DeRose v. Bloomingdale's Inc.DeRose v. Bloomingdale's Inc.
APPEARANCES OF COUNSEL
Lester Schwab Katz & Dwyer, LLP, New York City (Harry Steinberg of counsel), for respondent.
OPINION OF THE COURT
Acosta, J.P.
This appeal underscores the importance of
Plaintiff is a carpenter who sustained injuries while working on a renovation project in defendant‘s Manhattan store. Defendant contracted with RP Brennan General Contractors (RP), a third-party defendant who employed plaintiff, to conduct renovation and demolition work. On the day of the accident, Gerry Cole, plaintiff‘s supervisor who was also employed by RP, instructed him to assist with demolition work in a different section
Plaintiff began walking toward the back of the store to fetch a Baker scaffold, which he determined was the proper device to stand upon while dismantling the wall.1 However, Cole reprimanded plaintiff and directed him to use a ladder instead. Specifically, Cole told plaintiff that he could not “roll the f . . . [expletive deleted] scaffold through the store with customers” and commanded him to “[g]o work off the f . . . [expletive deleted] ladders” that were already in the section being demolished. Because he did not want to disobey his supervisor‘s orders or defendant‘s policy prohibiting workers from moving equipment around the store while customers were present, plaintiff did not obtain the Baker scaffold.
When plaintiff arrived in the demolition section of the store, he saw three ladders, two of which were fiberglass A-frame ladders that were already in use by other workers. The only other ladder available was a “rickety,” old, wooden A-frame ladder. Nevertheless, because plaintiff had been instructed to complete the demolition work “ASAP,” he used the wooden ladder. After working with that ladder for approximately one hour, plaintiff “began dismantling the top support beam of the wall.” He attempted to place the ladder securely on the concrete floor, despite the fact that the floor was uneven because it had recently been jackhammered. While plaintiff stood on the ladder, with his feet approximately four feet from the ground, he swung his hammer. Unfortunately, after the hammer struck, the ladder “first shifted and wobbled, and then kicked out,” causing plaintiff to fall to the ground. As a result of the fall, plaintiff suffered fractures to his face and wrist.
Plaintiff commenced this action in April 2011, alleging violations of
On December 19, 2011, plaintiff‘s counsel called defendant‘s counsel to confirm that plaintiff‘s deposition would take place the following day in accordance with the preliminary conference order. Plaintiff argues that defendant refused, but defendant claims that it could not proceed with plaintiff‘s deposition because it was still awaiting documents pursuant to plaintiff‘s authorizations. Defendant further alleges that plaintiff‘s counsel verbally consented to adjourn the deposition until February 2, 2012. Plaintiff, however, denies consenting to the adjournment.3 The parties did not reduce the alleged agreement to writing, and neither party moved to amend the preliminary conference order or adjourn the deposition.
In any event, plaintiff filed a motion on December 28, 2011, seeking partial summary judgment on the issue of liability under
“[i]f [he] had been provided the Baker scaffold, [he] would not have fallen. The scaffold would have been proper because it would not have shifted as [he] hammered. And, because of its dimensions, it would have been able to better cope with the fact that the concrete floor was uneven.”
Defendant responded that the motion should be denied as premature, because plaintiff‘s deposition had not yet been conducted. However, the parties conducted plaintiff‘s deposition on February 2, 2012, and each party submitted supplemental motion papers. Defendant argued that plaintiff‘s deposition testimony raised triable issues of fact as to whether he was the
The motion court denied plaintiff‘s motion without prejudice as premature under
The Labor Law requires building owners and contractors who conduct construction or demolition projects to “furnish or erect, or cause to be furnished or erected for the performance of such labor, scaffolding, . . . ladders, . . . and other devices which shall be so constructed, placed and operated as to give proper protection to a person so employed” (
Defendant does not dispute plaintiff‘s assertions that a Baker scaffold would have been the adequate safety device for the demolition work and that plaintiff was not provided with one. When plaintiff attempted to fetch the Baker scaffold from the back of defendant‘s store, his supervisor stopped him and commanded him to use the ladders in the section of the store that
Furthermore, defendant‘s proposition that plaintiff should have fetched the Baker scaffold (despite his supervisor‘s contrary instruction) or waited for the fiberglass ladders to become available is unconvincing. For example, defendant cites Montgomery v Federal Express Corp. (4 NY3d 805 [2005]), where the plaintiff declined to fetch an available ladder, opted instead to stand on an overturned bucket in order to reach an elevator motor room, and was injured while jumping the four feet down from the motor room (see also Robinson v East Med. Ctr., LP, 6 NY3d 550, 554 [2006] [describing the facts of Montgomery]). However, unlike the plaintiff in Montgomery, plaintiff in this case initially exhibited the “normal and logical response . . . to go get” the adequate safety device when he attempted to fetch the Baker scaffold (Montgomery, 4 NY3d at 806 [internal quotation marks omitted]), but he was rebuffed by his supervisor. That plaintiff‘s supervisor explicitly directed him not to use the scaffold, citing defendant‘s policy against rolling equipment through the store while customers were present, rendered the scaffold essentially unavailable to plaintiff. There is no practical difference between what happened here—where a supervisor directs an employee to not use an otherwise available safety device—and a situation where a scaffold simply was not present at the work site (see Rice v West 37th Group, LLC, 78 AD3d 492, 496 [1st Dept 2010]).
In addition, the Robinson Court noted the plaintiff‘s concession that although the necessary “eight-foot ladders may have been in use at the time of his accident,” the plaintiff‘s “foreman had not directed him to finish [the task at that time],” and thus the plaintiff‘s decision to use a shorter ladder by “standing on the ladder‘s top cap” was “the sole proximate cause of his injuries” (6 NY3d at 555 [emphasis added]). Here, by contrast, plaintiff‘s supervisor yelled and cursed at him to use the ladders,
The Labor Law, recognizing the realities of construction and demolition work, does not require a worker to demand an adequate safety device by challenging his or her supervisor‘s instructions and withstanding hostile behavior. To place that burden on employees would effectively eviscerate the protections that the legislature put in place. Indeed, workers would be placed in a nearly impossible position if they were required to demand adequate safety devices from their employers or the owners of buildings on which they work (see Lombardi v Stout, 80 NY2d 290, 296 [1992] [explaining that
We reach the merits of this case notwithstanding defendant‘s argument that plaintiff‘s motion was premature. Although the parties proceeded with plaintiff‘s deposition after the filing of the motion, plaintiff‘s testimony was consistent with his affidavit. Therefore, defendant could not raise any issue of material fact that would preclude a grant of partial summary judgment concerning liability under
Finally, insofar as defendant raises comparative negligence or other issues that might provide a defense to liability on
Accordingly, the order of the Supreme Court, New York County (Debra A. James, J.), entered January 25, 2013, which denied plaintiff‘s motion for partial summary judgment on the issue of liability on his
RENWICK, FEINMAN and CLARK, JJ., concur.
Order, Supreme Court, New York County, entered January 25, 2013, modified, on the law, to the extent of granting plaintiff‘s motion on the issue of liability pursuant to