E. E. ELMER, d/b/а Mississippi Testing Laboratories, Appellant, v. UNITED STATES FIDELITY & GUARANTY COMPANY, Appellee.
No. 18086.
United States Court of Appeals Fifth Circuit.
Feb. 29, 1960.
275 F.2d 89
J. A. Covington, Jr., E. L. Snow, Roger B. Shows, Meridian, Miss., for appellee, Snow, Covington & Shows, Meridian, Miss., of counsel.
Before RIVES, Chief Judge, and HUTCHESON and JONES, Circuit Judges.
JONES, Circuit Judge.
We have reviewed a judgment for the defendant in a suit on a contractor‘s bond given pursuant to the requirements of the Miller Act.1 Tyler-Hyde Construction Company contractеd with the United States for grading, asphalt paving, and concrete paving, at the Key Field Airport in Meridian, Mississippi. The appellee, United States Fidelity & Guаranty Company, was surety on the Miller Act bond. Tyler-Hyde sublet the grading and asphalt paving to T. F. Scholes Company which, in turn, made a contract with Acme Asphalt Company to do the asphalt paving. Acme employed the appellant, E. E. Elmer, to perform inspection and testing services. Tyler-Hyde knew thаt the appellant was rendering services on the job. The appellant‘s charge for his services was $1,966.61. Acme did not pay the appellant. Acme has become a bankrupt. The appellant asserted a claim against Tyler-Hyde and the appellee surety. The claim was rejeсted and suit was instituted by the appellant against the appellee. The pertinent facts were stipulated. From an adverse judgment the appеllant has brought the case before us for review.
In the MacEvoy case the claimant had furnished materials to one from whom the prime contractor had purchased them for use on the job. In the MacEvoy case it was held that the claimant could not recover. The appellant here seeks to distinguish the MacEvoy case on the basis of factual differences. The factual difference exists but does not call for a differеnt principle. The language of the MacEvoy opinion furnishes us with a rule for decision here. As is pointed out in the opinion of the district court, MacEvoy holds that a subcontractor, as that term is used in the Miller Act, is one who performs and takes from the prime contractor a specific part of the labor or matеrial requirements of the original contract. Scholes was a sub-contractor of Tyler-Hyde. Acme had a direct contractual relation with the sub-сontractor Scholes and hence would have been covered by the bond. But Acme was not a sub-contractor since it performed its work for Scholes rather than for the prime contractor, Tyler-Hyde. Since the appellant was not a sub-contractor within the meaning of the Miller Act and did not have a direct contractual relationship with a sub-contractor, he cannot recover. As said in MacEvoy, “To allow those in more remote relationships to recover on the bond would be contrary to the clear language of the proviso and to the expressed will of the framers of thе Act.” 322 U.S. 102, 108, 64 S.Ct. 890, 894.
The conclusions we have reached are in accord with United States for Use and Benefit of W. J. Halloran, etc., v. Frederick Raff Co., 1 Cir., 1959, 271 F.2d 415;
The judgment of the district court is Affirmed.
RIVES, Chief Judge (specially concurring).
As I read Clifford F. MacEvoy Co. v. United States, 1944, 322 U.S. 102, 64 S.Ct. 890, 88 L.Ed. 1163, it held simply that a materialman is not a “subcontractor” within the meaning of the provisо to
While I recognize that the dominant purpose of the Miller Act was to ameliorate certain procedural difficulties in the Heard Act аnd to permit a more prompt recovery under the payment bond, the legislative history cited in the following part of the MacEvoy opinion compels me to concur with the judgment of affirmance in this case:
“The proviso of Section 2(a), which had no counterpart in the Heard Act, makes clear that the right to bring suit on a payment bond is limited to (1) those materialmen, laborers and subcontractors who deal directly with the prime contractor and (2) thosе materialmen, laborers and sub-subcontractors who, lacking express or implied contractual relationship with the prime contractor, have direct contractual relationship with a subcontractor and who give the statutory notice of their claims to the prime contractor. To аllow those in more remote relationships to recover on the bond would be contrary to the clear language of the proviso and to the expressed will of the framers of the Act. Moreover, it would lead to the absurd result of requiring notice from persons in direct contractual relationship with a subcontractor but not from more remote claimants.
”5 ‘A sub-subcontractor may avail himself of the protection of the bond by giving written notice to the contractor, but that is as far as the bill goes. It is not felt that more remote relationships ought to come within the purview of the bond.’ H.Rep.No.1263 (74th Cong., 1st Sess.), p. 3.”
322 U.S. 102, 107-108, 64 S.Ct. 890, 894.
Somewhat reluctantly, I concur.
