OPINION
¶ 1 Physical Resource Engineering, Inc. (PRE) appeals from a judgment entered af *27 ter a jury trial in favor of Michael Goodman on his claim for breach of contract. PRE also challenges the trial court’s denial of its motion for judgment as a matter of law pursuant to Rule 50, Ariz. R. Civ. P., and motion for a new trial pursuant to Rule 59, asserting there was no evidence a contract between PRE and Goodman had existed, and, in any event, under the circumstances of this case Arizona law limited Goodman to pursuing only a tort claim. Additionally, PRE contends the case should be remanded for a new trial on Goodman’s negligence claim. For the reasons set forth below, we reverse and remand.
Factual Background and Procedural History
¶ 2 We view “the evidence in a light most favorable to upholding the jury verdict.”
Hutcherson v. City of Phoenix,
¶ 3 According to the site plan, one of the buildings should have been located twenty feet, three inches south of the north property line, resulting in a twelve-foot-wide rear yard on the building’s north side. PRE staked the building approximately six feet north of where it should have been built, and TVH constructed the building according to the stakes, resulting in a yard depth of only six feet and a violation of setback and floodplain requirements. In September 2008, TVH and Isles determined the building location did not conform to the site plan, and Goodman subsequently sued PRE for breach of contract and professional negligence. 1
¶4 PRE filed a motion for partial summary judgment in which it argued there was no contract between it and Goodman, and, furthermore, it had not breached its express agreement with TVH. PRE also contended that any claim Goodman might have against it could be based only on the alleged breach of a professional duty, limiting Goodman to a negligence claim. The trial court denied the motion following oral argument.
¶ 5 During trial, PRE moved for judgment as a matter of law pursuant to Rule 50, again arguing there was no contract between the parties and the verbal contract between PRE and TVH had not been breached. As to the negligence claim, PRE contended that Goodman had failed to introduce sufficient evidence establishing PRE had staked the building in the wrong lоcation or, alternatively, that Goodman and Isles should be found comparatively at fault. The court denied PRE’s motion. Following the close of evidence, PRE renewed its Rule 50 motion and later moved for a new trial pursuant to Rule 59 on the same grounds, which the court again denied. The jury found that a contract existed between Goodman and PRE, and that PRE had breached it, causing damages of $217,314. The court entered judgment in favor of Goodman in that amount, and awarded him attorney fees and costs under A.R.S. §§ 12-341.01 and 12-322. We have jurisdiction pursuant to A.R.S. §§ 12-120.21(A)(1) and 12-2101(A)(1), (A)(5)(a).
Discussion
¶ 6 PRE contends the trial court erred in denying its motions for judgment as a matter of law on Goodman’s breach of contract claim because there was no evidence a contract existed between PRE and Goodman under either of two theories Goodman advanced at trial. We review
de novo
the denial of a motion for judgmеnt as a matter of law under Rule 50.
A Tumbling-T Ranches v. Flood Control Dist. of Maricopa
*28
Cnty.,
Implied Contract between PRE and Goodman
¶ 7 To prevail on a breach of contract claim, Goodman was required to prove a contract existed between him and PRE, PRE breached thе contract, and Goodman suffered damages as a result.
See Graham v. Asbury,
¶ 8 The parties agree there was no written or express contract between them for the staking job. Goodman contends, however, that based on evidence of their prior course of dealing and other circumstances, the jury reasonably could infer PRE had intended to enter into a contract with him.
2
See Carroll v. Lee,
¶ 9 Although Goodman repeatedly points to evidence PRE had knowledge, from a variety of sources, that he was the owner of the property, he provides no authority for the proposition that such knowledge established the existence of a contract with him *29 rather than TVH. It is undisputed that PRE was hired by TVH and dealt exclusively with TVH throughout the course of the project. Thus, other than рossibly through TVH, acting as Goodman’s agent as we address infra, there was no evidence Goodman made an offer to PRE, much less that PRE accepted an offer from Goodman, to perform the staking on this project.
¶ 10 Goodman nevertheless contends that a contract with PRE was implied because PRE president Dan White had met with him personally to discuss possible solutions after it was learned the property had been staked in the wrоng place. But we agree with PRE that such conduct occurring after the fact cannot serve as the basis for finding an implied contract existed given that there was an express contract between PRE and TVH.
See Brown v. Beck,
Contract Formed through Agency
¶ 11 PRE argues there was no evidence that TVH was acting as Goodman’s agent when it employed PRE to stake the proрerty; rather, the record shows PRE entered into an express oral agreement only with TVH, and nothing said or done created a contractual relationship between PRE and Goodman. Goodman counters that the circumstances, acts, and conduct of Goodman and TVH manifested an agency relationship that resulted in a binding contract between him and PRE. Goodman, as the proponent of the agency theory, had the burdеn of proof.
Brown v. Ariz. Dep’t of Real Estate,
¶ 12 “Agency is the fiduciary relationship that arises when one person (a ‘principal’) manifests assent to another person (an ‘agent’) that the agent shall act on the principal’s behalf and subject to the principal’s control, and the agent manifests assent or otherwise consents so to act.” Restatement (Third) of Agency § 1.01 (2006) (hereinafter “Restatement”).
3
There are two types of agency, express and apparent.
Curran v. Indus. Comm’n,
¶ 13 Goodman contends the principal’s intent is controlling in determining whether an agency relationship was created, citing
Bru-
*30
tinel v. Nygren,
¶ 14 PRE disputes Goodman’s legal claims, contending the role of a general contractor does not imply an agency relationship with the property owner, citing
P. Flanigan & Sons, Inc. v. Childs,
¶ 15 Although agency generally is a question of fact, the issue of agency may be decided as a matter of law where “ ‘no competent evidence legally sufficient to prove it has been introduced’ ” and “ ‘the material facts frоm which it is to be inferred are undisputed and only one conclusion can be reasonably drawn therefrom.’”
Schenks v. Earnhardt Ford Sales Co.,
¶ 16 In
Stratton v. Inspiration Consol. Copper Co.,
¶ 17 At trial, Goodman testified “[Patterson] is in charge of doing all the construction work, getting it completed and getting it finaled out with the city,” and that Patterson is “an independent contractor” who does what Goodman requests on the projects. Patterson testified, not inconsistently with Goodman’s statements, that he alone was responsible for hiring subcontractors, and Goodman did not tell him which ones to employ. Goodman identifies no evidence in the record that he exercised authority over TVH’s hiring process or decisions.
See Urias v. PCS Health Sys., Inc.,
¶ 18 Furthermore, even assuming
arguendo
that TVH was Goodman’s agent, there is no evidence TVH ever disclosed it was acting in that capacity when it engaged PRE’s services to stake the property. A principal is undisclosed if the third party has no notice the agent is acting for a principal. Restatement § 1.03(2)(b);
cf. Myers-Leiber Sign Co. v. Weirich,
¶ 19 The record supports PRE’s assertion that TVH did not inform PRE that it was acting as Goodman’s agent and, thus, that PRE was contracting with Goodman, when TVH hired PRE to stake the property. Patterson testified as follows:
Q: As the general contractor, you’re the one that’s responsible for hiring the subcontractors?
A: Yes.
Q: Mr. Goodman doesn’t tell you which subs to hire?
*32 A: No.
Q: If there’s a problem with the sub’s work that’s between you and the sub?
A: Yes.
Q: When you hired PRE to work on projects, there were some projects that you were working on for Mr. Goodman but others that you were working on for other people; correct?
A: Yes.
Q: When you hired PRE to do construction staking, you never told them I’m doing this work for Mr. Goodman or somebody else?
A: No.
Q: When you hired them, they were working for you[?]
A: Yes.
Goodman nonetheless argues that PRE was aware of an agency relationship between Goodman and TVH, relying on two other contracts betweеn PRE and TVH pertaining to other work performed on the same property that identified Goodman as “owner.” Goodman also points out PRE had possessed a hydrology report for the property that had been prepared for Goodman. Further, PRE had worked on Goodman’s projects in the past, and PRE recognized Patterson “comes in on behalf of Mike Goodman for his projects.” But it is not the duty of the third person to determinе the existence of a principal, rather the duty is on the agent to disclose the principal at the time of the transaction.
Mahan v. First Nat’l Bank of Ariz.,
¶ 20 Because there is no evidence TVH was acting as Goodman’s agent for the staking contract, and PRE had no notice otherwise that Goodman was a party to the contract, there was insufficient evidence for the jury to have found the existence of a contract between PRE and Goodman based upon an agency theory. See generally Restatement § 2.03 cmt. f (where principal undisclosed, third party has no knowledge principal is party to contract). Accordingly, we conclude the trial court erred in denying PRE’s Rule 50 and 59 motions.
¶ 21 Because of our resolution of the contract issues, we need not address PRE’s additional argument that Arizona law limits Goodman to pursuing only remedies under tort law.
Disposition
¶ 22 For the reasons set forth above, we reverse the trial court’s entry of judgment in favor of Goodman on his claim for breach of contract аnd its order denying PRE’s motions for post-trial relief under Rules 50 and 59, as well as its award of $80,000 in attorney fees. PRE has requested an award of its attorney fees under A.R.S. § 12-341.01, and, because it is the successful party on appeal, we grant its reasonable fees upon compliance with Rule 21, Ariz. R. Civ.App. P.
See Schweiger v. China Doll Rest., Inc.,
Notes
. The trial court dismissed Goodman’s additional claim for breach of the covenant of good faith and fair dealing. TVH subsequently assigned to Goodman any claims it may have had against PRE. The court denied Goodman's subsequent motion to amend the complaint to add the assigned claims and Goodman has not challenged that ruling on appeal.
. In his complaint, the only theory Goodman advanced wаs that a contract had been formed as a result of TVH being his agent in its dealings with PRE. The trial court denied Goodman’s motion to amend his complaint to add a course-of-dealing theory. We may, however, affirm the jury’s verdict for any reason supported by the evidence.
See Hutcherson v. City of Phoenix,
. In the absence of prior decisions to the contrary, we may seek guidance from the Restatement when it is applicable.
Maricopa P’ships, Inc. v. Petyak,
. Apparent agency exists when " ‘the principal has intentionally or inadvertently induced third persons to believe that such a person was its agent although no actual or express authority was conferred on him as agent.’”
Curran,
.
See, e.g., Litchfield v. Green,
