History
  • No items yet
midpage
Goodman v. Physical Resource Engineering, Inc.
270 P.3d 852
Ariz. Ct. App.
2011
Read the full case

Background

  • Goodman hired Tortolita Valley Homes (TVH) to oversee construction of two duplexes on his Fort Lowell Road property.
  • TVH hired PRE to stake the building locations according to a site plan approved by the City of Tucson.
  • PRE stakes were placed roughly six feet north of the planned location, causing setback and floodplain violations.
  • TVH and Isles later determined the staking was incorrect, leading Goodman to sue PRE for breach of contract and negligence.
  • PRE moved for summary judgment arguing no contract existed; trial court denied; trial proceeded with additional Rule 50 and Rule 59 motions.
  • The jury found a contract existed between Goodman and PRE and awarded damages; on appeal, the court reversed and remanded, ruling there was insufficient evidence of a contract.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether a contract existed between Goodman and PRE Goodman contends agency theory or implied contract from conduct created privity. PRE argues there was no direct contract with Goodman and no agency-based contract via TVH. No contract existed between Goodman and PRE based on agency or implied agreement.
Whether TVH acted as Goodman’s agent to bind PRE Goodman asserts agency through TVH's control and dealings on the project. PRE contends no agency relationship and no disclosure of agency by TVH at contract formation. No agency relationship supported; TVH did not disclose agency, so no privity through agency.
Whether there was implied contract between PRE and Goodman Goodman points to past dealings and owner awareness to infer an implied contract. PRE notes no offer/acceptance between Goodman and PRE and post hoc conduct cannot form a contract. Insufficient evidence to infer an implied contract between PRE and Goodman.
Whether TVH’s role as general contractor creates privity with Goodman for PRE’s contract Goodman argues TVH's role and conduct established an agency that bound PRE. PRE maintains that general contractor role does not imply owner’s agency outside mechanics’ lien context. No privity via agency between Goodman and PRE; contract not established.
Whether undisclosed principal doctrine affects potential contract liability Goodman relies on undisclosed-principal concepts to hold PRE liable. PRE emphasizes lack of notice of any principal and absence of agency disclosure by TVH. Undisclosed-principal theory not sufficient to create contract liability here.

Key Cases Cited

  • Hutcherson v. City of Phoenix, 192 Ariz. 51 (1998) (standard for reviewing evidentiary sufficiency to uphold a verdict)
  • A Tumbling-T Ranches v. Flood Control Dist. of Maricopa Cnty., 217 P.3d 1220 (App. 2009) (de novo review of judgment as a matter of law; substantial evidence standard)
  • Brown v. Beck, 202 P.2d 528 (1949) (no implied contract where express contract existed for labor)
  • Curran v. Indus. Comm’n, 752 P.2d 523 (App. 1988) (tests for apparent agency and authority)
  • Stratton v. Inspiration Consol. Copper Co., 683 P.2d 327 (App. 1984) (general contractor not owner’s agent except for mechanics’ liens)
  • Schenks v. Earnhardt Ford Sales Co., 454 P.2d 873 (App. 1969) (agency question framework and evidence standard)
Read the full case

Case Details

Case Name: Goodman v. Physical Resource Engineering, Inc.
Court Name: Court of Appeals of Arizona
Date Published: Dec 28, 2011
Citation: 270 P.3d 852
Docket Number: 2 CA-CV 2011-0053
Court Abbreviation: Ariz. Ct. App.