland Contractors would have a substantial chance of winning the award. Therefore, even in light of the Federal Circuit‘s decision on eligibility of offerors in this procurement, Greenland Contractors has standing to pursue its two remaining claims in this court.
STANDARDS FOR DECISION
The
ANALYSIS
A. The Air Force‘s Discussions with Greenland Contractors
1. Criteria governing discussions.
In its first remaining claim, Greenland Contractors argues that the Air Force engaged in misleading discussions related to Greenland Contractors’ proposed pricing, resulting in discussions that were not “meaningful.” See Greenland Contractors’ Mot. at 22-27; Greenland Contractors’ Suppl. Br. at 1-2.
Nonetheless, “[t]he scope and extent of discussions are a matter of [a] contracting officer[‘s] judgment.”
2. The context for the discussions.
Here, Greenland Contractors specifically references its first round of discussions with the Air Force, noting that it received more than 50 Evaluation Notices (“EN“) from the Air Force regarding its first proposal. See AR Tab 156. In one particular EN, the Air Force stated:
Termination [contract line item number (“CLIN“) ] X100 has been evaluated as not reasonable in accordance with
FAR [§] 15.404-1(b)(2)(i) . Termination CLIN price has been evaluated high in comparison to proposals received. Provide a description of what is included within your Termination price or reevaluate your Termination price.
AR 156-12365. In response, Greenland Contractors explained that [***]. AR 158-12618. Additionally, Greenland Contractors submitted an updated “Section B Price Worksheet, and an updated summary page of total proposed price as a result of the changes made to Factor 1 ENs.” AR 158-12620. After reviewing these responses, the Air Force notified Greenland Contractors that its proposal had been “rated as acceptable in all areas.” AR 161-12718. It also found Greenland Contractors’ price ratings to be “[r]easonable, [a]ffordable, and [b]alanced,” AR 161-12732, and determined that additional ENs were unnecessary, AR 161-12737.
Following the second round of discussions with the other offerors, Exelis Services proposed the lowest price of 2,020,333,220 Danish kroners (“DKK“) ($363,925,645) while Greenland Contractors proposed the fourth-lowest price of DKK [***] ($[***]). AR 20c-678. Regarding termination price, Greenland Contractors discovered that its initial termination price of DKK [***] was approximately [***] times as high as the next two lowest prices, which were Exelis Services’ price of DKK [***] and Copenhagen Arctic‘s price of DKK [***]. See Greenland Contractors’ Mot. at 23 n.5 (citing AR 153-12158 to -211; AR 97-6236; AR 168-14492). Greenland Contractors also learned that its final proposed prices were higher than the other offerors’ final proposed prices for several other CLINs, including CLIN X001, X003, X005, X007, and X015. See id., App. A (citing AR 122-8856; AR 135-10439; AR 163-12886; AR 182-16141). Greenland Contractors notes that its prices for those CLINs were often more than [***] times as high as the prices from the other offerors. See id. at 26-27. In light of this information, Greenland Contractors argues that “by warning Greenland Contractors of only one CLIN price that was deemed unreasonable, the Air Force misled Greenland Contractors into believing (incorrectly) that its other CLIN prices were reasonable even though they were sometimes even more disparate and ‘unreasonable’ based on the Air Force‘s own standard.” Id. at 27.
3. The relevant RFP provision.
Greenland Contractors’ mistaken belief regarding its other CLIN prices stemmed from its interpretation of the RFP. Regarding pricing, Section M of the RFP provided:
Price analysis and competition will be used to determine price reasonableness, affordability, and balanced pricing. In order to be considered for award, the offeror‘s total evaluated price must be determined reasonable, affordable and balanced. All proposals will be ranked by total evaluated price. Total evaluated price includes the price of all services, supplies and equipment, for the basic year and all option years to include the 12-month extension of services (excluding the Phase-In, Phase-Out, cost-reimbursable [g]overnment-furnished subsistence, travel and supplies, projects and termination costs). The
Phase-In price and termination costs will be evaluated for price reasonableness, but will not be included in the total evaluated price used for ranking offerors. Award will be made to the offeror with the lowest total evaluated price, receiving an “acceptable” technical rating.
- Price Reasonableness. The techniques and procedure described under
FAR [§] 15.404-1(b) will be used to assess proposal reasonableness.- Affordability. The affordability assessment will also consider the total estimated contract price as compared to the independent U[.]S[.] [g]overnment estimate for this program.
AR 88-5265. Greenland Contractors asserts that this language required the Air Force to evaluate each CLIN price individually. Greenland Contractors’ Mot. at 22; see also Combined Reply of Pl. Greenland Contractors I/S in Support of Its Mot. for Judgment on the Administrative Record and in Opp‘n to Def.‘s and Intervenor‘s Cross-Mots. (“Greenland Contractors’ Reply“) at 18, No. 15-215C (consolidated), ECF No. 69. Thus, Greenland Contractors assumed that the Air Force would identify each CLIN that was highly priced during the first round of discussions, not only termination price. In contrast, the government argues that the cited provision of the RFP “only required the Air Force to evaluate three types of prices for reasonableness: 1) total evaluated price; 2) the phase-in CLIN; and 3) termination liability CLINs.” Def.‘s Cross-Mot. for Judgment on the Administrative Record and Resps. to Pls.’ Mots. for Judgment on the Administrative Record (“Def.‘s Cross-Mot.“) at 54, No. 15-215C (consolidated), ECF No. 66. Under the government‘s interpretation, the Air Force would not need to evaluate the price for each CLIN individually.8
The dispute between the parties based upon their disparate interpretations of the solicitation poses a question of law that the court reviews de novo. CBY Design Builders v. United States, 105 Fed. Cl. 303, 327 (2012) (citing NVT Techs., Inc. v. United States, 370 F.3d 1153, 1159 (Fed. Cir. 2004); Banknote Corp. of Am., Inc. v. United States, 365 F.3d 1345, 1353 (Fed. Cir. 2004)). The principles of contract interpretation apply to the interpretation of government solicitations. Banknote Corp., 365 F.3d at 1353 n.4 (in turn citing Grumman Data Sys. Corp. v. Dalton, 88 F.3d 990, 997-98 (Fed. Cir. 1996)). The court must therefore begin by examining the language of the solicitation. See Coast Fed. Bank, FSB v. United States, 323 F.3d 1035, 1038 (Fed. Cir. 2003). “If the provisions of the solicitation are clear and unambiguous, they must be given their plain and ordinary meaning.” Banknote Corp., 365 F.3d at 1353 (citing Coast Fed. Bank, 323 F.3d at 1038). The solicitation will only be considered ambiguous if “its language is susceptible to more than one reasonable interpretation.” Id. (citing Grumman Data Sys. Corp., 88 F.3d at 997).
Here, the relevant provision of the RFP is neither ambiguous nor indefinite. Section M states that “[i]n order to be considered for award, the offeror‘s total evaluated price must be determined reasonable, affordable and balanced.” AR 88-5265 (emphasis added). Section M also specifically identifies two individual CLINs, phase-in price and termination costs, to be evaluated separately from total evaluated price. Id. Contrary to Greenland Contractors’ contention, the pertinent language in the RFP did not identify any other CLINs for this analysis or provide any indication that each and every CLIN would be evaluated independently. The government thus correctly notes
4. The specific nature of the discussions.
Because the Air Force found Greenland Contractors’ total price to be reasonable, AR 161-12732, the individual CLIN items within that total price were not sufficiently high to create a deficiency or render the proposal unreasonable. The Air Force was therefore not required to identify the specific CLIN prices that Greenland Contractors now refers to in its brief, even though Greenland Contractors’ prices for those items were higher than those of the other offerors. See, e.g., DMS All-Star Joint Venture, 90 Fed. Cl. at 669 (“[I]f an offeror‘s costs are not so high as to be unreasonable and unacceptable for contract award, the agency may conduct meaningful discussions without raising the issue of the offeror‘s costs.“) (internal quotation marks and citations omitted). Additionally, the Air Force‘s decision to identify Greenland Contractors’ unreasonably high termination price, AR 156-12365, but not its other high CLIN prices, could not have reasonably misled Greenland Contractors. The other CLIN prices were not on equal footing with the termination and phase-in CLINs. The Air Force was thus not arbitrarily picking and choosing CLIN prices to discuss, but rather was addressing pricing for a particular CLIN, termination costs, that had been specifically identified in the RFP. Accordingly, the identification of the high termination price should not have reasonably indicated to Greenland Contractors that its other CLIN prices were sufficiently low. See DMS All-Star Joint Venture, 90 Fed. Cl. at 671 (holding that the Army did not mislead the offeror when it identified one price concern related to the offeror‘s proposal, but not other concerns regarding labor salaries and non-labor costs, because the agency did nothing to suggest that the offeror “should not consider lowering certain cost elements“). Greenland Contractors’ incorrect assumption regarding its other CLIN prices was based upon its own unjustified interpretation of the solicitation and the Air Force‘s ENs, not on any misleading conduct by the Air Force.9
Greenland Contractors’ reliance on precedents where discussions were found to be misleading is also unavailing. For example, in Multimax, Inc., B-298249.6 et al., 2006 WL 3300346 (Comp. Gen. Oct. 24, 2006), the solicitation at issue required offerors to propose 208 different labor rates. Id. at *2. Although two of the protesters later discovered that many of their labor rates were significantly higher than the Independent Government Cost Estimate (“IGCE“) rates, the agency only identified a few of those problematic rates during discussions and failed to inform the protesters of many others. See id. at *8-10. The agency specifically stated in discussions that it was identifying “the following labor categories” as problematic, id. at *9, and it “confirmed during discussions that only the identified labor rates were over-
Additionally, in EFW Inc., B-412608, 2016 WL 6919877 (Comp. Gen. Apr. 7, 2016), an offeror alleged that the procuring agency‘s discussion questions were misleading because they focused on a single discrete area of the offeror‘s proposal, but “did not address the agency‘s true concern with respect to the significant weakness assigned to [the offeror‘s] proposal under factor (1).” Id. at *5. GAO agreed, holding that the agency‘s questions “were insufficient to alert [the offeror] to the actual breadth of the agency‘s concerns, and were therefore misleading.” Id.
Here, in contrast, the Air Force did alert Greenland Contractors to its “true concern,” termination pricing. Greenland Contractors responded to the termination pricing EN by revising its proposal, and the Air Force then determined that Greenland Contractors’ proposal was acceptable. AR 161-12718. Although the proposal included other highly-priced CLINs, the Air Force viewed those CLINs within Greenland Contractors’ total evaluated price and found that price to be reasonable. See AR 161-12732. The mere fact that Greenland Contractors’ total price was higher than the prices of the other offerors does not render the price deficient or unreasonable, and the Air Force was therefore not required to raise the issue. See, e.g., CRAssociates, 102 Fed. Cl. at 715.10
Thus, for the reasons stated, the Air Force did not mislead Greenland Contractors when it engaged in a meaningful discussion related to pricing.
B. The RFP Provision Regarding Justification for “[S]ignificantly [L]ower [P]ricing”
1. The relevant RFP provision.
In its second and final remaining claim, Greenland Contractors argues that the Air Force contravened the RFP by failing to evaluate whether the other offerors had justified their “significantly lower pricing.” See Greenland Contractors’ Mot. at 28; Greenland Contractors’ Suppl. Br. at 5. Greenland Contractors contends that the RFP required the Air Force to evaluate an offeror‘s justification for significantly lower pricing, see Greenland Contractors’ Mot. at 28, and the government responds that the RFP only advised offerors to justify unique practices that resulted in significantly lower pricing, Def.‘s Cross-Mot. at 47. The dispute is based upon a provision in Section M of the RFP, which provides that “[o]fferors are advised to clearly show justification for unique practices that
This interpretation is consistent with the solicitation as a whole. See Banknote Corp., 365 F.3d at 1353 (noting that the court “must consider the solicitation as a whole, interpreting it in a manner that harmonizes and gives reasonable meaning to all of its provisions“) (citing Coast Fed. Bank, 323 F.3d at 1038). The RFP called for a firm-fixed-price contract with economic price adjustment, see AR 88-5251, which “places upon the contractor maximum risk and full responsibility for all costs and resulting profit or loss,”
fixed-price contract, the offeror bears the risk of proposing an unrealistically low price, not the agency. The RFP also provided for a lowest-price, technically acceptable award where price would be evaluated based only upon “[t]otal price reasonableness, affordability, and balanced pricing.” AR 88-5261 to 62.12 Unlike a price realism analysis, where the agency “investigates whether the contractor is proposing a price so low that performance of the contract will be threatened,” a price reasonableness analysis “has the goal of preventing the government from paying too much for contract work.” DMS All-Star Joint Venture, 90 Fed. Cl. at 657 n.5. The Air Force‘s cost evaluation was thus directed to ensuring that prices were not too high; the RFP did not include a price realism analysis that would have required the agency to evaluate whether prices were too low. See Raymond Express Int‘l, LLC v. United States, 120 Fed. Cl. 413, 422 n.4 (2015) (restricting the court‘s analysis of the solicitation to price reasonableness where the solicitation did not require price realism and the plaintiff failed to identify any provision that would indicate otherwise).13 Because the offerors bore the risk of unrealistically low pricing and the RFP called for a price reasonableness evaluation rather than a price realism analysis, the RFP did not require an evaluation of significantly lower pricing. Rather, as the govern-
2. The Air Force‘s price evaluation.
Greenland Contractors previously asserted that the Air Force did not evaluate the other offerors’ ability to reduce pricing through the use of United States-based sources, Greenland Contractors’ Mot. at 33-34, but this court and the Federal Circuit have already rejected this contention and held that the RFP‘s reference to Danish and Greenlandic sources was not an evaluation criterion, see Per Aarsleff I, 121 Fed. Cl. at 631; Per Aarsleff II, 829 F.3d at 1314-16. Greenland Contractors now states that its reference to Danish and Greenlandic sources was only “one example,” and further claims that “the Air Force never sought to have any of the offerors justify any of the[ir] significantly lower prices.” Greenland Contractors’ Suppl. Br. at 8. However, as discussed supra, the relevant RFP provision related to offeror justifications for unique practices, not lower prices. Greenland Contractors has simply failed to identify any unique practice that went unjustified or unevaluated.
CONCLUSION
For the reasons stated, Greenland Contractors’ motion for judgment on the administrative record is DENIED, and the government‘s and Exelis Services’ cross-motions are GRANTED. Accordingly, Greenland Contractors’ request for injunctive relief is DENIED. The clerk shall enter judgment in accord with this disposition.
No costs.
It is so ORDERED.
Charles F. Lettow
Judge
Notes
To the extent the court cites to the administrative record, such citations will refer to the record filed in Per Aarsleff, No. 15-215 (consolidated). The administrative record was filed on March 18, 2015 in the protest of Per Aarsleff, and then was supplemented on April 7 and 15, 2015 for the protests of Greenland Contractors and Copenhagen Arctic, respectively. The record is divided into tabs, but the pages are sequentially numbered without regard to the tabs. The court‘s citations to the administrative record will designate the tab, followed by the page, e.g., AR 83-4608 refers to tab 83, page 4608 of the record.