History
  • No items yet
midpage
504 S.W.3d 922
Tex. App.
2016
Read the full case

Background

  • El Paso County contracted with Sunlight Enterprises on a fixed-price renovation; County later assessed liquidated damages and terminated the contract; Sunlight sued for breach including claims for additional compensation and time.
  • Contract Paragraph 13 required written submission of contractor claims to Owner and Architect "no later than seven (7) calendar days" after the event; Subparagraphs 13(D) and 13(F) made strict compliance a condition precedent and provided that failure to comply waived the claim.
  • Sunlight moved for partial summary judgment arguing Tex. Civ. Prac. & Rem. Code § 16.071(a) (statutory rule invalidating contract notice requirements shorter than 90 days for "notice of a claim for damages") voided the seven-day provisions.
  • County moved for partial summary judgment arguing § 16.071(a) does not apply because the contract requires notice of events or claims for time/price adjustments, not "notice of a claim for damages."
  • Trial court held § 16.071(a) applied and voided the seven-day notice provisions; the court of appeals granted permissive appeal and reversed, holding § 16.071(a) is inapplicable and the seven-day provisions are enforceable.

Issues

Issue Plaintiff's Argument Defendant's Argument Held
Whether Tex. Civ. Prac. & Rem. Code § 16.071(a) applies to invalidate the contract's 7‑day notice provisions § 16.071(a) voids notice provisions shorter than 90 days because the seven‑day submission operates to bar Sunlight's right to sue for damages § 16.071(a) applies only to stipulations requiring "notice of a claim for damages" (i.e., notice of a cause of action); these provisions notify of events/requests for adjustment, not a damages claim Held: § 16.071(a) does not apply; the seven‑day notice provisions are not "notice of a claim for damages" and are therefore not void

Key Cases Cited

  • Greene v. Farmers Ins. Exch., 446 S.W.3d 761 (Tex. 2014) (historical background on notice statute)
  • Taber v. Western Union Tel. Co., 137 S.W. 106 (Tex. 1911) (statute construed to compute 90‑day period from accrual of cause of action)
  • American Airlines Employees Federal Credit Union v. Martin, 29 S.W.3d 86 (Tex. 2000) (statute does not apply when notice required is of an event, not a claim for damages)
  • St. Paul Mercury Ins. Co. v. Tri‑State Cattle Feeders, Inc., 638 S.W.2d 868 (Tex. 1982) (theft‑policy notice of loss is notice of an event antecedent to a claim and not covered by the statute)
  • Komatsu v. U.S. Fire Ins. Co., 806 S.W.2d 603 (Tex. App.—Fort Worth 1991, writ denied) (interpreting "claim for damages" to mean "cause of action")
Read the full case

Case Details

Case Name: El Paso County v. Sunlight Enterprises Co., Inc.
Court Name: Court of Appeals of Texas
Date Published: Dec 9, 2016
Citations: 504 S.W.3d 922; 2016 WL 7177005; 2016 Tex. App. LEXIS 13113; 08-16-00081-CV
Docket Number: 08-16-00081-CV
Court Abbreviation: Tex. App.
Log In
    El Paso County v. Sunlight Enterprises Co., Inc., 504 S.W.3d 922