delivered the opinion of the Court.
The United States entered into a contract with the petitioner Clifford F. MacEvoy Company whereby the latter agreed to furnish the materials and to perform the work necessary for the construction of dwelling units of a Defense Housing Project near Linden, New Jersey, on a cost-plus-fixed-fee basis. Pursuant to the Miller Aсt, 1 MacEvoy as principal and the petitioner Aetna Casualty and Surety Company as surety executed a payment bond in the amount of $1,000,000, conditioned on the prompt payment by MacEvoy “to all persons supplying labor and material in the prosecution of the work provided for in said contract.” Thе bond was duly accepted by the United States.
MacEvoy thereupon purchased from James H. Miller & Company certain building materials for use in the prosecution of the work provided for in MacEvoy’s contract with the Government. Miller in turn purchased these materials from the respondent, Calvin Tomkins Company. Miller failed to pay Tomkins a balance of $12,033.49. There is no аllegation that Miller agreed to perform or did perform any part of the work on the construction project.
Within ninety days from the date on which Tomkins furnished the last of the materials to Miller, Tomkins gave written notice to MacEvoy and the surety of the existence and amount of Tomkins’ claim for materials furnished to Miller. Tomkins as use-plaintiff then instituted this action against MacEvoy and the surety on the payment bond. The District Court granted petitioners’ motion to dismiss the complaint for failure to state a claim against them.
Specifically the issue is whether under the Miller Act a person supplying materials to a materialman of a Government contractor and to whom an unpaid balance is due from the materialman can recover on the payment bond executed by the contractor. We hold that he cannot.
The Heard Act,
2
which was the predecessor of the Miller Act, required Government contractors to execute penal bonds for the benefit of “all persons supplying him or them with labor and materials in the prosecution of the work provided for in such contract.” We consistently аpplied a liberal construction to that statute, noting that it was remedial in nature and that it clearly evidenced “the intention of Congress to protect those whose labor or material has contributed to the prosecution of the work.”
United States
v.
American Surety Co.,
The Miller Act, while it repealed the Heard Act, reinstated its basic provisions and was designed primarily to eliminate certain procedural limitations оn its beneficiaries.
4
There was no expressed purpose in the legis
“Provided, however, That any person having direct contractual relationship with a subcontractor but no contractual relationship express or implied with the contractor furnishing said payment bond shall have a right of action upon the said payment bond ppon giving written notice tо said contractor within ninety days from the date on which such person did or performed the last of the laboror furnished or supplied the last of the material for which such claim is made. . . .”
The Miller Act, like the Heard Act, is highly remedial in nature. It is entitled to a liberal construction and application in order properly to effectuate the Congressional intent to protect those whose labor and materials go into public projects.
Fleisher Engineering Co.
v.
United States,
The proviso of § 2 (a), which had no counterpart in the Heard Act, makes clear that the right to bring suit on a payment bond is limited to (1) those materialmen, lаborers and subcontractors who deal directly with the prime contractor and (2) those materialmen, laborers and sub-subcontractors who, lacking express or implied contractual relationship with the prime contractor, have direct contractual relationship with a subcontractor and who givе
The ultimate question in this case, therefore, is whether Miller, the materialman to whom Tomkins sold the goods and who in turn supplied them to MacEvoy, was a subcontractor within the meaning of the proviso. If he was, Tomkins’ direct contractual relationship with him enables Tomkins to recover on MacEvoy’s payment bond. If Miller was not a subcontractor, Tomkins stands in too remote a relationship to secure the benefits of the bond.
The Miller Act itself makes no attempt to define the word “subcontractor.” We are thus forced to utilize ordinary judicial tools of definition. Whether the word includes laborers and materialmen is not subject to easy solution, for the word has no single exact meaning.
6
In a broad, generic sense a subcontractor includes anyone who has a contract to furnish labor or material to the prime contractor. In that sense Miller was a subcontractor. But under the more technical meaning, as established by usage
It is apparent from the hearings before the subcommittee of the Hоuse Committee on the Judiciary leading to the adoption of the Miller Act that the participants had in mind a clear distinction between subcontractors and materialmen. In opening the hearings, Representative Miller, the sponsor of the bill that became the Miller Act, stated in connection with the various proposed bills that “we would like to have the reaction and opinion of members in reference to those bills that deal with the general subject of requiring a bond for the benefit of laborers and materialmen who deal with subcontractors on public works.”
7
And the authoritative committee report
8
made numerous references to and distinguished among “laborers, materialmen and subcontractors.” Similar uncontra-dicted statements were made in both houses of Congress when the Act was pending before them.
9
The fact that
Practical considerations underlying the Act likewise support this conclusion. Congress cannot be presumed, in the absence of express statutory language, to have intended to impose liability on the payment bond in situations where it is difficult or impossible for the prime contractor to protect himself. The relatively few subcontractors who perform part of the original contract represent in a sense the prime contractor and are well known to him. It is easy for the prime contractor to secure himself against loss by requiring the subcontractors to give security by bond, or otherwise, for the payment of those who contract directly with the subcontractors.
United States
v.
American Surety Co., supra,
204;
Mankin
v.
United States, supra,
540. But this method of protection is generally inadequate to cope with remote and undeter-minable liabilities incurred by an ordinary materialman, who may be a manufacturer, a wholesaler or a retailer.
11
Many such materialmen are usually involved in large
The judgment of the court below is
Reversed.
Notes
Act of August 24, 1935, c. 642, 49 Stat. 793; 40 U. S. C. § 270a ef seq.
Act of August 13,1894, c. 280, 28 Stat. 278, as amended by Act of February 24, 1905, c. 778, 33 Stat. 811; 40 U. S. C. § 270.
In
United States
v.
American Surety Co.,
Under the Heard Act, a single bond was required to protect both the Government and the suppliers of labоr and materials. The Government was given the sole right to sue on the bond for six monthR after completion of the work and final settlement. Other claimants could sue only thereafter and had to join in a single action. Serious
“A sub-subcontractor may avail himself of the protection of the bond by giving written notice to the contractor, but that is as far as the bill goes. It is not felt that more remote relationships ought to come within the purview of the bond.” H. Rep. No. 1263 (74th Cong., 1st Sess.), p. 3.
In analogous situаtions, state and lower federal courts have expressed divergent opinions as to whether the word “subcontractor” includes laborers and materialmen. See annotation in 141 A. L. R. 321 for a summary of the conflicting cases. We have not heretofore had occasion to define the word in this connectiоn. Any loose, interchangeable use of “subcontractor” and “materialman” in any prior decision of ours is without significance.
Hearings on H. R. 2068, et al., Bonds of Contractors on Public Works, House Committee on the Judiciary, 74th Cong., 1st Sess., p. 1. See also statements by Rep. Miller, id., pp. 18, 26, 60, 67, 74; Rep. Robsion, p. 30; Rep. McLaughlin, p. 73; Rep. Dоckweiler, pp. 12-22; Rep. Celler, pp. 83, 84, 89; Edward H. Cushman, pp. 23-31, 85.
H. Rep. No. 1263 (74th Cong., 1st Sess.), pp. 1, 2.
Rep. Miller stated in the House that “This bill merely provides that in the construction of public buildings and other public works there shall be two bonds, one for the performance of the contract with the Government, and the other a payment bond for the protection of subcontractors and those furnishing the labor and material. Under the present law we have but one bond, with a dual obligation, but it is not satisfactory in that it does not afford protection to the
Sen. Burke said in the Senate that “This bill would amend that law by requiring an additional bond, a payment bond, for the protection of materialmen and laborers, subcontractors, and all who put forth thеir labor or furnish materials or incur expenditures in connection with the work.” 79 Cong. Rec. 13382.
See, in general, Campbell, “The Protection of Laborers and Materialmen Under Construction Bonds,” 3 Univ. of Chicago L. Rev. 1; Annotation, 77 A. L. R. 21.
See Note, “The Widening Scope of Protection of Statutory Construction Bonds,” 45 Harvard L. Rev. 1236.
Congress has shown its ability in other statutes to make clear an intent to include materialmen within the meaning of the word “subcontractor.” See § 301 (a) (3) of the Act of Dec. 2, 1942, 56 Stat. 1035, 42 U. S. C. Supp. II, § 1651 (a) (3), providing that the provisions of the Act shall not apply to employees of a “subcontractor who is engaged exclusively in furnishing materials or supplies.” In other statutes, Congress has clearly used the term “subcontractor” in contrast to “materialman.” See 40 U. S. C. § 407 (b); 41 U. S. C. § 10b (a) and (b); 41TJ. S. C. § 28.
