Environmental Defense Fund v. MarshEnvironmental Defense Fund v. Marsh
Lawrence A. G. Moloney, Richard A. Fine, Marta W. Berkley, Civ. Div., Dept. of Justice, Washington, D. C., H. M. Ray, U. S. Atty., Oxford, Miss., for defendants-appellees.
James Hugh Ray, Tupelo, Miss., Hunter M. Gholson, Columbus, Miss., Alfred P. Holmes, Jr., Mobile, Ala., for defendants-intervenors-appellees.
Appeal from the United States District Court for the Northern District of Mississippi.
REAVLEY, Circuit Judge:
The Environmental Defense Fund and other plaintiffs brought suit against John O. Marsh, Jr., in his capacity as Secretary of the Army, based on the claim that the Army Corps of Engineers has violated several statutes and regulations in the course of planning and constructing a major water project, the Tennessee-Tombigbee Waterway. The district court granted the government‘s motion for summary judgment, and the plaintiffs appealed. We affirm in part and reverse in part.
I. The Background Facts
A. The History and Design of the TTW Before 1971
The Tennessee-Tombigbee Waterway (“the TTW“) is a major navigational project of the Army Corps of Engineers (“the Corps“). The TTW extends 253 miles across portions of the states of Mississippi and Alabama to serve as a link between the Tennessee River in the north and an existing waterway to the south, the Black Warrier-Tombigbee Waterway (“BWTW“), which leads into the tidewater port of Mobile, Alabama. The TTW will thus be the completing link of a continuous waterway from the Tennessee, upper Mississippi, and Ohio Valleys to the Gulf of Mexico. The territorial limits of the TTW itself, however, extend only northward from Demopolis, Alabama (the northern terminus of the BWTW), to Pickwick Pool in the Tennessee River, near the common border of Tennessee, Alabama, and Mississippi. The TTW was first authorized by Congress in 1946, but essentially lay dormant until 1965, when Congress authorized a re-evaluation of the economics of the project.1 Consequently, the Corps’ district engineer at Mobile completed an economic re-study of the TTW on June 30, 1966 (“the 1966 study“).
After public comment based on the 1966 study, the Secretary submitted a proposal to Congress in 1969 that allocated funds for pre-construction planning of the TTW. In 1971, the Corps prepared and filed an environmental impact statement (“EIS“) that was also based on the 1966 study, pursuant to the requirements of the National Environmental Policy Act (“NEPA“),
B. The Design and Economics of the TTW After 1971
Major construction projects usually change in design, cost, scope, and impact over the years required for development. In fact, the original EIS for the TTW anticipated major changes in the project and specifically stated that the EIS was only
the first of three phases of a comprehensive environmental study of the project area .... The second phase of the study will consist of a detailed evaluation of the impacts identified during the first phase and will be correlated with advanced engineering and design work for the project. Alterations in design will be made to increase the gains and mitigate the losses. In addition, the environmental statement will be updated prior to the construction of major segments of the project.
Environmental Statement, Tennessee-Tombigbee Waterway, p. 2 (March 1971) (emphasis added).
It is not important for the purposes of this case to trace the origin and motive behind each change in the design and economics of the TTW after the 1971 EIS was filed. But by late 1974, the Corps had initiated design changes costing about $330 million and inflation had added a like amount to project costs. As a result, the TTW was projected to cost more than three times the amount originally submitted to Congress. Faced with such grim statistics, the Corps decided to commission a new economic analysis of the waterway, which was published in 1976. That study (“the 1976 study“) publicly revealed that the TTW would depart from the 1971 designs and economic projections in the following ways:
- Traffic on the waterway in the initial year of operation will be 350% of the figure projected in 1971 (28 million tons as compared to 8 million tons), will move 90% from north to south (as compared to the former projection that 80% would move from south to north), and will carry a total of 18 million tons of coal (as compared to the former projection of 2 million tons);
- Total land use for the project will be 150% of the figure projected in 1971 (105,000 acres as compared to 70,000 acres);
- A 45-mile section of the canal has been changed in design from a “perched canal,” created by artificial levees on both sides, to a “chain of lakes,” using an artificial levee on one side and a natural barrier of hills on the other to create a larger body of navigable water, which will also serve as a better reservoir for locks. This design will allegedly flood an additional 5,000 acres and waterlog an additional 50,000 acres;
- A navigation channel that originally was to follow the natural course of the Tombigbee River has been straightened by artificial cutoffs that will isolate 21 miles of the river‘s previous channel; and
- Excavations in one section of the project will create the need for disposal of 9 million cubic yards more spoil than was projected in the 1971 EIS.
The design of the TTW was changed in one additional way after the 1976 study. Prior to 1975, the Corps had assumed that it could, without congressional authorization, remove certain barriers from the BWTW to accommodate two-way traffic from the larger 8-barge tows that the TTW will be able to carry.2 A 1974 decision of the United States District Court for the District of Columbia, however, held that the Corps did not have authority to make such improvements without congressional authorization. Atchison, Topeka & Santa Fe RR Co. v. Callaway, 382 F.Supp. 610 (D.D.C.1974). See EDF v. Alexander, 467 F.Supp. 885, 896 n.5 (N.D.Miss.1979). Based on this ruling, the Corps decided in 1975 to sever the authorized TTW project and pursue the improvements to the BWTW as a separate project, which is still under study and has not been proposed to Congress. That segmentation decision was made public in the 1976 study. As a practical result, total long-distance traffic volume on the TTW will be limited by the 6-barge tows and slower speeds that the unimproved BWTW can currently accommodate, placing an effective traffic limit on the TTW of 29 million tons annually.3 If and when the BWTW is improved, the TTW may eventually handle up to 55 million tons a year by 1995. Since 1976, the Corps has chosen to evaluate the cost-benefit ratio of the TTW on the basis of the 29 million ton limit, and all submissions to Congress have been based upon that limitation.
(1) If the final environmental statement previously filed clearly failed to comply with the requirements of NEPA: e. g. failed to discuss alternatives or failed to disclose the environmental impacts of the proposed action, or if there has been a major change in the plan of development or method of operation of the proposed action, (or)
(2) Whenever the final environmental statement on file becomes deficient because certain environmental effects of the project were not discussed or design features or project purposes were modified significantly subsequent to the filing of the original environmental statement.
(3) Whenever it is necessary only to clarify or amplify a point of concern raised after the final environmental statement was filed with CEQ (Council on Environmental Quality) (and such point of concern was considered in making the initial decision) or if comments on the final environmental statement are received from Federal, State or local governmental agencies or the public, the clarification, amplification or response to the comments received shall be prepared and filed with CEQ. No waiting periods are required....
The Corps chose to treat all post-1971 changes in the TTW under subsection (3), as “point(s) of concern ... considered in making the initial decision” but needing only “clarification” or “amplification.” As a result, the Corps has filed 18 volumes of “supplemental environmental reports” (“SERs“) with the CEQ. The SER is entirely an ad hoc creation of the Corps: its contents and the procedures accompanying its preparation and release are not governed by any statutes or regulations. Thus the Corps may include as much or as little environmental analysis, and allow as much or as little public comment, as it wishes.7 The federal defendants rarely cited the SERs in their motions and memoranda relating to summary judgment on the environmental issues in this case, which leads us to believe that the SERs contain little substantive environmental analysis of the post-1971 changes.
Congress has continued to appropriate funds for the TTW, and the project is now about 55% complete. The waterway is currently expected to cost approximately $2 billion, of which about $800 million has already been spent. The improvements to the BWTW, still in the study and planning stage, are projected to cost an additional $1 billion.
II. The Current Litigation
The plaintiffs filed this suit against the Corps in 1976, containing 15 counts. The district court divided these causes of action into three general sets of issues:
- challenges to the legal authority of the Corps to build the TTW in light of the changes in the design and economic projections of the waterway;
- the need for a supplemental EIS in relation to these changes; and
- challenges to the Corps’ method of calculating certain costs and benefits for the project.
The district court decided to try the first of these three issues separately.8 Certain of the changes that the plaintiffs discussed in this first trial as a basis for negating the Corps’ legal authority were public knowledge by the time of the 1971 EIS.9 With regard to these pre-1971 changes, the district court held that the equitable doctrine of laches barred any challenge to the Corps’ authority, and a panel of this court affirmed that judgment on appeal. EDF v. Alexander, 467 F.Supp. 885 (N.D.Miss.1979), aff‘d, 614 F.2d 474 (5th Cir. 1980), cert. denied, 449 U.S. 919, 101 S.Ct. 316, 66 L.Ed.2d 146 (1980) (“EDF II“). But this first issue was also based upon some of the post-1971 changes listed in section I.B. above, most of which did not become public knowledge until the 1976 study was released. The district court recognized that an affirmative defense of laches would not apply to these changes and proceeded to the substantive legal issue. In deciding whether the post-1971 changes undermined the statutory authority of the Corps to construct the TTW, the district court found that several specific documents and regulations of the Corps establish a discretionary area within which Corps officials may make changes in congressionally-approved projects without securing Congress’ approval. 467 F.Supp. at 899-902, 908-09. The district court evaluated the new chain-of-lakes design and the new straightening of the Tombigbee River channel in the light of these Corps documents and regulations, finding that these two changes were not so significant as to fall outside the discretionary area established by the Corps’ policies. Id. at 909-10. This finding of the district court was not discussed in the Fifth Circuit opinion.
III. The Standard of Review
A party who moves for summary judgment under
IV. The Need for a Supplemental EIS
As discussed in section I.B. above, the plaintiffs identified five general areas of change in the design and economic projections for the TTW that allegedly necessitate a supplemental EIS. NEPA itself does not contain any specific requirement for the supplementation of an EIS, and the federal defendants argue that this leaves the question to be determined only by the Corps’ own regulations. We do not believe that NEPA should be read so narrowly, however, as to leave the need for supplementation of an EIS entirely up to the discretion of an agency. NEPA requires that
(A)ll agencies of the Federal government shall ... include in every recommendation or report on proposals for legislation and other major Federal actions significantly affecting the quality of the human environment, a detailed statement by the responsible official on ... the environmental impact of the proposed action (and) ... any adverse environmental effects which cannot be avoided should the proposal be implemented ....”
A. The Changes in Traffic Levels, Directions, and Cargo
The 1976 study revealed for the first time that barge traffic in the first year would be 350% of the traffic projected in 1971, would move primarily in the opposite direction, and would carry nine times the amount of coal projected in 1971. The district court did not even mention these new projections in its discussion of post-1971 changes in the TTW. EDF III, 501 F.Supp. at 753. The government argues that the new level of traffic cannot be considered “significant” or new because the 1966 economic study, which served as the data base for the 1971 EIS, contained one chart that projected traffic at this level by the year 2010. But the 1971 EIS did not discuss the eventual impact of such a traffic level on the environment, much less the impact of that level if achieved in the first year. And it obviously could not have discussed the newly-discovered characteristics of the traffic.
The affidavit of the plaintiff‘s leading environmental expert states that these vastly greater traffic levels will have major new environmental impacts through increased turbidity, bank sloughing, congestion, and pollution. Other affidavits show that significant environmental impacts from this larger traffic level will also be felt along the course of the BWTW and in Mobile harbor, impacts on geographical areas that were entirely excluded from the 1971 EIS. The supervisory sanitary engineer in the Mobile district office of the Corps testified in deposition, and the federal defendants have not denied, that the Corps has made no studies to determine the environmental significance of these new traffic projections. Perhaps because of the lack of such studies, the federal defendants’ motions and memoranda relating to summary judgment cite no evidence to indicate that these changes will not have significant effects upon the environment.
The only relevant argument advanced by the federal defendants is that the 1971 EIS addressed several categories of impacts that result from barge traffic, e. g., turbidity and bank sloughing. But only one of these general categories, the volume of water transfer between the Tennessee and Tombigbee Rivers, was analyzed in terms of the maximum volume of traffic, presumably the 29 million ton figure. All other environmental impacts related to traffic volume were discussed in the broadest generic terms, without being tied to any volume of traffic, not even the 8 million ton figure then projected for the first year. See excerpts printed at the end of EDF I, 467 F.Supp. at 942. The 1971 EIS thus provides no evidentiary basis for finding that a 250% increase in traffic in the initial year will not have significant environmental impacts. Even if the impacts of such traffic levels are qualitatively the same as was discussed in the 1971 EIS, the plaintiffs have offered to prove that they are quantitatively very different and very significant. The defendants made no counter offer of relevant evidence.11
B. Increased Land Use
The district court did consider the 50% increase in land use as a change in the project, but found that
major sections ... will be unaffected by construction, and will not result in destruction of habitat. In other instances, additional lands were acquired to mitigate environmental impact (record citation omitted). Mere increase in the quantity of land for a project does not alone constitute a project change or basis for supplementing the EIS.
501 F.Supp. at 753. These findings are inadequate. First, the question is not whether “major sections” of the new acquisitions will not be affected by construction, but whether some sections will be significantly affected in environmental terms. Second, merely because some of the new land acquisitions may have been intended to “mitigate environmental impact” does not shield those acquisitions from review under NEPA and the Corps’ own regulations. The proper question is not the intent behind the actions, but the significance of the new environmental impacts. And even if the Corps was correct in deciding that the new land use will be beneficial in impact, a beneficial impact must nevertheless be discussed in an EIS, so long as it is significant. NEPA is concerned with all significant environmental effects, not merely adverse ones. Hiram Clarke Civic Club, 476 F.2d at 424-25. Finally, the plaintiffs did not base their claim on a “mere increase in the quantity of land,” but on allegations that the new land would be used in a way that had significant effects on the environment, which obviously could not have been addressed in the 1971 EIS. The affidavit of plaintiffs’ environmental expert avers that at least some significant portion of the new land will be used for spoil disposal, and that conclusion is supported by a Corps memorandum, dated February 5, 1973, which was also part of the record. The plaintiffs also cited the federal defendants’ answer to an interrogatory showing that substantial portions of the new land will be “destroyed or substantially modified,” to use the Corps’ own words.12 In contrast, the federal defendants’ motions and memoranda relating to summary judgment give us no evidence that the new land acquisitions and uses will avoid a significant environmental impact.
C. The New “Chain-of-Lakes” Design
The district court found that there was no material factual dispute concerning the change from a “perched canal” to a “chain-of-lakes” design, even though the plaintiffs’ leading environmental expert testified in deposition that the new design will flood 5,000 additional acres, waterlog an additional 50,000 acres, and create a very different set of environmental dynamics as compared to the previous design.13 The court‘s finding was based on the following rationale:
Plainly, (the new design) was adopted because of its environmental and aesthetic advantages. Additionally, this court has specifically found that the chain-of-lakes design is not a significant change inasmuch as it does not necessitate acquisition of additional real estate and because the acreage to be inundated by the pools is lowland subject to periodic flooding under the original design. 467 F.Supp. at 910. This court also held that the chain-of-lakes concept “does not affect either the scope or purpose of the project, nor does it materially change the plan of improvement.” Id.
501 F.Supp. at 753. The district court‘s reasoning may be summarized in two points: (1) the new design is intended to be environmentally superior, and (2) the 1979 trial on the Corps’ legal authority previously determined that the design change was not significant.
The first point is an inadequate basis for summary judgment to the extent it is based only on the Corps’ intent or belief in making the design change. Even if the Corps correctly decided that the design is superior in terms of overall environmental impact, that decision does not dispose of the material issue before the court: does the design have any significant new environmental impacts, whether beneficial or harmful? The original perched canal design may have been so problematic that the new flooding, waterlogging, and environmental dynamics of the chain-of-lakes design are a net improvement. But as discussed in section B. above, that improvement may still be significant for the purposes of NEPA, and it could not have been discussed in the 1971 EIS.
Clearly a challenge based upon noncompliance with environmental laws presents a different cause of action than the issue of the Corps’ lack of authority to construct a channel with dimensions in excess of statutory authorization.
For this reason, we do not believe that the findings made in the legal authority trial finally determined the environmental issues in dispute in this case. If those findings had even discussed or enumerated significant environmental factors, we would be disposed to expand on the meaning of the court‘s holding and find it applicable to this environmental question. But the court had severed the current environmental issues from the authority issues in EDF II, and the court‘s brief discussion of the chain-of-lakes design in EDF II simply is not concerned with the significance of the new design‘s environmental impact. EDF II, 467 F.Supp. at 909-10. That is the critical issue in this case, and the holdings in EDF II, from whatever viewpoint, did not address it. The doctrine of res judicata does not apply.
We would indeed expect that testimony in the legal authority trial might have been relevant to show the environmental significance of the changes, and the federal defendants could have cited and submitted copies of such testimony to support their motion for summary judgment in this case. International Distribution Corp. v. American District Telegraph Company, 569 F.2d 136, 138 (D.C.Cir.1977). They did not choose to do so.
The plaintiffs presented specific expert testimony that the new design will have very significant new impacts upon the environment. The only response of the Corps was to make general reference to two documents, one by Corps staff and the other by outside consultants, concluding that the new design was superior in overall engineering and environmental terms. The federal defendants’ motions and memoranda relating to summary judgment, therefore, do not cite any evidence to prove that the new design will not have the significant new environmental impacts alleged by the plaintiffs.
D. Straightening of the Tombigbee River
The district court found that the previous trial on the Corps’ legal authority had also resolved all factual dispute concerning the environmental significance of new cutoffs in the Tombigbee River Channel that will isolate 21 miles of the river‘s channel:
(T)his court has heretofore found as a fact that the cutoffs were justified from an engineering standpoint since the amount of excavation otherwise required under the Corps (sic) new bend-widening criteria would have been much greater, and the additional cutoffs “did not affect the scope, purpose or plan of improvement in any material way.” (467 F.Supp. at 410).
We must once again point out that the earlier trial did not address the issue that is relevant to the summary judgment motion. The cutoffs may well be justified from an engineering standpoint, and they may require less excavation than alternative measures,14 but that does not, by itself, negate the significance of any new environmental impact from these cutoffs. Although the earlier finding from EDF II that the new cutoffs do not “affect the scope, purpose or plan of improvement in any material way” would be dispositive if it had been made in the context of an environmental analysis, it was made in the context of an engineering and legal authority analysis. EDF II, 467 F.Supp. at 410. As discussed in section C. above, the earlier trial simply did not address the specific question at issue in this case, and res judicata does not apply.
E. Additional Spoil Disposal
The most extensive excavations in the entire TTW project will occur in northeast Mississippi, where the waterway will cut through a divide to a depth of about 175 feet. The 1971 EIS estimated that this divide cut would excavate 140 million cubic yards of spoil, out of 260 million cubic yards for the entire TTW. The Corps now estimates that the divide cut will excavate an additional 9 million cubic yards of spoil. The district court found that
measures respecting spoil disposal as set forth in the supplemental reports to the EIS are essentially those which were visualized by government witnesses in the 1972 trial, and that these disposal measures have proved to be environmentally sound. Additionally, the present reliable estimate of the quantity of all material to be excavated is not more than 6 1/2 % of the amount of spoil projected in the 1972 EIS, and this increased amount may hardly be considered a significant new environmental impact.
Here, the district court has used the correct legal standard and logical analysis. The 1971 EIS broadly outlined the possible and probable methods of spoil disposal, acknowledging that a final decision had not yet been made. This discussion was found to be sufficient in the 1972 trial, EDF I, 348 F.Supp. at 916, 492 F.2d at 1123, and the plaintiffs have not offered any proof that the disposal of the 9 million additional cubic yards will depart from the methods discussed at that time. And, although 9 million cubic yards is an enormous amount of spoil, it is not a significant amount when viewed in relation to the 260 million tons of spoil disposal already discussed in the 1971 EIS.15 Thus the plaintiffs have not offered any evidence that the environmental impacts of this added spoil will significantly differ in either quantity or quality from those envisioned in the 1971 EIS, unlike all of the other post-1971 changes at issue in this case.
Conclusion: Need for Supplemental EIS
In relation to all of the changes discussed above, the issue before the district court was the reasonableness of the Corps’ decision that the changes, singly or cumulatively, would not have significant new environmental impacts and, therefore, would not necessitate a supplemental EIS under NEPA or
When we look to the reasonableness of the Corps’ decision in light of the plaintiffs’ evidence, we find no solid evidence that the Corps has ever asked the right question, much less answered it reasonably. The Corps offered only a single document that shed some light on the actual decision to file SERs under § 209.410(g)(3) rather than a supplemental EIS under subsection (2). That document is a memorandum from the chief of the Corps’ Office of Policy to the chief of the planning division in charge of the TTW. The memorandum seems merely to confirm some earlier decision to prepare SERs, and reveals only a single standard as the basis for that decision:
The facts to date clearly show, however, that no significant deviations have been discovered or actions taken which were not in the best interest of the natural environment in the project area. Therefore, no new EIS or supplementing statements need be prepared in accordance with the other paragraphs of Section 7 of the regulation (using a parallel citation to the Corps’ internal version of § 209.410(g)).
Memorandum from Irwin Reisler dated May 12, 1975.16 As discussed above, that is simply the wrong standard. NEPA requires the discussion of all significant environmental impacts, not just adverse ones. Hiram Clarke Civic Club, 476 F.2d at 426-27.
V. The Segmentation of the TTW from the BWTW
The plaintiffs also appeal the holding of the district court that the Corps may legally segment the TTW project from the widening and improvements to the BWTW and not submit a supplementary EIS that covers the eventual improvements to the BWTW as well.
As discussed in section I.B. above, the Corps assumed until 1974 that it needed no Congressional authority to widen and improve the 200 foot wide BWTW to accommodate the large levels of traffic that the 300 foot wide TTW will feed into the smaller waterway. Accordingly, the 1971 EIS assumed sub silentio that the BWTW would eventually be widened, but never acknowledged the need for that work. The 8 million tons of annual traffic projected for the TTW in the 1971 EIS were well within the capacity of the BWTW, whether that waterway was improved or not. The Corps discovered in 1975, however, that the BWTW project would require separate authorization, and that the TTW would achieve annual traffic of 28 million tons in the first year. Faced with these new facts, the Corps made a practical decision: it separated the two projects, initiated economic studies of the BWTW improvements, and evaluated the TTW on the basis of the lower traffic levels that the BWTW can accommodate even if it is not widened. At some point and by some means that are not clear from this limited record, the Corps decided that the BWTW could accommodate maximum traffic made up predominantly of 6-barge tows, which would yield a maximum level for the BWTW of 29 million tons annually. Consequently, all relevant projections for the TTW since 1976 assume that it will carry no more than the 29 million tons that the BWTW can currently accommodate, even though the waterway could carry up to 55 million tons annually if the BWTW were widened and improved.
The problem here is that the plaintiffs have made specific offers of proof that the BWTW cannot, in fact, accommodate that 29 million ton level of traffic.17 They thus argue that the vastly greater traffic now projected to use the TTW in its first years will “coerce” approval of the separate BWTW when it comes time to approve that separate project, in order to enable the TTW to carry the minimal level of traffic at which it is economically justified. Accordingly, the plaintiffs believe that the Corps must file an EIS that addresses the environmental impact of the entire TTW-BWTW project. This argument is based on an analogy to highway construction: in certain cases, federal agencies have segmented highway projects and attempted to file an EIS only in relation to a single segment. Reviewing courts have often found that the segments were actually a single project, that each segment was useless without the complete project, and that the entire highway must be evaluated in the EIS rather than allow a piecemeal approach. Ecology Center of Louisiana, Inc. v. Coleman, 515 F.2d 860 (5th Cir. 1975); Named Individual Members of San Antonio Conservation Society v. Texas Highway Dep‘t., 446 F.2d 1013 (5th Cir. 1971). See also Swain v. Brinegar, 542 F.2d 364 (7th Cir. 1976); Indian Lookout Alliance v. Volpe, 484 F.2d 11 (8th Cir. 1973).
As an alternative holding, the district court found that the Corps is not required to file an EIS until it “makes a recommendation or report on a proposal for federal action,” quoting Aberdeen Rockfish R. Co. v. SCRAP, 422 U.S. 289, 320, 95 S.Ct. 2336, 2356, 45 L.Ed.2d 191 (1975). See also Kleppe v. Sierra Club, 427 U.S. 390, 406, 96 S.Ct. 2718, 2725, 49 L.Ed.2d 576 (1976). The district court found that there was no proposal for federal action on the BWTW, and, therefore, no need to file an EIS addressed to that project.
Although we have some doubts that res judicata or the doctrine of laches apply to this issue,18 we agree that no proposal has been made for action on the BWTW. Preparatory designs and studies are still under way, and will not be completed until 1984. Given that conclusion, the Supreme Court‘s opinion in Kleppe clearly indicates that NEPA does not require the filing of an EIS for the BWTW at this time. 427 U.S. at 408-15, 96 S.Ct. at 2729-33. The highway cases cited by the plaintiffs were either decided prior to Kleppe or were based upon a specific regulation of the Federal Highway Administration setting standards for highway segmentation. See, e. g., Swain, 542 F.2d at 368, 370. In addition, many of these highway cases involved two segments that were both proposed actions, and Kleppe allows a court to prohibit segmentation of proposed actions that have “cumulative or synergistic environmental impact.”19 427 U.S. at 410, 96 S.Ct. at 2730. But we are here dealing with two projects that are historically distinct, one of which is proposed and the other still in the process of study and design. In that situation, NEPA does not yet require the Corps to evaluate the environmental impact of the BWTW.20
VI. Review of Cost-Benefit Ratio
Several statutes and regulations set out standards for the Corps to use in the computation of cost-benefit ratios (“CBRs“) for navigation projects.21 The primary, and perhaps exclusive, purpose of most of these statutes and regulations is to provide the Corps and Congress with accurate data to evaluate the economic efficiency of navigation projects. The plaintiffs challenged the accuracy of the CBRs computed for the TTW and submitted to Congress since the 1976 study, alleging that more than 60% of the navigation benefits are illusory, that several of the most significant traffic movements are impossible, and that the BWTW cannot accommodate the assumed levels of traffic flowing from the TTW.22 The district court found that a material factual dispute existed in relation to this issue. EDF III, 501 F.Supp. at 756.
This court specifically considered the 1972 holding of the district court in relation to § 701a. EDF I, 492 F.2d at 1134. We read our opinion in that case as re-opening the issue whether CBRs computed pursuant to § 701a are subject to judicial review. The opinion noted that Phillips was decided prior to the enactment of the Administrative Procedure Act and NEPA, and that those two statutes might create a right to judicial review of an agency‘s CRB computations. We avoided resolution of that question under the APA, however, by finding that NEPA subsumed any rights that might exist under § 701a and the APA:
(Because) NEPA requires a more comprehensive and pervasive weighing of costs and benefits than Section 701a contemplates, whatever rights may exist under that statute have been subsumed by NEPA insofar as our review of the Tennessee-Tombigbee project is concerned.
EDF I, 492 F.2d at 1134. EDF I thus recognized a limited right of judicial review of CBR computations under NEPA23 and left open the question whether the APA might create a right of review of CBRs computed under various other statutes and regulations. See also Sierra Club v. Callaway, 499 F.2d 982, 991-92 (5th Cir. 1974).
The plaintiffs have based their appeal of this issue entirely on the argument that our opinion in South Louisiana Environmental Council, Inc. v. Sand, 629 F.2d 1005, 1012-15 (5th Cir. 1980), created a general right to judicial review of CBRs. A moderately attentive reader of our opinion in that case, however, would readily perceive that Sand approved judicial review of CBRs only when that review was based upon NEPA. Id. Sand thus went no further than this court had already gone in EDF I, 492 F.2d at 1134, 1138-41. But the plaintiffs here cannot justify any review under NEPA because they challenge only those CBRs prepared since 1975, which have never appeared in any EIS. The plaintiffs will be free to challenge these CBRs to the extent they are incorporated into the supplemental EIS that we order the Corps to prepare in section VIII. below.
As for any right to review under the numerous other statutes and regulations raised by the plaintiffs below, the district court briefly discussed these statutes and regulations and found that each one was intended merely to govern preparation of information for the benefit of Congress. On that basis, the court held that there was no right of judicial review of such CBRs under these statutes. EDF III, 501 F.Supp. at 756-58. In their briefs and oral argument before this court, the plaintiffs have not challenged any aspect of these specific holdings of the district court. They are, therefore, not before us on appeal and we specifically decline to affirm them as being the law in this circuit.
VII. Local Assurances of Support
The final issue raised on appeal is whether the Corps complied with certain statutory requirements concerning the form of assurances given by state and local agencies that non-federal portions of project costs would be paid.
A. Compliance with 42 U.S.C. § 1962d-17(b)
The Water Resources Development Act of 1974 (“WRDA“),
The Board therefore recommends that the United States undertake the construction of a waterway ... subject to the condition that local interests give assurances satisfactory to the Secretary of War that they will:
(a) Make and maintain at their expense alterations as required in highways and highway bridges and in sewer, water supply, and drainage facilities.
(b) Provide and maintain at their expense as required suitable and adequate river and canal terminals in accordance with plans approved by the Secretary of War and the Chief of Engineers.
House Document No. 486, pp. 55-56 (emphasis added). The district court then reasoned that the language “assurances satisfactory to the Secretary of War”24 indicated the intent of Congress to commit that decision entirely to the discretion of the Secretary.
The district court omitted one critical logical step from this analysis: neither the district court nor the federal defendants cited any indication that House Document 486, written in 1946, was intended to define the term “satisfactory assurances” as used in
Having found the district court‘s holding to be unsupported, we must return to the original question of law: may the plaintiffs challenge the Corps’ acceptance of local assurances and consequent use of the lower interest rate under
But we also note that the Corps has enacted an internal regulation, Engineer Regulation 405-2-680, that sets very specific standards for the adequacy of local assurances concerning necessary real estate acquisitions. The regulation also requires the district engineer in charge of the relevant project to make specific decisions on the basis of written instruments.25 The Corps is bound “not only by the precepts of its governing statute but also by those incorporated in its own regulations.” Nader v. Nuclear Regulatory Commission, 513 F.2d 1045 (D.C. Cir. 1975). See also Pacific Molasses Company v. FTC, 356 F.2d 386, 389-90 (5th Cir. 1966). The “agency discretion” exception to the APA is very narrow and should be limited to those situations where “statutes are drawn in such broad terms that in a given case there is no law to apply.” Citizens to Preserve Overton Park v. Volpe, 401 U.S. 402, 410 (1971), 91 S. Ct. 814, 820-21. An agency regulation may provide that “law to apply,” Save the Bay, Inc. v. Administrator of E. P. A., 556 F.2d 1282, 1294 (5th Cir. 1977), and we find that ER 405-2-680 establishes such law at least in relation to some of the local assurances required under
There is also a question of the plaintiffs’ standing to raise this issue. Before the district court went astray in its reliance upon House Document No. 486, it found that the plaintiff Louisville & Nashville Railroad Company (“L& N“) had standing to raise the claim because it will be injured by the construction of the TTW, when substantial amounts of coal traffic will be diverted from the railway to the waterway. EDF III, 501 F. Supp. at 262-63. The federal defendants have not challenged this holding, but we believe that the standing issue deserves a closer examination before we proceed to the substantive question.
Because the WRDA establishes no specific right to judicial review of an agency action, the plaintiffs must establish standing under the general provisions of the APA.
Economic injury from business competition created as an indirect consequence of agency actions can serve as the required “injury in fact,” see Data Processing, 397 U.S. at 151-53, but it is arguable that the L&N‘s injury is not caused by the Corps’ use of the lower interest rate under
But the plaintiffs have shown that the Corps’ use of the lower interest rates under
Turning to the second element of standing under the APA, we find that the injury to the L&N is arguably within the zone of interests to be protected by the relevant statute.
The substantive question is considerably easier to dispose of. It is undisputed that the Corps did not comply with the specific requirements contained in ER 405-2-680.30 In fact, the federal defendants’ motions and memoranda on summary judgment have not offered the slightest evidence that any Corps official made the specific determination that the local assurances for the TTW were “satisfactory,” under whatever standard or at whatever time. For that reason, we find that the Corps has not complied with the broader legal requirement contained in
B. The Need for Written Assurances
The plaintiffs also raise a very brief challenge to the district court‘s finding that the Corps is not required to obtain written agreements of local support under
VIII. The Appropriate Remedies
The parties have been of little assistance to us in proposing reasonable and proportionate remedies for the violations discussed above. The plaintiffs seek to enjoin construction of the entire TTW for the slightest infringement, while the federal defendants rarely even address the question of remedies.
A. The Supplemental EIS
When a court has found that a party is in violation of NEPA, the remedy should be shaped so as to fulfill the objectives of the statute as closely as possible, consistent with the broader public interest. An injunction of the federal action at issue is often appropriate, but the injunction should be limited by general equity principles. One beneficial effect of such injunction is to maintain the status quo so that the relevant decision makers and the public may still have the opportunity to choose among alternatives, as required by NEPA. Another purpose is to provide the agency with an incentive to comply with NEPA in as rapid and thorough a manner as is reasonably possible. The court should tailor its relief to fit each particular case, balancing the environmental concerns of NEPA against the larger interests of society that might be adversely affected by an overly broad injunction. See State of Alaska v. Andrus, 580 F.2d 465 (D.C. Cir. 1978), vacated in part on other grounds sub nom. Western Oil & Gas Association v. Alaska, 439 U.S. 922 (1978), 99 S. Ct. 303.
On the issue of the need for a supplemental EIS, we reverse the judgment of the district court and remand the cause for entry of summary judgment for the plaintiffs. The most important remedy available is that the Corps must immediately prepare a supplementary EIS covering all of the changes in the design and economic projections for the TTW that we have discussed in parts IV.A.-D. of this opinion. The EIS must comply with all the requirements of NEPA, both procedural and substantive.
In order to encourage rapid and thorough compliance with NEPA, it is appropriate to impose some injunctive remedy until a final supplemental EIS is filed. A blanket injunction of construction on the entire TTW is not justified, however, because the bulk of this project has been discussed in a valid EIS. The injunction that would most closely fit the Corps’ specific violation of NEPA is one targeted directly at some of the major post-1971 changes in the TTW that will be discussed in the supplemental EIS. We therefore direct the trial court immediately to enjoin (1) the construction or letting of contracts on the chain-of-lakes segment and the cutoffs of the Tombigbee River channel, and (2) any activity significantly affecting the environment of the land acquisitions planned after 1971.33
The district court may allow specific exemptions from this injunction at the request of the Corps and after an evidentiary hearing. Such exemptions shall be granted only if the Corps demonstrates by a preponderance of the evidence that the public interest will suffer irreparable harm, but not based merely upon future increases in cost of construction. The district court shall retain jurisdiction pending the submission of a final supplemental EIS. At that time, the district court may issue whatever order it finds to be appropriate and consistent with this opinion.
B. Correction of Interest Rates and CBRs
We have found that the Corps may not properly use the lower interest rate in CBR computations for the TTW, as provided in
IX. Conclusion
We are extremely reluctant to interfere with the construction of a project that Congress has authorized for the last ten years and that is now 55% complete. But the plaintiffs have established that the Corps has blatantly violated NEPA and its own regulations by refusing to prepare a supplemental EIS on the major changes in the Tennessee-Tombigbee Waterway that have occurred since 1971. Any layperson looking at a list of these changes would at once perceive that such major alterations could have significant environmental impacts. All the expert testimony offered by the parties has confirmed that lay judgment, and the Corps has been at an utter loss for evidence to justify its refusal to file a supplemental EIS. If the limited injunctive relief we have imposed seems harsh or late, the fault lies with the decision of the Corps to ignore its responsibility and to resist this lawsuit while continuing its default. We have discussed in notes 7 and 10, above, the Corps’ new regulations governing the preparation of a supplemental EIS. 45 Fed. Reg. 56760 (1980) (to be codified 33 C.F.R. § 230). They embody what appears to be an accurate perception of NEPA‘s requirements, along with a genuine desire to implement the full spirit of that act. If that kind of clarity and intent had guided the Corps in its decisions for the Tennessee-Tombigbee Waterway from 1975 to 1979, this case would not have been necessary.
To briefly summarize our holdings, we reverse the district court‘s judgment as to the need for a supplemental EIS and remand with directions to enter summary judgment for the plaintiffs, except on the issue of additional spoil disposal, a holding which we join. We affirm the district court‘s judgment that the Corps does not yet need to file a comprehensive EIS addressed to future improvements on the Black Warrior-Tombigbee Waterway. On the issue of general statutory challenges to the cost-benefit ratios for the Tennessee-Tombigbee, we disapprove of the reasons given by the district court in denying relief, but the court‘s judgment stands on alternate grounds not challenged on appeal. Finally, we reverse the judgment that the plaintiff Louisville & Nashville Railroad may not obtain judicial review of the Corps’ compliance with
We direct the district court to impose a temporary injunction affecting certain segments of the waterway, pending the submission of a final supplemental EIS in accord with this opinion. The district court should retain jurisdiction of this cause until that document is submitted to the court, at which time the district court may enter a final order.
AFFIRMED IN PART and REVERSED IN PART.
Notes
Engineer Regulation 405-2-680.The determination of sufficiency of assurances rests with the Division or District Engineer. It is, therefore, essential that the legal authority of the local agency be thoroughly investigated, and that a firm determination be made that the agency has full legal authority, under local laws, to give the assurances. It must also be established to the satisfaction of the Division or District Engineer that the local agency is financially responsible for the fulfillment of all required local cooperation. Finally, the written assurances must be in strict compliance with the pertinent act of Congress, and the instrument or instruments constituting the assurances must be legally sufficient.