El Paso County v. Sunlight Enterprises Co., Inc.El Paso County v. Sunlight Enterprises Co., Inc.
OPINION
Since 1891, Texas law has provided that a contract stipulation requiring a claimant to give notice of a claim for damages as a condition precedent to the right to sue on the contract is not valid unless it is reasonable, and that a stipulation requiring notification within less than 90 days is void. Tex. Civ, PRAC, & Rem. Code Ann. § 16.071(a) (West 2015). The construction contract between Sunlight Enterprises Co., Inc. and El Paso County provides that any contractor claims for additional compensation and extension of time are waived unless submitted to the County within seven calendar days. The controlling issue in this permissive appeal is whether Section 16.071(a) of the Texas Civil Practice and Remedies Code applies and renders the seven-day notice provisions void. We conclude Section 16.071(a) does not apply and does not render the seven-day notice provisions void. Accordingly, we reverse and remand this case to the trial court for further proceedings in light of this opinion.
BACKGROUND
The County and Sunlight executed a fixed-price construction contract for the renovation of the El Paso County Sports Park. After the County imposed liquidated damages on Sunlight for lack of performance and then terminated the contract, Sunlight sued the County for breach of contract, alleging in part that it had incurred additional costs due to delay and hindrance by the County.
1
The County al
Subparagraph 13(A) of the construction contract requires that all contractor claims be submitted within seven calendar days:
(A) All Contractor claims against the Owner shall be initiated by a written claim submitted to the Owner and the Architect. Such claim shall be received by the Owner and the Architect no later than seven (7) calendar days after the event, or the first appearance of the circumstances, causing the claim, and same shall set forth in detail all known facts and circumstances supporting the claim[.]
Subparagraph 13(D) provides that in making a claim for an increase in the contract price, the contractor must strictly comply with the seven-day notice provision in 13(A) as a condition precedent to any liability of the owner and that failure to comply constitutes a waiver by the contractor of any claim for additional damages:
(D) In the event the Contractor seeks to make a claim for an increase in the Contract Price, as a condition precedent to any liability of the Owner- therefore, the Contractor shall strictly comply with the requirements of Subparagraph 13(A) above and such claim shall be made by the Contractor before proceeding to execute any additional or changed work. Failure of the condition precedent to occur shall constitute a waiver by the Contractor of any claim for additional compensation[.]
Subparagraph 13(F) similarly provides that in making any claim for an extension of time, the contractor must strictly comply with the seven-day notice provision in 13(A) and that failure to do so results in waiver of any claim for an extension of time:
(F) In the event the Contractor should be delayed in performing any task which at the time of the delay is then critical, or which during the delay becomes critical, as the sole result of any act or omission by the Owner or someone acting in the Owner’s behalf, or by Owner-authorized Change Orders, ... the date for achieving Substantial Completion, or, as applicable, final completion, shall be appropriately adjusted by the Owner upon the written claim of the Contractor to the Owner and the Architect. ... Any claim for an extension of time by the Contractor shall strictly comply with the requirements of Subparagraph 13(A) above. If the Contractor fails to make such claim as required in this Subpara-graph 13(F), any claim for an extension of time shall be waived.
Both parties filed motions for partial summary judgment. Sunlight argued that the seven-day notice deadlines imposed by Subparagraphs 13(A), (D), and (F) were rendered void by Section 16.071(a) of the Texas Civil Practice and Remedies Code, which provides:
(a) A contract stipulation that requires a claimant to give notice of a claim for damages as a condition precedent to the right to sue on the contract is not valid unless the stipulation is reasonable. A stipulation that requires notification within less than 90 days is void.
Tex, Civ. PRAO. & Rem. Code Ann. § 16.071(a). The County argued that Sec
The trial court concluded that Section 16.071(a) was applicable and that the seven-day notice provisions of Subparagraphs 13(A), (D), and (F) were void, preventing the County from relying on those provisions to bar Sunlight’s claims for additional compensation and additional time. Accordingly, the trial court granted Sunlight’s motion for partial summary judgment and denied the County’s motion for partial summary judgment. Both the trial court and this Court granted the County permission to pursue a permissive interlocutory appeal. See Tex. Civ. PRAC. & Rem. Code ANN.' § 51.014(d)(1) (West Supp. 2016) (permissive appeal allowed from order involving controlling question of law on which there is a substantial ground for difference of opinion); see also Tex, R. Civ, P. 168; Tex. R. App, P. 28.3.
DISCUSSION
The controlling question of law in this permissive appeal is whether Section 16.071(a) renders Subparagraphs 13(A), (D), and (F) void and unenforceable by the County. In Issue One, the County contends that Section 16.071(a) does not apply because Subparagraphs 13(A), (D), and (F) did not require Sunlight to give “notice of a claim for damages” as a condition precedent to the right to sue on the contract. We agree.
Standard of Review
A statute’s meaning is a question of law we review de novo.
LTTS Charter Sch., Inc. v. C2 Constr., Inc.,
Analysis
We start with the language the Legislature chose in Section 16.071(a). By its terms, the 90-day minimum notice requirement contained in Section 16.071(a) applies to a contract stipulation that requires a claimant to give a “notice of a claim for damages” as a condition precedent to the right to sue on the contract.
The statutory language used in
Despite the lack of cases addressing the application of
This narrow construction is consistent with the surrounding statutory language that the “notiee of-a claim for damages” must be “a condition precedent to
the right to sue on the contradi.]”
It is also consistent with the surrounding statutory landscape, since
The Supreme Court first alluded to this narrow construction in
Taber
in 1911, when it discussed the applicability of article 3379 (an earlier predecessor to
[W]e are of the opinion the 90-day period should be computed from the time the causé of action arose, and that such period was intended by the Legislature to be designated. The purpose of the act was to fix a minimum period of 90 days from the time -the cause of action arose, in which notice of any claim for damages might be required by stipulation, as a condition precedent' to the right to sue[.]
The Court reaffirmed its holding in
Martin
two years later when it specifically disavowed a court of appeals’ holding that a 14-day notice provision for unauthorized transactions in a deposit account was a “notice of a claim for damages” and void under
Indeed, the Supreme Court’s decision in
Martin
is consistent with its prior decisions under the nearly-identical predecessor statutes. For example, in
St. Paul Mercury Ins. Co. v. Tri-State Cattle Feeders, Inc.,
the Court explicitly disagreed with the court of appeals’ holding that a 24-hour notice of loss provision in a theft insurance policy, which required the insured to report within 24 hours “every loss which may become a claim under this policy,” was void because it was a “notice of claim for damages” under the statute.
We discern from these cases that contractual notice provisions do not fall within
Under the terms of the construction contact, the submission of a notice of a claim for additional compensation or time under Subparagraphs 13(A), (D), and (F) is only a precursor to a possible cause of action for damages, which “may or may not result.” Subparagraphs 13(A), (D), and (F) do not mention a “claim for damages,” and the construction contract does not contain such a notice provision.
2
Rather, the contract specifically provides that both the
This case involves only the initial step on the way to a possible cause of action for breach of contract,
ie.,
the notice of an event possibly supporting , additional compensation or time that could possibly lead to a claim for damages. Thus, the notice provisions in the construction contract, like the notice provisions in
Martin, Community Bank, St. Paul,
and
Harper,
do not constitute a “notice of a claim for damages” under
We also discern from these cases that there is good reason for the Supreme Court to so limit the scope of
Likewise, the seven-day notice provisions in the construction contract simply require “notice of the happening of an event” ultimately upon which a breach of contract claim “may or may not result.” If met, the provisions would have allowed the parties to investigate, evaluate, and possibly approve and settle the claims regarding adjustments in contract time or price without breaching the contract, thereby avoiding any ultimate claim for damages. In other words, if the notice provisions had been followed, adjustments to contract time or price could have been made during the course of the project without either party having to establish a breach of contract to recover damages. As such, the contractual notice provisions do not constitute a “notice of a claim for damages” under
The County notes that contractual provisions requiring notice for adjustments in time and price are standard in the form construction contracts promulgated by various entities such as the American Institute of Architects. Sunlight points out, however, that generally these form construction contracts provide for alternate dispute resolution, while the present con
What we do consider significant is that by entering into the construction contract, Sunlight agreed to the seven-day notice requirement, and had actual knowledge that failure to provide timely notice would result in waiver of a claim.
In re Border Steel, Inc.,
Texas strongly favors parties’ freedom of contract, which allows parties to bargain for mutually agreeable terms and allocate risks as they see fit.
Gym-N-I Playgrounds, Inc. v. Snider,
■ In sum, we conclude that, although the notice provisions in the construction contract address events that could lead to a claim for damages, they fail to constitute notice requirements encompassed by
Because
Notes
. The Local Government Code waives immunity and allows suits against a county for
. We note that notice of a claim for damages is required by statute. A party may not sue a county for any claim before the 60th day after the date the party presents its claim to the commissioners court and the court neglects or refuses to pay the claim. Tex Local Gov’t Code Ann. § 89.004(a) (West 2008).
. In light of our holding, we do not reach the County’s second issue, in which it contends in the alternative that if