DRIFTLESS AREA LAND CONSERVANCY and WISCONSIN WILDLIFE FEDERATION v. MICHAEL HUEBSCH, et al.
No. 20-1350
United States Court of Appeals For the Seventh Circuit
SUBMITTED JULY 2, 2020 — DECIDED AUGUST 11, 2020
Before SYKES, Chief Judge, and FLAUM and ROVNER, Circuit Judges.
Appeal from the United States District Court for the Western District of Wisconsin. No. 19-cv-1007-wmc — William M. Conley, Judge.
SYKES, Chief Judge. The Wisconsin Public Service Commission issued a permit authorizing the construction of a $500 million electricity transmission line in southwestern
Briefing was completed at the end of June, and we set the case for oral argument on September 22, 2020. The permit holders moved for expedited review without oral argument; they want an earlier ruling because the case continues without them in the district court. The environmental groups responded in opposition, and the matter is ready for decision.
We grant the motion. The briefs and record adequately address the single issue raised on appeal, and oral argument would not significantly assist the court. See
I. Background
The plaintiffs are two Wisconsin environmental groups, Driftless Area Land Conservancy and Wisconsin Wildlife Federation. The defendants are the Wisconsin Public Service Commission of Wisconsin and its three commissioners (collectively, “the Commission“). The Commission regulates public utilities in the state. Two of the proposed intervenors—American Transmission Company LLC and ITC Midwest LLC—are Wisconsin electric-power utilities. The
In April 2018 the two utilities and the cooperative filed an application with the Commission for permission to construct a high-voltage transmission line running from Madison through the southwestern part of the state and ending in Dubuque County, Iowa. A project of this type is subject to heavy regulatory oversight and requires a special permit from the Commission known as a “certificate of public convenience and necessity.”
The permitting process requires a “class 1” contested case hearing.
In December 2019 Driftless Area Land Conservancy and the Wisconsin Wildlife Federation filed this lawsuit against the Commission seeking to invalidate the permit. Both groups had participated in the permit proceedings as intervenors in opposition, but their views obviously did not carry the day. The complaint raises three constitutional claims under
The Commission filed a motion to dismiss in January 2020. A week later the transmission companies moved to intervene, seeking intervention as of right under
The district judge rejected intervention as of right, concluding that the transmission companies and the Commission have the same goal—dismissal of the lawsuit—and the Commission adequately represents that shared objective. The judge also declined to authorize permissive intervention, saying that adding the transmission companies as parties would “almost certainly and needlessly complicate and delay this case.” The judge denied the motion without prejudice and invited the transmission companies to renew their request if “a concrete, substantive conflict or actual divergence of interests should emerge” later in the litigation. Alternatively, he invited a “standby” application to intervene—essentially a placeholder motion that could be activated if circumstances changed. See Solid Waste Agency of N. Cook Cty. v. U.S. Army Corps of Eng‘rs (SWANCC), 101 F.3d 503, 509 (7th Cir. 1996).
Not content to rely on governmental regulators to protect their $500 million private investment, the transmission companies appealed.
II. Discussion
A. Appellate Jurisdiction
We begin by addressing a skirmish over appellate jurisdiction.1 It will not take long. It is well established that “from the perspective of a disappointed prospective intervenor, the denial of a motion to intervene is the end of the case, so an order denying intervention is a final, appealable decision under
The possibility of a new motion if circumstances change does not block an immediate appeal. The contingency that the judge has in mind might never arise, leaving the transmission companies on the sidelines of the litigation without appellate review of their intervention claim. Nor does the incantation of the words “without prejudice” automatically defeat finality; what matters is that the judge addressed the substantive merits of the intervention motion and conclusively denied it, freezing the transmission companies out of the case. See United States v. City of Milwaukee, 144 F.3d 524, 531 n.14 (7th Cir. 1998). Finally, the judge‘s invitation to file a
The plaintiffs rely on City of Milwaukee, but that case actually supports rather than defeats appellate jurisdiction. There the district court denied an intervention motion based on a purely technical error: the intervenor failed to include a proposed pleading with his intervention motion as required by
This case is not remotely analogous. As we specifically observed in City of Milwaukee,
the circumstances would be different if a district court denied a motion to intervene on the ground that the putative intervenor‘s interests were adequately protected by the existing parties but entered the denial “without prejudice” in recognition of the fact that the circumstances of the case may change such that intervention at a later date would be appropriate.
The judge‘s order is final and appealable under
B. Intervention as of Right
With the jurisdictional hurdle cleared, we move to the intervention question. The rule governing intervention as of right provides:
(a) Intervention of Right. On timely motion, the court must permit anyone to intervene who:
...
(2) claims an interest relating to the property or transaction that is the subject of the action[] and is so situated that disposing of the action may as a practical matter impair or impede the movant‘s ability to protect its interest, unless existing parties adequately represent that interest.
The rule is straightforward: the court must permit intervention if (1) the motion is timely; (2) the moving party has an interest relating to the property or transaction at issue in the litigation; and (3) that interest may, as a practical matter, be impaired or impeded by disposition of the case. A proposed intervenor who satisfies these three elements is entitled to intervene unless existing parties adequately represent his interests.
Everyone agrees that the three basic criteria for intervention are satisfied: the intervention motion was timely; the transmission companies hold a valuable property interest in
“The most important factor in determining adequacy of representation is how the interest of the absentee compares with the interests of the present parties.” 7C CHARLES ALAN WRIGHT, ARTHUR R. MILLER & MARY KAY KANE, FEDERAL PRACTICE AND PROCEDURE § 1909 (3d ed. 2007). Our recent decision in Planned Parenthood of Wisconsin, Inc. v. Kaul describes our circuit‘s three-tiered methodology for evaluating adequacy of representation under
However, if the interest of the absentee is identical to that of an existing party, or if a governmental party is charged by law with representing the absentee‘s interest, then the standard for measuring adequacy of representation changes. In both situations—where the absentee and an existing party have identical interests, or the existing party is a governmental agency or official with a legal duty to represent the absentee‘s interest—a rebuttable presumption of adequate
In Planned Parenthood we explained the presumption in this way:
Where the prospective intervenor and the named party have the same goal, ... there is a rebuttable presumption of adequate representation that requires a showing of some conflict to warrant intervention. This presumption of adequacy becomes even stronger when the representative party is a governmental body charged by law with protecting the interests of the proposed intervenors; in such a situation the representative party is presumed to be an adequate representative unless there is a showing of gross negligence or bad faith.
942 F.3d at 799 (quotation marks and citation omitted).
In the district court, the plaintiffs advocated for the highest standard, which applies when a governmental party is legally required to represent the absentee‘s interests. This standard sets a nearly insurmountable bar: the absentee must show that the existing representation is grossly negligent or in bad faith. The judge declined to go that far; he was not convinced that the Commission is charged by law with protecting the transmission companies’ interests. Still, he applied the presumption of adequacy in its weaker form. He first concluded that the transmission companies and the Commission share the same goal: dismissal of the plaintiffs’ suit. Extrapolating from that conclusion, the judge applied
The transmission companies challenge the judge‘s use of the intermediate standard. They argue instead for the lenient default standard, which involves no thumb on the scale and requires only a minimal showing that the existing party‘s representation “may be” inadequate. Alternatively, they argue that the judge misapplied the intermediate standard. The plaintiffs, for their part, no longer advocate for the gross-negligence/bad-faith standard. They adopt a more moderate stance and simply defend the judge‘s application of the intermediate standard.
Under a correct reading of
To trigger the presumption of adequacy under the intermediate standard, it‘s not enough that a defense-side intervenor “shares the same goal” as the defendant in the brute sense that they both want the case dismissed. The judge seemed to think it was, but that mode of analysis operates at too high a level of generality. Needless to say, a prospective intervenor must intervene on one side of the “v.” or the other and will have the same general goal as the party on that side. If that‘s all it takes to defeat intervention, then intervention as of right will almost always fail. The judge‘s
That‘s not how the presumption works.
The Commission‘s interests and objectives overlap in certain respects but are importantly different. The Commission is a regulatory body, and its obligations are to the general
More broadly, the Commission regulates the transmission companies, it does not advocate for them or represent their interests. The transmission companies cannot be forced to rely entirely on their regulators to protect their investment in this enormous project, which they stand to lose if the plaintiffs are successful. For these reasons, their intervention request is not controlled by the line of cases involving intervention motions by individual members of the public, citizen groups, or other units of government that hold identical or closely aligned interests and objectives as existing governmental parties. See, e.g., Planned Parenthood, 942 F.3d at 810 (Sykes, J., concurring); WEAC, 705 F.3d at 658-59; SWANCC, 101 F.3d at 508.
Instead, this case falls within a line of cases involving permit holders that have successfully invoked
Because the transmission companies’ interests and objectives are materially different than the Commission‘s, the
As we‘ve noted, the Commission can be expected to mount a vigorous defense against the plaintiffs’ attack on the integrity of the permitting process and the impartiality of the commissioners. But the power-line project itself, and the permit necessary to construct it, belong to the transmission companies, as does the authority to use eminent domain, which is the subject of counts two and three. The Commission may be content to move slowly in this litigation; but the transmission companies want to move quickly, begin using eminent domain as soon as possible, and otherwise keep the construction project on schedule. Different defenses have been raised. In their proposed motion to dismiss submitted with the intervention motion, the transmission companies argue that even if two commissioners had conflicts, the permit was lawfully issued on the vote of the remaining commissioner or would have issued as a matter of law regardless. The Commission raised neither of these arguments in its motion to dismiss. These are not mere “quibbles with ... litigation strategy.” WEAC, 705 F.3d at 659. Rather, they reflect very real differences in the interests at stake.
Accordingly, the transmission companies cannot be kept out of this case. The basic prerequisites for intervention under
REVERSED AND REMANDED WITH INSTRUCTIONS.
