CSRS, LLC v. Element 25 LimitedCSRS, LLC v. Element 25 Limited
ORDER
Before the Court is Element 25 Limited’s (“Defendant”) Motion to Compel Arbitration and to Stay Pending Arbitration. (R. Doc. 21). CSRS, LLC, (“CSRS”) and Fides Consulting, LLC’s (“Fides”) oppose the motion (R. Doc. 31). Defendant filed a Reply. (R. Doc. 35).
I. Background
CSRS and Fides (“Plaintiffs”) initiated this lawsuit on May 6, 2024, bringing breach of contract, suit on open account, and unjust enrichment claims against Defendant. (R. Doc. 1). The suit concerns a contract (the “Contract”), entered into between Defendant and CSRS on or about June 30, 2023, wherein CSRS agreed to perform work and services for Defendant in connection with the construction of an industrial facility in Ascension Parish, Louisiana. (R. Docs. 1; 1-1). According to Plaintiffs, the Contract “also applied to work and services provided by Fides.” (R. Doc. 31 at 2). Plaintiffs allege Defendant owes them $830,783.25 for unpaid invoices from work they performed under the Contract. (R. Doc. 1). Pursuant to this same Contract, Defendant now brings the instant motion, requesting that this Court compel arbitration regarding this case.
II. Law and Analysis
A. Legal Standards
Defendant argues the Contract is subject to the New York Arbitration Convention
“In determining whether the Convention requires compelling arbitration in a given case, courts conduct only a very limited inquiry.” Freudensprung v. Offshore Technical Servs., Inc., 379 F.3d 327, 339 (5th Cir. 2004). Courts “should compel arbitration if (1) there is an agreement in writing to arbitrate the dispute, (2) the agreement provides for arbitration in the territory of a Convention signatory, (3) the agreement arises out of a commercial legal relationship, and (4) a party to the agreement is not an American citizen.” Francisco v. Stolt Achievement MT, 293 F.3d 270, 273 (5th Cir. 2002) (citation omitted). If these four requirements are met, the Court must enforce the arbitration clause “unless it finds that the said agreement is null and void, inoperative or incapable of being performed.” Freudensprung, 379 F.3d at 339 (citation omitted).
B. Analysis
i. There is an Arbitration Agreement in Writing
Defendant argues that the Contract contains an agreement to arbitrate, in London, any dispute relating to the Contract. This alleged agreement to arbitrate appears below:
16.1 In the event of any dispute, question or difference of opinion between Element 25 and the Consultant arising out of or in connection with this agreement (Dispute), a party may give a notice to the other party (Dispute Notice) specifying the Dispute and requiring its resolution under this clause.
16.3 If a Dispute is not resolved within 20 Business Days after the Notice Date, either party may submit the Dispute to arbitration and: . . .
(b) if the Consultant‘s primary place of business for the purpose of providing the Services is located outside of Australia, clause 16.5 will apply[.]
. . .
16.5 (a) the Dispute must be referred to the London Court of International Arbitration (LCIA) for resolution by arbitration in accordance with the LCIA Rules for the time being in force, which procedure (LCIA Rules) is deemed to be incorporated by reference into this clause, and the seat of the arbitration shall be London, England[.]
(R. Doc. 1-1 at 4, 12, 13). To determine whether an arbitration agreement exists, this Court must assess one sentence from the above: “If a Dispute is not resolved . . ., either party may submit the Dispute to arbitration[.]” (R. Doc. 1-1 at 12) (emphasis added). Plaintiffs do not dispute that they entered into the Contract that included the above, but instead argue, citing Retractable Technologies, Inc. v. Abbott Laboratories, Inc., 281 Fed. Appx. 275 (5th Cir. 2008) (per curiam) (unpublished), that the inclusion of “may” in this sentence makes the alleged arbitration agreement permissive.
In Retractable, a Fifth Circuit panel held that the following agreement was permissive:
[T]he Court [is] bound by Deaton Truck Line under the “rule of orderliness[,]” [which] provides that “one panel of [the Fifth Circuit] may not overturn another panel’s decision, absent an intervening change in the law, such as by statutory amendment, or the Supreme Court, or [an] en banc court.” Jacobs v. Nat’l Drug Intelligence Ctr., 548 F.3d 375, 378 (5th Cir. 2008). This is true even if the first “panel’s interpretation of the law appears flawed.” Id. [Retractable and Deaton] were panel decisions, so [Retractable] can[not] be interpreted as voiding the decision in Deaton Truck Line. The decision in Deaton Truck Line, as the earliest decision of the three, is therefore the authority that binds this Court.
Primoris Energy Servs. Corp. v. New Day Aluminum, LLC., No. CV 18-5839, 2018 WL 6046194, at *5 (E.D. La. Nov. 19, 2018); see Valley Int’l Cold Storage, LLC v. Conagra Foods Packaged Foods, LLC, No. 1:24-CV-00044, 2024 WL 5274509, at *2 (S.D. Tex. June 6, 2024) (citations omitted) (“Deaton Truck Line remains controlling law absent an intervening change in law.”); see also Retractable, 281 F. App’x at 275 (“Pursuant to 5th Cir. R. 47.5, the court has determined that this opinion should not be published and is not precedent except under the limited circumstances set forth in 5th Cir. R. 47.5.4.”). This Court must therefore follow Deaton, and other courts within the Fifth Circuit,1 to find that “may” in the alleged arbitration agreement does not make arbitration permissive, but instead makes arbitration mandatory in the event one of the parties to the Contract requests it. Thus, this Court finds the alleged arbitration agreement is, in fact, an arbitration agreement (heretofore, the “Arbitration Agreement”).
ii. The Arbitration Agreement Contains a Valid Delegation Clause
Defendant asserts that, according to the Contract, any dispute concerning arbitrability has been delegated to the arbitrator. Requiring that arbitration occur in the London Court of International Arbitration (the “LCIA”) in London England, the Arbitration Agreement states that the LCIA Rules are “deemed to be incorporated by reference[.]” (R. Doc. 1-1 at 4). LCIA Rule 23.1 states, “The Arbitral Tribunal shall have the power to rule upon its own jurisdiction and authority, including any objection to the initial or continuing existence, validity, effectiveness or scope of the Arbitration Agreement.” (R. Doc. 21-2). Based on the analysis below, this Court finds the incorporated LCIA Rule 23.1 serves as a valid delegation that this Court must abide by.
The Supreme Court “has consistently held that parties may delegate threshold arbitrability questions to the arbitrator, so long as the parties’ agreement does so by ‘clear and unmistakable’ evidence.” Henry Schein, Inc. v. Archer & White Sales, Inc., 586 U.S. 63, 69 (2019) (citations omitted). The Fifth Circuit has held that a “[p]arties’ express incorporation of rules from specific arbitration services in their arbitration agreement delegates arbitrability.” Richland Equip. Co., Inc. v. Deere & Co., 745 F. App’x 521, 524 (5th Cir. 2018) (citing Petrofac, Inc. v. DynMcDermott Petroleum Operations Co., 687 F.3d 671, 675 (5th Cir. 2012) (incorporating the American Arbitration Association rules); Brittania-U Nigeria, Ltd. v. Chevron USA, Inc., 866 F.3d 709, 714 (5th Cir. 2017) (incorporating the United Nations Commission on International Trade Law rules)). Thus, this Court finds that the incorporation of the LCIA Rules properly delegates arbitrability to the arbitrator.
“[A]bsent a challenge to the delegation clause itself, [courts] will consider that clause to be valid and compel arbitration.” Noble Cap. Grp., L.L.C. v. US Cap. Partners, Inc., No. 20-50721, 2021 WL 3477481, at *2 (5th Cir. Aug. 6, 2021); see Edwards v. Doordash, Inc., 888 F.3d 738, 744 (5th Cir. 2018) (“If there is an agreement to arbitrate with a delegation clause, and absent a challenge to the delegation clause itself, we will consider that clause to be valid and compel arbitration.”). Plaintiffs’ contention, detailed further below, is that the arbitration provision as a whole is unenforceable under Louisiana law and is not a specific challenge to the delegation clause itself. Noble, 2021 WL 3477481, at *3; Rent-A-Ctr., W., Inc. v. Jackson, 561 U.S. 63, 74 (2010) (“It may be that had Jackson challenged the delegation provision by arguing that these common procedures as applied to the delegation provision rendered that provision unconscionable, the challenge should have been considered by the court.”). Accordingly, this Court concludes that the Contract‘s incorporation of the LCIA Rules provides clear and unmistakable evidence that LCIA Rule 23.1 is a valid delegation clause with which this Court must comply.
iii. The Court May Still Determine Whether the Arbitration Agreement Exists and Whether it is Null and Void
Again, LCIA Rule 23.1 delegates to the arbitrator “the power to rule upon its own jurisdiction and authority, including any objection to the initial or continuing existence, validity, effectiveness or scope of the Arbitration Agreement.” (R. Doc. 21-2). Despite this “initial” language in LCIA Rule 23.1, this Court may, as it has in section (i), determine whether the Arbitration Agreement exists. See Henry, 586 U.S. at 66-71 (“To be sure,
As Plaintiff argues under Louisiana law, the FAA,2 and the Convention, this Court may also determine whether the Arbitration Agreement is null and void, despite the delegation clause, because the Convention itself provides that where the arbitration agreement is found to be “null and void, inoperative or incapable of being performed” arbitration need not be compelled. Convention, Article II(3). Plaintiffs have asked this Court to find that
iv. The FAA and the Convention preempt La. R.S. § 9:2779
In full,
A. The legislature finds that, with respect to construction contracts, subcontracts, and purchase orders for public and private works projects, when one of the parties is domiciled in Louisiana, and the work to be done and the equipment and materials to be supplied involve construction projects in this state, provisions in such agreements requiring disputes arising thereunder to be resolved in a forum outside of this state or requiring their interpretation to be governed by the laws of another jurisdiction are inequitable and against the public policy of this state.
B. The legislature hereby declares null and void and unenforceable as against public policy any provision in a contract,subcontract, or purchase order, as described in Subsection A, which either:
(1) Requires a suit or arbitration proceeding to be brought in a forum or jurisdiction outside of this state; rather, such actions or proceedings may be pursued in accordance with the Louisiana Code of Civil Procedure or other laws of this state governing similar actions.
(2) Requires interpretation of the agreement according to the laws of another jurisdiction.
C. The provisions of this Section apply to contracts, subcontracts, and purchase orders, as described in Subsection A, entered into on or after September 6, 1991.
D. Notwithstanding any other provisions of law to the contrary, the provisions of this Section shall not apply to negotiated labor contracts.
Based on the above, Plaintiff argues the Arbitration Agreement is null and void and unenforceable. (R. Doc. 17). Relying on OPE Int‘l LP v. Chet Morrison Contractors, Inc., 258 F.3d 443, 447 (5th Cir. 2001) and Lim v. Offshore Specialty Fabricators, Inc., 404 F.3d 898 (5th Cir. 2005), Defendant argues the FAA and the Convention preempt
Plaintiff argues that Police Jury stands for the proposition that “foreign arbitration clauses cannot be enforced where Louisiana law provides that such a clause is against public policy.” (R. Doc. 31 at 13) (emphasis in original). Plaintiff reads Police Jury incorrectly, however. In Police Jury, Louisiana insurers were attempting, in the Western District of Louisiana, to use equitable estoppel to compel arbitration under a foreign insurer‘s contract that was subject to the Convention in order to circumvent
Plaintiff‘s reliance on
Although the Fifth Circuit has never determined whether the FAA preempts section 9:2779, we have held that the FAA preempts other state laws that preclude parties from enforcing arbitration agreements. . . . Section 9:2779 declares “null and void and unenforceable as against public policy any provision in [certain construction subcontracts] . . . which [ ] [r]equires a suit or arbitration proceeding to be brought in a forum or jurisdiction outside of [Louisiana].” La. Rev. Stat. Ann. 9:2779(B)(1). The statute directly conflicts with § 2 of the FAA because the Louisiana statute conditions the enforceability of arbitration agreements
on selection of a Louisiana forum; a requirement not applicable to contracts generally. . . . The FAA therefore preempts the Louisiana statute[.]
OPE, 258 F.3d at 447-48. Plaintiff asks this Court to ignore the Fifth Circuit‘s holding on the basis that the parties in OPE waived their rights pursuant to
The Court comes to the same conclusion regarding the Convention. In Lim, the Fifth Circuit held that the Convention preempted a Louisiana statute,
This Court finds the same is true with regard to
Miller, 389 U.S. 429, 440-41 (1968); Clark v. Allen, 331 U.S. 503, 508 (1947) (Where there is a conflict between a treaty and a state statute, the treaty will control.).
v. The Four Convention Requirements Are Met Here
According to the Convention, courts “should compel arbitration if (1) there is an agreement in writing to arbitrate the dispute, (2) the agreement provides for arbitration in the territory of a Convention signatory, (3) the agreement arises out of a commercial legal relationship, and (4) a party to the agreement is not an American citizen.” Francisco, 293 F.3d at 273 (citation omitted). Here, there is an agreement in writing, and whether the agreement covers the instant dispute has been delegated to the arbitrator. Thus, the first factor is met. As for factors two through four, they are met as the arbitration is set to be in London, UK, a Convention signatory; the Contract and Arbitration Agreement arose out of a commercial legal relationship; and one of the parties to the Contract and Arbitration Agreement is not an American citizen. Viator v. Dauterive Contractors, Inc., 638 F. Supp. 2d 641, 647 (E.D. La. 2009) (London, UK is a Convention signatory). As all of the factors have been met, this Court shall compel arbitration.
As none of the parties deny that the Contract “also applied to work and
vi. The Case May Be Stayed Until the Arbitration Ends
“[T]he Convention and its implementing legislation do not explicitly authorize staying litigation pending arbitration, and thus parties whose arbitration agreements fall under the Convention have had to seek authority for stays under
III. Conclusion
Considering the foregoing,
IT IS ORDERED that the Motion to Compel Arbitration and to Stay Pending Arbitration (R. Doc. 21) is GRANTED and this case shall be arbitrated, pursuant to the Arbitration Agreement, in London, UK, with the case to be STAYED in this court pending said arbitration.
Signed in Baton Rouge, Louisiana, on March 18, 2025.
RICHARD L. BOURGEOIS, JR.
UNITED STATES MAGISTRATE JUDGE
Notes
(R. Doc. 1-1 at 4) (emphasis added).Each party represents and warrants . . . that it is not entitled to claim immunity from any legal action or proceeding with respect of itself or any of its assets in relation to the enforcement of this agreement on the ground of sovereignty or otherwise under any law.
However, such an interpretation would require a reader of Lim to ignore the Fifth Circuit‘s equally clear assertion that it was also apportioning weight based on “the strong federal policy in favor of international arbitration agreements in general” Id. The undersigned is faced with a Contract to which the FAA and the Convention equally apply, and this Court sees no logic in finding that