Environmental Defense Fund, Inc. v. AlexanderEnvironmental Defense Fund, Inc. v. Alexander
MEMORANDUM OPINION
This is another chapter in the saga of the ongoing controversy relating to the Tennessee-Tombigbee Waterway (TTW), a navigation project in Alabama and Mississippi which Congress authorized in 1946 and commenced funding in 1971.
On July 14, 1971, Environmental Defense Fund, Inc. (EDF), Committee for Leaving the Environment of America Natural (CLEAN) and James D. Williams brought a class action on behalf of all persons aggrieved or detrimentally affected by the project against the Secretary of the Army, Chief of Engineers and United States Corps of Engineers to enjoin construction of TTW. The district court on April 13, 1972, dismissed five of the six causes of action alleged in the complaint and ordered an evidentiary hearing on the cause of action based upon noncompliance with the National Environmental Policy Act of 1969 (NEPA). On August 4,1972, the complaint was dismissed
*746
with prejudice. The district court, while declining to make a substantive review under NEPA, found that defendants had fully complied with NEPA’s procedural requirements,
EDF v. Corps of Engineers,
On November 30,1976, the present action was filed to enjoin the continued construction of the waterway. As before, plaintiffs are EDF, CLEAN and a plaintiff class of individuals aggrieved or detrimentally affected by TTW. Additional plaintiffs are Louisville & Nashville Railroad (L&N), Randall Grace, National Audubon Society, Birmingham Audubon Society and Alabama Conservancy. After extensive discovery, plaintiffs on January 30, 1978, filed an amended complaint which consisted of 15 counts.
In a lengthy evidentiary hearing on the first two counts, the district court held that plaintiffs’ primary claim that defendants lacked statutory authorization to construct a channel 300' wide was barred by laches, and that other challenges to modifications of original project design were without merit.
EDF v. Alexander,
Following status conference on May 30, 1980, the court dismissed Count XI upon motion of plaintiffs and scheduled the remaining 12 counts to be considered for disposition on cross-motions for summary judgment and defendants’ alternative motion for judgment on the pleadings. The parties have submitted a plethora of exhibits and affidavits as well as voluminous briefs in support of their respective motions.
After due consideration, the court finds that plaintiffs are not entitled to prevail and their amended complaint is dismissed with prejudice, except in one particular as to Count XIV. Instead of treating the counts seriatim, the court has organized discussion of the remaining claims as follows: (1) NEPA issues, (2) benefit/cost computation, (3) local assurances, (4) fish and wildlife, (5) discharge of dredged material, and (6) failure to publish agency regulations.
I. NEPA ISSUES
In Counts VII, VIII, IX and X, plaintiffs challenge a variety of environmental and economic aspects of the project which they claim violate NEPA,
(1) illegal segmentation of TTW into two parts, one a waterway between Pickwick Pool in Tennessee and Demopolis, Alabama, and the other a waterway between Demopolis and Mobile, and failure to prepare, circulate and file an Environmental Impact Statement (EIS) discussing the effects on both segments before continuing con- ■ struction;
(2) failure to analyze and disclose project alternatives in the 1976 Economic Reanalysis Summary;
(3) failure to prepare a supplemental or revised EIS after making major changes in project design and subsequently identifying adverse environmental and economic impacts.
Defendants contend that plaintiffs, in attempting to raise charges of NEPA noncompliance, have failed to state claims upon which relief can be granted or that, since there is no genuine issue of material fact, defendants are entitled to summary judgment on all NEPA issues.
Of the many environmental challenges made by plaintiffs, the primary complaint is that the 1976 Economic Reanalysis Summary revealed for the first time that “TTW’s *747 fundamental purpose was to move goods from waters north of Pickwick, Tennessee, through Demopolis, Alabama, and down the river below Demopolis to Mobile,” and it was then first disclosed that TTW would require work downstream from Demopolis to achieve maximum navigation benefits. According to plaintiffs, when Corps officials in 1975 discovered that 8-barge tows could not navigate south of Demopolis, they decided to divide the TTW project by treating the 300' waterway between Pickwick and Demopolis separately from the 200' waterway between Demopolis and Mobile, and to continue construction on the northern part while studying need for work on the southern part. It is urged that this procedure contravenes NEPA since an EIS on the entire project-Pickwick to Mobile-must be prepared, published and filed before work may continue north of Demopolis. No EIS on the TTW, so plaintiffs contend, has ever discussed and analyzed the impacts of the project upon the river south of Demopolis or upon the Port of Mobile.
In advancing this contention plaintiffs ignore the history of TTW, Black WarriorTombigbee River (BWT) and the Port of Mobile as separate congressionally-authorized navigation projects as well as the adjudication that defendants have fully complied with NEPA. This court has previously recounted TTW’s history. The salient features are that TTW’s original 1939 survey, as contained in House Document 269, reported that the “improvement desired is a navigable waterway of dimensions which would permit modern barge-line operation between the Tennessee and Tombigbee Rivers.” 1 House Document 486, which was incorporated in the authorizing statute, Pub.L.No. 79-525, 79th Cong., 2d Sess., enacted July 24, 1946, discussed the “function of the canal and its connections as a through route between the Gulf of Mexico and the Ohio, upper Mississippi, Missouri, and Illinois Rivers.” 2 As we have previously found, TTW was designed from its inception as
a navigational project for two-way barge traffic to connect the north-flowing Tennessee River with the south-flowing Tombigbee River so as to provide a continuous waterway from the Tennessee, upper Mississippi and Ohio Valleys to the tidewater Port of Mobile on the Gulf of Mexico. The territorial limits of the TTW, however, extended northward from Demopolis, Alabama, on the existing canalized BWT, a separate navigation project, upstream via the Tombigbee River, East Fork of the Tombigbee, Mackeys Creek, with a deep cut through the divide into Yellow Creek, then to the Pickwick Pool in the Tennessee River near the common boundary of the states of Tennessee, Alabama and Mississippi. The original overall project length — Demopolis to Pickwick Pool, corrected by cutoffs — was 260 miles.
House Document 486 specifically discussed the relationship of the TTW with the connecting Tennessee River and the 200' wide Warrior-Tombigbee Waterway, also known as Black Warrior-Tombigbee. 3 Plans for TTW were deferred for a number of years until the project’s economics were completely reevaluated in June 1966. The original design of a 170' channel was then dropped “since that width would unduly restrict tow size and would not be comparable to the connecting channels in the Tennessee and Black Warrior-Tombigbee waterway,” 4 and the 1966 study recommended a 300' wide channel to “enable waterway carriers to operate 8-barge tows in two-way traffic,” rather than a 200' channel for 6-barge tows. 5
The BWT, south of Demopolis, however, still remained with no more than a 200' authorized channel width, and limited lock capacity. Both of these factors precluded efficient navigation of 8-barge *748 tows on that waterway. In recognition of this, the reevaluation report included in the cost of the TTW project “adding duplicate locks at the Jackson and Demopolis projects when the combined traffic on the Black Warrior-Tombigbee and Tennessee-Tombigbee exceed the capacities of the single locks at those locations.” 6
The 1966 evaluation report submitted by General Cassidy, then Chief of Engineers, to the Secretary of War, specifically recommended a 300', and not a 200', channel width for TTW. This court has previously found:
Although it is apparent that both the 1966 reevaluation report and General Cassidy assumed a positive BCR was based upon navigation benefits of 8-barge tows operating between the Tennessee River and Mobile, this assumption did take into account reduced tow speeds, and hence lesser navigation bénefits because of existing constraints of the BWT south of Demopolis to 8-barge tows.
The 1966 supplement did not anticipate the need for duplicate locks south of Demopolis until the year 2010 when TTW’s projected traffic would reach 28 million tons annually. 7 Project capacity, 39 million tons annually, was anticipated by the year 2026. 8 The 1976 report, upon the basis of present studies of prospective commerce on TTW and BWT, found that the duplicate locks would be required at an earlier date after the completion of TTW, then scheduled for 1986, and also the navigation constraints to 8-barge tows would exist in the BWT at various locations. 9 The report recommended that work continue on TTW and a feasibility report be prepared to investigate more fully downstream navigation work and duplicate locks.
BWT and Mobile Harbor are long-established waterways which Congress tradition- ^ ally has regarded as entirely separate from TTW, and plaintiffs’ fears that TTW’s construction will have “coercive” effects upon them are unfounded. The connecting BWT has been a navigation project for which Congress has appropriated funds since 1884. 10 Channel dimensions of 9' X 200' as well as the Oliver Lock were authorized in 1935. 11 First funded by the Rivers and Harbors Act of May 20, 1826, Mobile Harbor has been the subject of many appropriation acts, and present channels were authorized by the Rivers and Harbors Act of September 3, 1954. 12 The increased depth of Theodore Ship Channel, to which plaintiffs allude, was first authorized in 1970, 13 and is a project for which a final EIS was filed in 1977 with the Council on Environmental Quality (CEQ). 14
It is clear that when the first action was filed attacking the sufficiency of the 1971 EIS and the Corps’ failure to comply with NEPA, constraints to 8-barge traffic were known to exist and, if TTW’s capacity was to be fully utilized, downstream work on the BWT would be needed. All arguments which plaintiffs now make as to the insufficiency of the original EIS and the need for it to analyze in detail the environmental impacts of TTW on the BWT and Mobile Harbor could have been raised in the original suit. The same can be said of the alleged failure to consider a 200' channel
*749
rather than a 300' channel, for these very alternatives were prominently discussed in the 1966 Supplement. As the pleadings, trial transcript and court opinions in the first case clearly reveal, the adequacy of. the 1971 EIS was vigorously challenged on numerous grounds, not only for alleged insufficient analysis and treatment of matters which were discussed, but also for many items of environmental and economic concern which the plaintiffs there contended had been completely omitted from the document.
15
Moreover, the alternatives of rail transportation and no action, as well as the project’s economic justification, were specifically detailed in the EIS, and unsuccessfully challenged. The Court of Appeals made a final determination on the merits that the Corps officials had complied in all respects with the procedural and substantive requirements of NEPA,
All of the present parties who were plaintiffs in the first action-EDF, CLEAN, and the plaintiff class, including Dr. Glenn Clemmer and Dr. F. Glenn Liming-are precluded by res judicata from re-litigating any questions of NEPA compliance which could have been raised in the first suit, and this bars them from now complaining that the EIS should have dealt with impacts on the BWT and Mobile Harbor, or more fully considered project alternatives or TTW’s economics.
The purpose of the doctrine of res judicata is to promote finality of judgment and judicial economy by eliminating nee'dless re-litigation of claims for relief.
Maher v. City of New Orleans,
Is the same right infringed by the same wrong? Would a different judgment obtained in the second action impair rights under the first judgment? Would the same evidence sustain both judgments?
Aerojet-General Corp. v. Askew,
The doctrine of “virtual representation” applies when a party’s interest in a suit is “so closely aligned with [a nonparty’s interest] as to be his virtual representative.”
Pollard v. Cockrell,
Even if res judicata is not effective as to L&N, Randall Grace and three organizational plaintiffs, they are nonetheless subject to the defense of collateral estoppel which prevents them from relitigating issues which were decided on their merits in the earlier case, even though a different cause of action is now presented.
Maher, supra; International Ass’n of Machinists & Aerospace Workers v. Nix,
An alternative ground for our holding is that the 1976 study does not constitute a “recommendation or report on proposals for legislation and other major Federal action significantly affecting the quality of the human environment,” so as to require an EIS, under
The procedural duty imposed upon agencies by this section is quite precise, and the role of the courts in enforcing that duty is similarly precise. A court has no authority to depart from the statutory language and, by a balancing of court-devised factors, determine a point during the germination process of a potential proposal at which an impact statement should be prepared. Such an assertion of judicial authority would leave the agencies uncertain as to their procedural duties under NEPA, would invite judicial involvement in the day-to-day decision-making process of the agencies, and would invite litigation. As the contemplation of a project and the accompanying study thereof do not necessarily result in a proposal for major federal action, it may be assumed that the balanc *751 ing process devised by the Court of Appeals also would result in the preparation of a good many unnecessary impact statements. (Emphasis in original text).
speaks solely in terms of proposed actions; it does not require an agency to consider the possible environmental impacts of less imminent actions when preparing the impact statement on proposed actions. Should contemplated actions later reach the stage of actual proposals, impact statements on them will take into account the effect of their approval upon the existing environment; and the condition of that environment presumably will reflect earlier proposed actions and their effects.
The Fifth Circuit applied
Kleppe’s
rationale in
Atlanta Coalition v. Atlanta Regional Comm’n,
Although the Kleppe Court accepted in part the thesis that proposed actions with “cumulative or synergistic” effects may require a comprehensive EIS, it added the qualification that an agency need not “consider the possible environmental impacts of less imminent actions when preparing the impact statement on proposed actions.” Id. at 410 n.20,96 S.Ct. at 2730 n.20. . .. Since it is clear that many, if not most, of the individual transportation projects included in the [Regional Development Plan] are not “proposed” federal actions — some will not ever be implemented, others not for another ten or twenty years — but are, at best, “contemplated” actions, the impact statement prepared on proposed projects . . . need not address the environmental impact of the entire RDP.
In
Texas Committee on Natural Resources v. Bergland,
We hold that since neither the BWT improvements mentioned by the Corps in the 1976 report nor the Mobile Harbor improvement alluded to by plaintiffs have reached the proposal stage, there is no requirement that an EIS be prepared to discuss the environmental impacts of such improvements.
Finally, we look at the claim that a supplemental EIS must be prepared because of the subsequent identification of adverse impacts or design changes after the original EIS was judicially approved in 1972. NEPA itself contains no such requirement, but plaintiffs stress that Corps regulations adopted in 1974 do and that they have not been adhered to. The record shows that Corps officials updated the original EIS by compiling and submitting to CEQ 18 volumes entitled First and Second Supplemental Environmental Reports to be appended to the EIS. Summaries of these reports have been received in evidence. (D. Ex. 8, 9). Corps officials claim that this procedure
*752
has satisfied the applicable regulation,
Plaintiffs claim that significant project changes occurring since the 1971 EIS include (a) increase of project land acquisition from. 70,000 acres to 105,000 acres; (b) changing from a “perched canal” to the “chain-of-lakes” concept in the canal section; (c) shortening the river section by 20 miles; and (d) taking additional spoil material excavated in the divide cut section.
These claims, both singly and collectively, are without merit. It is clear that major sections of more acreage in the river, canal and divide cut sections will be unaffected by construction, and will not result in destruction of habitat. In other instances, additional lands were acquired to mitigate environmental impact. (D. Ex. 47). Mere increase in the quantity of land for a project does not alone constitute a project change or basis for supplementing the EIS. Plainly, the chain-of-lakes design in the canal section was adopted because of its environmental and aesthetic advantages. Additionally, this court has specifically found that the chain-of-lakes design is not a significant change inasmuch as it does not necessitate acquisition of additional real estate and because the acreage to be inundated by the pools is lowland subject to periodic flooding under the original design.
As for shortening the river section, this court has heretofore found as a fact that the cutoffs were justified from an engineering standpoint since the amount of excavation otherwise required under the Corps new bend-widening criteria would have been much greater, and the additional cutoffs “did not affect the scope, purpose or plan of improvement in any material way.” Id. Res judicata bars relitigation of plaintiffs’ contentions as to the chain-of-lakes concept and shortening of the river.
As for spoil disposal, the excavation of more spoil may hardly be considered as a “design change.” In any event, in the original suit, spoil was identified in the EIS as a significant impact
for the proper disposition of which judicious planning will be required. The EIS further states that “the optimum methods for the disposal of all this material have not been determined;” and various proposals were under consideration for utilization of the excavated material in a most advantageous manner, to enhance the present environment. . . . The evidence convinces the court that environmental design arts are being employed in the project’s advanced engineering stages which will lessen the potential adverse effects of the spoil. Contrary to opinions expressed by some of plaintiffs’ witnesses, it will be wholly impracticable to require that the ultimate environmental design for the disposition of this material be included in the EIS.
In
Inman Park Restoration, Inc. v. Urban Mass Transportation Administration,
Plaintiffs also contend that a revised EIS is essential because significant new information has been gained since 1971 as to certain categories of impacts which the original EIS discussed only in general terms. This claim relates to such matters as waterlogging, sedimentation and water quality, disposal or dredged spoil, and fish and wildlife mitigation lands. But these very items were specifically identified as impacts in the original EIS, and can hardly be characterized as significant new impacts under
Moreover, the Corps’ final regulation for implementing NEPA, adopted August 25, 1980, and found in 45 Fed.Reg. 56760-56786 is merely declaratory of the previous regulation ER 1105-2-207. With respect to projects in a continuing construction category, the applicable portion of the final regulation, 45 Fed.Reg. 56785, provides that a new EIS is not required in the absence of significant environmental impacts from design changes or new circumstances occurring since the completion of the Phase II GDM. The court finds that the exceptional conditions are not here present.
The court therefore concludes that the Corps officials correctly determined that a revised EIS for TTW did not become necessary or appropriate under its regulations and that they acted properly by filing supplemental reports to the EIS which adequately clarify and amplify all points of environmental concern. The argument that the Corps failed to comply with its own regulation must be rejected. Accordingly, Counts VII, VIII, IX and X are dismissed for failure to state a claim upon which relief can be granted.
II. BENEFIT/COST COMPUTATIONS
In Counts III and VI plaintiffs attack TTW’s economic justification by claiming that defendants have not adhered to statutory and regulatory requirements for computing benefits and costs. Plaintiffs allege various ways in which the project’s benefits have been greatly inflated and falsely overstated and costs grossly understated, maintaining that a correct comparison of true benefits and true costs would reveal a benefit/cost ratio (BCR) less than 1, a condition requiring the Corps to deter the project and they say that defendants have deliberately misrepresented the benefits and costs to the public and Congress. Count III specifically charges defendants have violated the Water Resources Planning Act of 1965,
Defendants interpose several defenses to these issues of economic justification: first, that plaintiffs lost on such claims in the former litigation and are barred from relitigating them by invoking different statutes than those previously relied upon; second, that benefit/cost computations are agency decisions which, apart from NEPA, are not subject to judicial review; and third, that Congress has affirmed the benefit/cost computations submitted by Corps officials by making annual appropriations to TTW and courts may not review congressional decisions of this character. We find merit in these positions.
Certain basic facts are undisputed. On March 30, 1967, Congress was advised that TTW, based on a 50-year project life, had an estimated BCR of 1.24 and, in the opinion of then Secretary of Army Resor, the proposed investment (then estimated at $316 million) was “only marginally justified.”
By February 1975, the Corps ascertained that the BCR had fallen to 1.4, and the project’s cost had risen to $815,000,000. Corps officials realized that inflation and other factors of increased costs threatened to drive the BCR below 1. In March 1975 the Corps advised Congress:
Current estimates [of benefits] are based on field traffic survey data collected in 1964 and reflects [sic] base year conditions as of 1963. Due to the recent rapid escalation of transportation and construction costs and the lengthy period since the 1963 field survey, an economic reanalysis based on new field traffic surveys, current freight rate analyses and updated construction costs has been initiated. The results of this analysis will be available in January 1976. 19
Thereafter, Corps officials engaged A. T. Kearney & Company, management consultants, to make an extensive' study of the transportation economics of TTW.
The results of the Kearney investigation and other data were incorporated in the 1976 Economic Reanalysis Summary. As previously noted, this study dealt with three areas of evaluation: (a) the basic project plan, or the authorized TTW which extended from Demopolis Lake to Pickwick Reservoir; (b) navigation work on the BWT downriver from Demopolis; and (c) duplicate lock construction at Demopolis and Coffeeville. While noting that plans (b) and (c) were not authorized, the report stated that, despite the identified constraints, TTW was “economically justifiable, but in view of the current projections of traffic the plan [authorized TTW] would neither provide for the orderly development of Waterway capacity nor for the optimization of project benefits.” The report estimated that the authorized project still had a positive BCR, at 1.08, with annual benefits of $88,896,000 and annual charges of $82,339,-000. At October 1975 price levels, TTW’s total cost was calculated at $1,360,400,000. Twenty-eight million tons of commerce, principally coal and metallic ore shipments, were estimated for the initial year of completion, 1986, to derive transportation savings of $55.5 million. The report also brought out that the carrying capacity of the 300' TTW would be constrained by the 200' BWT downriver from Demopolis by necessitating the use of 6-barge, and not 8-barge, tows on that portion of the river and by the need for duplicate locks. If both hindrances were overcome, the BCR would rise to 1.30.
*756 Plaintiffs assail the accuracy of the 1976 economic reanalysis and say that, to arrive at 28 million tons of traffic moving over the TTW in 1986, the Corps has had to assume that the BWT south of Demopolis can accommodate two-way 8-barge traffic and has ignored the admitted constraints. According to plaintiffs, the 200' BWT can safely accommodate two-way traffic of no more than 4-barge tows. Plaintiffs also vigorously challenge the methodology of the Kearney transportation survey, claiming that it is based upon numerous false assumptions, incorrect and nonexistent data and completely fails to comply with traffic formulas mandated by statute as well as by the Corps’ own regulations.
Plaintiffs present the affidavits of Dr. Joseph L. Carroll and Dr. Robert Haveman, economic experts, and other specialists which provide substantial factual support for their contentions. Defendants offer counteraffidavits of experts who furnish contrary opinions. Thus, genuine issues of material fact are raised which preclude the court from granting summary judgment if issues relating to benefit/cost computations are judicially reviewable.
We continue to be of the opinion that benefit/cost computations insofar as TTW is concerned are not judicially reviewable. In the first place, plaintiffs are prevented from relitigating these issues. Plaintiffs in the first suit contended that “the navigation benefits were substantially overstated by the Corps,”
Plaintiffs’ second ground for not applying res judicata is that several parties plaintiff in the case sub judice were not before the court in the earlier suit and that therefore they cannot be bound by that suit. As previously noted, if the “new” plaintiffs are not bound by res judicata under the virtual representation doctrine, they are surely precluded by collateral estoppel from relitigating identical issues. We therefore sustain defendants’ pleas of res judicata and collateral estoppel and conclude that we are barred from reconsidering the issue whether BCR calculations are judicially reviewable under the cited statutes.
Apart from res judicata, most courts have ruled there is no independent right of judicial review of statutes providing for benefit/cost computations by agencies for congressional review and action on public works projects.
See, e. g., Sierra Club v. Froehlke,
These statutes and regulations serve the same purpose as
It is for the Congress to determine, in authorizing such a project and in, thereafter, making subsequent appropriations therefor, whether the benefits are “in excess of the estimated costs.” The Court does not believe that it has the authority to enjoin the expenditure of appropriated funds upon a showing that the benefits are less than the estimated cost. The plaintiffs and others are free to bring such matters to the attention of the legislative branch at the time any new appropriation for this project is proposed. Indeed, they could bring the matter to the attention of Congress at this time with the hope of obtaining legislation which would prevent the expenditure of funds already appropriated (which would obviously include those needed for the construction of the dam proper and the clearing of the lake). The methods of calculating cost-benefit ratios are innumerable and in many cases esoteric. The Court’s judgment as to sound procedures in this regard might well not be in accord with the judgment of Congress. And, as stated above, the Court does not believe it should, in any event, attempt to substitute its judgment for that of the legislature. (emphasis in original text).
The same result may be found in
Duck River Preservation Ass’n v. TVA,
A case relied upon by both sides is Atchison, supra, which construes the statutes at issue here. In Atchison the district court *758 denied review of BCRs in the absence of NEPA 22 because “Congress intended those laws to serve a more limited purpose than NEPA.” Id. at 977. Thus, “[t]he judiciary should defer to congressional expertise in the weighing of costs and benefits, except where Congress has indicated that judicial scrutiny is appropriate.” Id. Finding a lack of such indication in congressional silence, the court declined to review agency action, reasoning as follows:
[These statutes’ and regulations’] primary goal is to provide the President and Congress with guidance in their planning efforts in the water resources field. See H.R.Rep.No.169, 89th Cong., 1st Sess. 3 & 5 (1965), U.S.Code Cong. & Admin.News 1965, p. 1921. Because these guidelines are intended for the primary benefit of Congress and the President, approval of a recommended project by these lawmakers vitiates whatever claims a party may possess regarding the Corps of Engineers compliance with the Act and regulations thereunder. In this case, Congress has itself weighed the costs and benefits and, by authorizing construction, indicated its finding that the benefits exceeded costs, within the meaning of the Water Resources Planning Act. Once Congress has reached a decision on this matter, courts should decline to interfere with the legislative judgment. Cf. Oklahoma ex rel. Phillips v. Guy F. Atkinson Co.,313 U.S. 508 , 527-528,61 S.Ct. 1050 , 1060,85 L.Ed. 1487 (1941). In contrast to NEPA, Congress did not envision continuing judicial review to determine compliance with the Act.... All of the defects could have been — or were in fact — brought to the attention of Congress during the legislative process; yet, Congress decided to accept the proposal despite the alleged non-compliance with [these provisions]. The Court believes that congressional approval ... is tantamount to a finding that these oversights either never occurred or were, for the purposes of [these provisions], insignificant. It would certainly constitute an invasion of the legislative process for this Court to breathe new life into these allegations and then seek to determine their accuracy. Id. at 978.
Finally, as held by the Fifth Circuit, Congress is the “ultimate decisionmaker” of the TTW. That court has explicitly held that although BCRs were reviewable through NEPA, even that review was foreclosed because Congress had determined that the waterway should be built. It must be emphasized that it is the Congress-not the Corps of Engineers-which has to this date 22 ® continued massive funding of the project.
The record discloses that, just as in
Atchison, supra,
at 978 n.l, plaintiffs have presented to Congress allegations that the Corps has furnished Congress with false and misleading information about the waterway’s benefits and costs. Congress, at least since 1975, has considered not only data submitted by the Corps but also information supplied by plaintiffs, including the allegations of misrepresentation made here.
23
The Corps itself reported to Con
*759
gress the substance of plaintiffs’ allegations on justification sheets for the fiscal years 1979-1981. Notwithstanding plaintiffs’ allegations, Congress has not discontinued its support for the project.
See EDF v. Alexander,
■Plaintiffs argue that
TVA v. Hill,
For the foregoing reasons, plaintiffs have failed to state claims in Counts III and VI upon which relief can be granted, and those counts must be dismissed with prejudice.
III. LOCAL ASSURANCES
(a) Discount Rate.
In Count IV plaintiffs allege that the defendants are violating § 80 of the Water Resources Development Act of 1974,
By § 80(a) of the Water Resources Development Act,
Both sides seek summary judgment on this claim, and defendants also move for judgment on the pleadings. Plaintiffs urge that neither Alabama’s nor Mississippi’s assurances prior to December 31, 1969, or indeed since that date, are in fact satisfactory, that the assurances which have been given fail to satisfy Corps criteria, and that, since there is no reasonable prospect that the required local contributions will be forthcoming, the Corps has been under a duty since 1974 to place TTW in deferred status. Federal defendants mount several defenses: first, the plaintiffs have no standing to challenge a violation of § 80 of the Water Resources Development Act of 1974; second, that the determination of adequacy of local assurances of support for TTW, being solely a matter of agency discretion with no law or standards for a court *761 to apply, is not susceptible to review under the Administrative Procedure Act; third, that plaintiffs’ challenge to the 3*/4% interest rate is barred by principles of res judicata, collateral estoppel and laches; fourth, that, if the merits of the claim are reached, plaintiffs cannot show the agency’s determination as to sufficiency of local contribution to be arbitrary and capricious; and finally, that even if a higher interest rate should be applied in computing, the benefits and costs of TTW, the remedy is not to grant plaintiffs an injunction but to require that Corps officials submit a revised benefit/cost analysis to Congress on the basis of the new rate. 26
We first address the issue of standing since it poses a serious question whether plaintiffs may complain about a violation of § 80(b). To have standing plaintiffs must (1) allege and establish some injury-in-fact, and (2) show the interest they seek to represent is “arguably” within the zone of interests protected by the statute.
Sierra Club v. Morton,
Two cases support the view that environmental plaintiffs have no § 80 standing. In
Sierra Club v. Froehlke,
Akers v. Resor,
do not have standing to complain about a failure to comply with the aforesaid statutory provision. The interest that the plaintiffs seek to protect is that of ecology; and since such interest is not arguably within the zone of interest intended to be protected by this statutory provision, they do not have standing.
Id. at 1378 (citing Data Processing, supra).
Plaintiffs cite two cases which recognize § 80 standing.
Concerned Residents of Buck Hill Falls v. Grant,
In
Baxley,
the district court held that the State of Alabama, in an action brought by the state attorney general, had standing to sue under § 80.
Plaintiffs also urge that, quite apart from environmental concerns, Louisville and Nashville Railroad (L&N) has § 80 standing because it will sustain economic injury upon the completion of the waterway. In this respect, plaintiffs allege that substantial shipments of coal and other commodities will be diverted from rail to water transportation when TTW becomes operational, and that, unlike L&N, which has had to purchase and maintain its rights-of-way and pay taxes thereon, barge operators will use the waterway free of such costs, thus placing L&N “at a decided competitive disadvantage in the economic competition for coal and other commodities now moving over plaintiff’s rail lines.” Amended Complaint, App. ¶¶ 2, 3. Based on these allegations, it is contended that the railroad will sustain economic injury if the federal defendants are allowed to construct a waterway which cannot be economically justified.
It is well-settled law that, to make a case or controversy, cognizable in the federal courts, the injury alleged by a party must be concrete, not abstract; it must be objective, not speculative; and the threat of injury must be both real and immediate, not conjectural or hypothetical.
O’Shea v. Littleton,
However, we further conclude that plaintiffs’ claim under
House Document No. 486, which was incorporated into TTW’s authorizing statute, Pub.L.No. 79-525, provides as follows:
The Board therefore recommends that the United States undertake the construction of a waterway . . . subject to the condition that local interests give assurances satisfactory to the Secretary of War * that they will:
(a) Make and maintain at their expense alterations as required in highways and highway bridges and in sewer, water supply, and drainage facilities.
(b) Provide and maintain at their expense as required suitable and adequate river and canal terminals in accordance with plans approved by the Secretary of War and the Chief of Engineers. (House Document No. 486, p. 55-56). (Emphasis added).
By its plain terms, the statute confers upon a designated public official-the Secretary of the Army-the sole responsibility and discretion for determining the satisfactoriness or sufficiency of the local assurances, and the discretion thus delegated to him by Congress is not reviewable in the courts. Manifestly, no standards are articulated in the authorizing statute or the underlying House Document for determining the sufficiency of the required local assurances. Consequently, the language is “drawn in such broad terms that . . . there is no law to apply.”
Citizens to Preserve Overton Park v. Volpe, supra,
the public law does not articulate any specific standard. The Act voices only a broadly stated objective, which gives the Secretary of the Army authority to exercise his discretion in obtaining assurances from Indiana of “maximum feasible” pollution control in Burns Harbor.. .. We think the Secretary’s acceptance of Indiana’s submission is the end of the matter as regards the applicability of Public Law 89-298.
Plaintiffs again rely upon
Baxley,
a case relating to a Corps project for channeliza
*764
tion of Luxapalila Creek, a tributary of the Tombigbee River, carried out under the Flood Control Act of 1958, Pub.L.No. 85-500. Local interests were required to obtain necessary easements and relocate roads and bridges. District Judge Hancock, in
Baxley,
found the phrase “satisfactory assurances” in § 80(b) was used “in a general nonspecific sense and vests no particular public official with the authority to make a determination of precisely what degree of assurances is required in order to be considered ‘satisfactory.’ ”
Moreover, the record shows beyond dispute that the Secretary of the Army has found that satisfactory assurances of the non-Federal costs have been given. These assurances have been annually documented by his delegate, the Chief of Engineers, in justification data submitted to Congress. (D.Ex. 38, 39, offered at the Authorization Hearing). Each year since the start of the project there has been a detailed statement made as to the nature and extent of the local contributions. This procedure began in 1970, when the estimated non-Federal cost was $38,100,000 and has continued through 1980 when such cost has climbed to $137,000,000. In no instance has the Secretary of the Army noted on the cost justification sheets dissatisfaction with the stated local support, nor has he ever taken exception to the sufficiency of those assurances. The court can find no reason not to take this documentation at face value and concludes that the Secretary of the Army has in fact accepted as satisfactory to him local assurances for providing non-Federal costs.
This disposition of the
(b) Written Agreements.
Count V of the amended complaint alleges that defendants have violated § 221 of the Rivers and Harbors Act of 1970,
On May 25, 1971, the President of the United States at Mobile, Alabama, presided over the dedication and groundbreaking of the project. Congress first appropriated construction funds of $1,000,000 for the fiscal year 1971 ending June 30, 1971. Pub. L.No. 91-439, 84 Stat. 890.
28
A portion of this appropriation was earmarked for the purchase of land at the Gainesville Construction area. In August 1971 the Corps of Engineers, using TTW-appropriated funds, acquired the first real estate in Greene County, Alabama, for the Gaines-ville Lock and Approach Channel. In September 1971, the project was halted by plaintiffs when they obtained an injunction from the United States District Court for the District of Columbia, which recited in a memorandum opinion that “[ajctual construction of the Tennessee-Tombigbee Waterway has not yet begun.”
EDF v. Corps of Engineers,
From the foregoing facts, it is clear that the Secretary of the Army in 1971 regarded construction of the TTW to have commenced with the first acquisition of real estate in August of that year. We believe this was a reasonable interpretation of
*766
Moreover, it is evident that any delay in project commencement beyond January 1, 1972, was occasioned entirely by the preliminary injunction sought by plaintiffs and they are in no position to assert that
Accordingly, defendants are entitled to summary judgment on this issue, and Count V will be dismissed with prejudice.
IV. FISH AND WILDLIFE
By Count XIII of their amended complaint, plaintiffs charge that defendants violated the Fish and Wildlife Coordination Act of 1934 (FWCA),
As to the first ground, plaintiffs respond by asserting that the “narrow issue” in the prior case was only whether the Secretary of Interior could delegate his functions under
This court agrees with defendants on both grounds.
In the previous action, plaintiffs alleged, as a second cause of action, the Corps’ failure to comply with FWCA. We dismissed the FWCA cause of action in a bench ruling for failure to state a claim by holding that this statute, among others, enacted long before the adoption of NEPA, did not provide a right of action for private parties. We stated that FWCA was passed to direct responsible federal officials to consult with other governmental agencies before carrying out a particular project and to furnish Congress data for its own legislative purposes.
Additionally, most courts confronted with the question have held that
The Eighth Circuit in
EDF v. Froehlke, supra,
upheld the trial court’s dismissal of a separate count in a complaint based on FWCA noncompliance where the counts also charged violation of NEPA. The Court of Appeals approved the reasoning of District Judge Eisele that “if the Corps complies with NEPA in good faith, it will ‘automatically take into consideration all of the factors required by the Fish and Wildlife Act and it is not reasonable to require them to do both separately.”’
We endorse the above reasoning. Any separate claim by plaintiffs that the defendants did not comply with FWCA is merged with and subsumed by their claim in those counts based upon NEPA. We therefore hold that defendants are entitled to judgment on the pleadings as to Count XIII on the ground that it fails to state a claim upon which relief can be granted.
V. DISCHARGE OF DREDGED MATERIAL
Count XII of plaintiffs’ amended complaint alleges violation of the Federal Water Pollution Control Act (FWPCA) as amended by the Clean Water Act of 1977,
The Aberdeen Lake navigation channel will require the excavation of approximately 5 million cubic yards of material, mainly consisting of sand and gravel; the Columbus Lake navigation channel will require dredging of 30 million cubic yards of material; and the Aliceville Lake navigation channel will require the excavation of 15 million cubic yards of material. Furthermore, construction of the locks and dams will require excavation of approximately 23,500,000 cubic yards of earth. In addition, maintenance of the project will require excavation of over 500,000 cubic yards annually. Obviously, this material must be disposed of in some way. It is the method of disposal and the selection of disposal sites, particularly those sites which affect wetlands, to which plaintiffs object in this count. Both sides have moved for summary judgment.
Defendants first maintain that this count should be dismissed for lack of jurisdiction inasmuch as plaintiffs have failed to comply with FWPCA jurisdictional prerequisite.
The circuits are split as to whether the notice requirement in
Nothing in this section shall restrict any right which any person (or class of persons) may have under any statute or common law to seek enforcement of any effluent standard or limitation or to seek any other relief (including relief against the Administrator or a State agency).
We agree with the Third Circuit decision in
National Sea Clammers Ass’n, supra,
that
(a)
Section 404 (S
Section 404 of the FWPCA, as amended by the Clean Water Act of 1977, provides that a permit for discharging dredged or fill materials into navigable waters must be obtained from the Secretary of the Army after notice and opportunity for public hearings. Plaintiffs contend that this section and the regulations adopted thereunder (
The regulations require that the following information appear in the notice:
(i) The name and location of the Federal project and proposed disposal site(s);
. (ii) The citation of the law(s) under which the Federal project is to be reviewed (See paragraph (b), of this section);
(iii) A brief description of the Federal project and a description of the estimated type, composition and quantity of materials to be discharged, the proposed time schedule for the dredging activity, and the types of equipment and methods of dredging and conveyance proposed to be used;
(iv) A sketch showing the location of the Federal project including depth, of water in the area and all proposed disposal site(s);
(v) A brief description of the existing use of properties immediately adjacent to the disposal area;
(vi) The nature, estimated amount, and frequency of known and anticipated related dredging and disposal to be conducted by others;
(vii) A statement as to whether the proposed disposal site(s) is (are) ones which has (have) previously been.designated by the Administrator, EPA;
(viii) A list of Federal, State and local agencies with whom these activities are being coordinated;
(ix) A statement concerning a preliminary determination of the need for and/or availability of an environmental impact statement;
(x) Any other available information which may assist interested parties in evaluating the likely impact of the disposal of the dredged material;
(xi) A reasonable period of time, normally thirty days but not less than fifteen days from date of mailing, within which interested parties may express their views concerning the disposal of the dredged material.
(2) The following statement will also be included in the public notice:
Any person who has an interest which may be affected by the disposal of this dredged material may request a public hearing. The request must be submitted in writing to the District Engineer within -days of the date of this notice and *769 must clearly set forth the interest which may be affected and the manner in which the interest may be affected by this activity.
(3) If the federal project involves the discharge of dredged material into navigable waters, the public notice shall also contain the following:
Designation of the proposed disposal site for dredged material associated with this Federal project shall be made through the application of guidelines promulgated by the Administrator EPA in conjunction with the Secretary of the Army. If these guidelines alone prohibit the designation of this proposed disposal site, any potential impairment to the maintenance of navigation, including any economic impact on navigation and anchorage which would result from the failure to use this disposal site, will also be considered.
A review of Public Notice No. 77-901 (Attachment A to Affidavit of Nathaniel D. McClure IV) leads us to conclude that the regulations have been followed. All required information is provided in the notice. Although the notice provided that a public hearing could be held upon request, no such request was made. Comments from EDF were responded to by the Corps. In short, we see no § 404 violation in the form of the notice.
Plaintiffs next attack the Corps’ Statement of Findings (SOF) relating to the discharge of dredged material as violative of § 404 and the regulations adopted thereunder. Failure to follow these standards, plaintiffs argue, renders the agency’s decision arbitrary, capricious, and not in accordance with the law. The question before us is “whether the decision was based on a consideration of the relevant factors and whether there has been a clear error of judgment.”
Citizens to Preserve Overton Park v. Volpe,
The regulations recognize the importance of wetlands,
The regulations also provide that disposal of dredged material in wetlands will not be performed
unless the District Engineer concludes ... that the benefits of the proposed disposal outweigh the damage to the wetlands resource and the proposed disposal is necessary to realize those benefits. In evaluating whether a particular alternation is necessary, the District Engineer shall primarily consider whether the wetland resources and environment must be utilized in performing the dredged disposal, and whether feasible alternative disposal sites are available.
The disposal areas for dredged material have been located to limit the pumping distances for a hydraulic dredge to less than one-half mile wherever possible. The disposal areas have been located away from developed or settled areas and *770 on the low bank or cut bank where practical. They will be aesthetically oriented in a manner that will preclude blocking natural drainage, while at the same time utilizing natural drains for the management of return water.
These references lead us to believe that alternative disposal sites were considered and that the District Engineer concluded that utilization of wetlands as disposal sites was necessary. In addition, the SOFs state “[disposal will not have an unacceptable adverse impact on the aquatic resource.”
See
Plaintiffs next argue that the SOF findings do not have a basis in fact in the administrative record. Our standard of review is, of course, limited by § 706 of the Administrative Procedure Act-we may set aside the Corps’ findings only if its action is found to be “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.”
“In order to upset the final agency decision, there must be a clear showing that such decision was improper. The burden of proving that the action was improper is on the party challenging the decision. It is well settled that there is a definite presumption of regularity in favor of the administrative decision.”
Gables by the Sea, Inc. v. Lee,
As discussed
supra,
the burden of proving that agency action is arbitrary and capricious rests on plaintiff. Only the administrative record may be looked at to determine whether the agency’s action had a basis in fact.
Id.
As stated in
[W]hile the Overton Park mandate does require that we base our review on the entire record before the agency, we do not interpret it to require that we plunge into the record unaided by the parties. The record’s length is on the order of 10,000 pages, and it is both technical and poorly organized. Lest we make of this case a career, we must generally restrict our consideration to the parties’ specific citations.
State of Texas
v.
EPA,
*771 Furthermore, the failure of plaintiffs to produce any portion of the record, although extensive discovery has been undertaken in this lengthy and complex litigation and plaintiffs are well aware of the standard of review of agency action, leads us to conclude that plaintiffs are estopped from claiming insufficient factual findings.
We summarily reject plaintiffs’ argument that
(b)
Section 401 (
Plaintiffs contend that § 401 (
On September 1, 1978, the State of Alabama decided to waive the requirements of § 401.
See
D. Ex. 29 and Affidavit of Nathaniel D. McClure IV. Plaintiffs contend that § 401 does not allow affirmative waivers. We disagree. The section provides that a state shall be deemed to have waived its rights under § 401 if it “fails or refuses to act on a request for certification, within a reasonable period of time (which shall not exceed one year).” We do not interpret this to mean that affirmative waivers are not allowed. Such a construction would be illogical and inconsistent with the purpose of this legislation. “The purpose of the certification mechanism ... is to assure that Federal licensing or permitting agencies cannot override State water quality requirements.” S.Rep. No. 414, 92nd Cong., 2d Sess.,
reprinted in
[1972] U.S.Code Cong. & Admin. News 3668, 3735. A state need not avail itself of this protection. If it fails to certify within a reasonable time, waiver is automatic. Thus, had the state simply ignored the certification request, plaintiffs could not complain if the permit was granted after a “reasonable” time. We therefore believe that a state may make an affirmative decision to waive § 401 certification. In any event, “the proper forum for judicial review of state certification is in state court.”
Mobil Oil Co. v. Kelley,
Having determined that there is no genuine issue of material fact and that defendants are entitled to prevail as a matter of law, we dismiss with prejudice Count XII of the complaint.
*772 VI. AGENCY’S FAILURE TO PUBLISH REGULATIONS
By Count XIV, plaintiffs allege that defendants have violated § 3 of the Administrative Procedure Act,
Count XIV of the amended complaint fails to designate or describe any particular unpublished regulation which was required to be published. Plaintiffs, however, learned in 1977 and 1978 during discovery of at least three Corps of Engineers regulations which, to plaintiffs’ knowledge, have never been published in the Federal Register. These include Reg. No. 1165-2-6-Water Resource Policies and Authorities: Evaluation of Redevelopment Effects; Reg. No. 1120-2-114-Survey Investigations and Reports: Water Improvement Studies-Navigation Benefits; and Reg. No. 11-2-24-Civil Works Activities Construction and Design. Federal defendants do not take issue that these regulations are unpublished but claim that they are internal agency guidelines used by Corps personnel in the preparation of reports as well as in reviewing ongoing projects and that as such their publication was required neither by the Administrative Procedure Act nor by the Department of the Army regulations.
Assuming without deciding that the three regulations as well as possibly others constitute information required to be published by
We therefore grant summary judgment to defendants on Count XIV insofar as it denies injunctive relief to halt the construction of TTW, but without prejudice to plaintiffs’ right to seek an order requiring the defendants to publish all heretofore unpublished regulations and other documents required by
We find it unnecessary to discuss Count XV which sets forth no facts or claims of violations of law not contained in other counts.
Let an order issue accordingly.
Notes
. H.R.Doc.No. 269, í¡ 20 at 16.
. H.R.Doc.No. 486, 1i 136 at 51.
. Id., •: 19.
. Id., V 21 at 7.
. Id., U 16.
. Id, fi 19 at 6.
. GDM Supp. Table 4 at 8 and Table A-3 at A-3 & A-4 (1966).
. Id., Table 4 at 8 and Table B-13 at B-34.
. Economic Reanalysis Summary at 7-10 (1976).
. Act of July 5, 1884, Chapter 229, as set forth in H.R.Doc.No. 1491, 62nd Cong., 3d Sess. 395, 405.
. Act of Aug. 30, 1935, Chapter 831 (Pub. L.No. 74-409), as set forth in H.R.Doc.No. 379, 76th Cong., 1st Sess. 2330, 2336.
. Pub.L.No. 83-780, as set forth in H.R.Doc. 182, 90th Cong., 1st Sess. 3351, 3355.
. 1965 Flood Control Act § 201, as modified by § 112 of Water Resources Dev. Act of 1976 (D. Ex. 35).
. D. Ex. 35 & 36.
. In fact, TTW’s effect on Mobile Bay and the charge that the EIS inadequately discussed the impacts upon the Mobile area were a major feature of the prior case.
. Economic Reanalysis Summary at 40 (1976).
. g. Revising or Supplementing Statements Whenever necessary, an appropriate revision or supplement to a final environmental statement on file with CEQ shall be prepared by the District Engineer. The extent of the revision and further coordination with other agencies, groups and individuals on the project mailing list will be based on paragraph (n) of this section and the following:
(1) If the final environmental statement previously filed clearly failed to comply with the requirements of NEPA: e. g. failed to discuss alternatives or failed to disclose the environmental impacts of the proposed action, or if there has been a major change in the plan of development or method of operation of the proposed action, a revised environmental statement (draft and final) must be prepared and filed with CEQ. The 90 and 30 day waiting period of CEQ guidelines § 1500.11(b) (38 FR 20556) will apply. Revised draft and final environmental statements will be circulated in accordance with paragraph (1)(4) of this section.
(2) Whenever the final environmental statement on file becomes deficient because certain environmental effects of the project were not discussed or design features or project purposes were modified significantly subsequent to the filing of the original environmental statement, an appropriate supplement to the final statement shall be prepared. The supplement will be prepared in draft and final format with a 45 day review and comment period allowed after publication by CEQ in the Federal Register for the draft.... The draft supplement will be circulated to agencies, groups and individuals on the project mailing list. Both the draft and final supplement will be filed with CEQ and noted in a separate category in CEQ’s weekly listing in the Federal Register.
(3) Whenever it is necessary only to clarify or amplify a point of concern raised after the final environmental statement was filed with CEQ (and such point of concern was considered in making the initial decision) or if comments on the final environmental statement are received from Federal, State or local governmental agencies or the public, the clarification, amplification or response to the comments received shall be prepared and filed with CEQ.
. The prefaces of the First and Second Supplemental Environmental Reports (D. Ex. 5 & 6), state as follows:
The primary purpose of the second phase of the Continuing Environmental Studies is to assure that every opportunity to enhance the environment and to minimize any adverse effects is given full consideration. The ongoing studies of this phase are in greater detail than those conducted in Phase 1 and greatly expand the data base. Analysis of the data is continuing to insure that the environmental aspects are thoroughly integrated into the further planning, design, and construction of the waterway. The results of these continuing studies have not revealed any significant deviations from the EIS as filed and reveal adherence to the points of concern considered in making the initial decision.
. Corps of Engineers Justification Data, Congressional Submission, Fiscal Year 1976, etc. at 49.
. H.R.Rep.No. 1309, 78th Cong., 2d Sess., reprinted in [1944] U.S.Code Cong. & Admin. News 1349, 1353.
. The 1973 “Principles and Standards for Planning Water and Land Related Resources” were promulgated two years after construction was commenced on TTW, and, by their terms, apply only to projects in planning stages, and not to those specifically authorized by Congress.
See
. On the subsumation of
a. We note that, since the date of this decision but prior to publication, the Fifth Circuit has reiterated that a decision by Congress to approve funding of a project despite known economic and environmental problems “effectively supplants the Corps’ decision to build the project, and precludes [court] review of that substantive decision.” South Louisiana Environmental Council, Inc. v. Sand,
. Public Works for Water and Power Development and Atomic Energy Commission Appropriation Bill, 1975: Hearings before the Subcommittee on Public Works of the Committee on Appropriations, House of Representatives, 93rd Cong., 2d Sess., Part 1 at pages 509, 512, 640; Part 7 at pages 248, 252, 253, 258, 265.
Public Works for Water and Power Development and Energy Research Appropriation Bill, 1976: Hearings before the Subcommittee on Public Works of the Committee on Appropriations, House of Representatives, 94th Cong., 1st Sess., Part 1 at pages 480, 486.
Public Works for Water and Power Development and Energy Research Appropriation Bill, 1977: Hearings before the Subcommittee on Public Works of the Committee on Appropriations, House of Representatives, 94th Cong., 2d *759 Sess., Part 1 at pages 622, 628, 643, 644; Part 8 at pages 970-973, 976, 978.
Public Works for Water and Power Development and Energy Research Appropriation Bill, 1978: Hearings before the Subcommittee on Public Works of the Committee on Appropriations, House of Representatives, 95th Cong., 1st Sess., Part 1 at pages 723, 730; Part 8 at pages 1532, 1533, 1538; Part 9 at pages 37, 104, 110.
Public Works for Water and Power Development and Energy Research Appropriation Bill, 1979: Hearings before the Subcommittee on Public Works of the Committee on Appropriations, House of Representatives, 95th Cong., 2d Sess., Part 2 at pages 1579, 1587; Part 8 at pages 29, 34, 42, 55, 73, 82, 90.
Energy and Water Development Appropriations for 1980: Hearings before the Subcommittee on Energy and Water Development of the Committee on Appropriations, House of Representatives, 96th Cong., 1st Sess., Part 2 at pages 801, 810; Part 9 at page 2141.
Energy and Water Development Appropriations for 1981: Hearings before the Subcommittee on Energy and Water Development of the Committee on Appropriations, House of Representatives, 96th Cong., 2d Sess., Part 3 at pages 2949, 2958, 3113, 3114, 3330; Part 9 at pages 42, 820, 822, 823, 825, 827, 830, 840.
Public Works for Water and Power Development and Atomic Energy and Atomic Energy Commission Appropriations for Fiscal Year 1975: Hearings before the Subcommittee of the Committee on Appropriations, United States Senate, 93rd Cong., 2d Sess., on H.R. 15155, Part 1 at page 307; Part 6 at pages 4694, 4707.
Public Works for Water and Power Development and Energy Research Appropriations for Fiscal Year 1976: Hearings before a Subcommittee of the Committee on Appropriations, United States Senate, 94th Cong., 1st Sess., on H.R. 8122, Part 1 at pages 317, 323; Part 6 at page 5540; Part 7 at pages 6915, 6917.
Public Works for Water and Power Development and Energy Research Appropriations for Fiscal Year 1977: Hearings before a Subcommittee of the Committee on Appropriations, United States Senate, 94th Cong., 2d Sess., Part 1 at pages 45, 51, 172; Part 7 at pages 6576, 6381, 6383, 6387.
Public Works for Water and Power Development and Energy Research Appropriations for Fiscal Year 1978: Hearings before a Subcommittee of the Committee on Appropriations, United States Senate, 95th Cong., 1st Sess., on H.R. 7553, Part 2 at pages 1310, 1317; Part 7 at pages 2296, 2299, 2300.
Public Works for Water and Power Development and Energy Research Appropriations for Fiscal Year 1979: Hearings before a Subcommittee of the Committee on Appropriations, United States Senate, 95th Cong., 2d Sess., on H.R. 12928, Part 2 at pages 1697, 1705; Part 6 at pages 234, 235, 249, 251, 252.
Energy and Water Development Appropriations for Fiscal Years 1980: Hearings before a Subcommittee of the Committee on Appropriations, 96th Cong., 1st Sess., Part 2 at pages 2076, 2085, 2241; Part 8 at pages 1390, 1391, 1394, 1397, 1414, 1415.
122 Cong.Rec. 5889, 5890 (1976)
124 Cong.Rec. S17028-S17030 (daily ed. Oct. 4, 1978)
125 Cong.Rec. S3471-S3477 (daily ed. Mar. 27, 1979)
126 Cong.Rec. H318-H322 (daily ed. Jan. 29, 1980)
. Such an example is the Montgomery to Gadsden, Coosa River Channel, Alabama project, which was authorized in the 1945 Rivers and Harbors Act, Pub.L. 79-14, as amended by Pub.L. 83-436. Testimony presented on June 28, 1978, showed this project to have BCRs of 0.50 using a 3'/4% interest rate and 0.30 using a 65/s% interest rate. See Subcommittee on Public Works, Committee on Appropriations, United States Senate, F Y 79 hearing transcript, Part 9, pages 364, 365. Notwithstanding the negative BCRs, Congress appropriated $1,400,000 for the project. Pub.L. 95-482; 60 Stat. 634.
. (b) In the case of any project authorized before January 3, 1969, if the appropriate non-Federal interests have, prior to December 31, 1969, given satisfactory assurances to pay the required non-Federal share of project costs, the discount rate to be used in the computation of benefits and costs for such project shall be the rate in effect immediately prior to December 24, 1968, and that rate shall continue to be used for such project until construction has been completed, unless otherwise provided by a statute enacted after March 7, 1974.
. The issue may well be moot. An affidavit of recent date submitted by the Governor of Alabama states that all relocations and other local work required of his state have either been completed or are under construction, with more than adequate funding to meet all requirements of his state. Mississippi officials submit similar affidavits stating that all Mississippi responsibilities have been met by work either under construction or contracted for. The single exception is reconstructing a U.S. Highway 78 bridge, for which necessary funds are said to be available.
By § 205(a) of Act, July 26, 1947, chap. 343, Title II, 61 Stat. 501, the Department of War was designated the Department of the Army and the title of the Secretary of War was changed to Secretary of the Army.
. (a) After December 31, 1970, the construction of any water resources project by the Secretary of the Army, acting through the Chief of Engineers, or by a non-Federal interest where such interest will be reimbursed for such construction under the provisions of section 1962d-5a of this title or under any other provision of law, shall not be commenced until each non-Federal interest has entered into a written agreement with the Secretary of the Army to furnish its required cooperation for the project.
(f) This section shall not apply to any project the construction of which was commenced before January 1, 1972 ....
. Fiscal year 1972, of course, commenced July 1, 1971. The second TTW appropriation, for fiscal 1972, was contained in Pub.L.No.92-134, 85 Stat. 365.
See
. Although the Fifth Circuit addressed the claim on its merits, we do not interpret that was necessarily meant to constitute a finding that the FWCA provides a private cause of action. The appellate court did not address this issue, but rather concluded that the “short answer” to plaintiffs’ contentions was on the merits.
. The Fifth Circuit has not decided the question. See note 29 supra.
. The discharge of dredged or fill material as part of the construction of a federal project specifically authorized by Congress whether prior to or on or after December 27, 1977, is not prohibited by or otherwise subject to regulation under this section, or a State program approved under this section, or section 1311(a) or 1342 of this title (except for effluent standards or prohibitions under section 1317 of this title), if information on the effects of such discharge, including consideration of the guidelines developed under subsection (b)(1) of this section, is included in an environmental impact statement for such project pursuant to the National Environmental Protection Act of 1969 and such environmental impact statement has been submitted to Congress before the actual discharge of dredged or fill material in connection with the construction of such project and prior to either authorization of such project or an appropriation of funds for such construction.
. (a)(1) Any applicant for a Federal license or permit to conduct any activity including, but not limited to, the construction or operation of facilities, which may result in any discharge into the navigable waters, shall provide the licensing or permitting agency a certification from the State in which the discharge originates or will originate, or, if appropriate, from the interstate water pollution control agency having jurisdiction over the navigable waters at the point where the discharge originates or will originate, that any such discharge will comply with the applicable provisions of sections 1311, 1312, 1313, 1316, and 1317 of this title. In the case of any such activity for which there is not an applicable effluent limitation or other limitation under sections 1311(b) and 1312 of this title, and there is not an applicable standard under sections 1316 and 1317 of this title, the State shall so certify, except that any such certification shall not be deemed to satisfy section 1371(c) of this title. Such State or interstate agency shall establish procedures for public notice in the case of all applications for certification by it and, to the extent it deems appropriate, procedures for public hearings in connection with specific applications. In any case where a State or interstate agency has no authority to give such a certification, such certification shall be from the Administrator. If the State, interstate agency, or Administrator, as the case may be, fails or refuses to act on a request for certification, within a reasonable period of time (which shall not exceed one year) after receipt of such request, the certification requirements of this subsection shall be waived with respect to such Federal application. No license or permit shall be granted until the certification required by this section has been obtained or has been waived as provided in the preceding sentence. No license or permit shall be granted if certification has been denied by the State, interstate agency, or the Administrator, as the case may be.
. (a) Each agency shall make available to the public information as follows:
(1) Each agency shall separately state and currently publish in the Federal Register for the guidance of the public—
(B) statements of the general course and method by which its functions are channeled and determined, including the nature and requirements of all formal and informal procedures available;
(D) substantive rules of general applicability adopted as authorized by law, and statements of general policy or interpretations of general applicability formulated and adopted by the agency; and
(E) each amendment, revision, or repeal of the foregoing.
Except to the extent that a person has actual and timely notice of the terms thereof, a person may not in any manner be required to resort to, or be adversely affected by, a matter required to be published in the Federal Register and not so published. For the purpose of this paragraph, matter reasonably available to the class of persons affected thereby is deemed published in the Federal Register when incorporated by reference therein with the approval of the Director of the Federal Register.
. In deciding which information to publish, consideration shall be given to the fundamental objective of informing all interested persons of ■ how to deal effectively with the Department of the Army.