PETROFAC, INCORPORATED, Plaintiff-Appellee, v. DYNMCDERMOTT PETROLEUM OPERATIONS COMPANY, Defendant-Appellant.
No. 11-20141.
United States Court of Appeals, Fifth Circuit.
July 17, 2012.
671 F.3d 671
We have already determined that the “timely validate” language is not inconsistent with the letter‘s notice. While overshadowing is a different inquiry than inconsistency, we conclude that McMurray‘s overshadowing argument as to the “timely validate” language fails for similar reasons.
The supposed threat falls in the category of “letters [that] encourage debtors to pay their debts by informing them of the possible negative consequences of failing to pay,” words that do not overshadow the required notice language. Durkin v. Equifax Check Servs., Inc., 406 F.3d 410, 417-18 (7th Cir.2005). This is because “one way to encourage someone with a true dispute to come forward and resolve that dispute is to inform him of the possible negative consequences of his continued inaction.” Id. at 418 n. 7. “Not only does this encouragement promote payment of valid debts, it also promotes disclosing genuine claims of invalid debts (such as demonstrating the debt resulted from a forgery).” Id. “Promoting final resolution of such matters, either way, is inherently beneficial.” Id. The letter in this case essentially provided such warnings and nothing more. Thus, the notice language in ProCollect‘s letter is not overshadowed by the letter‘s bad-credit warnings.
We also conclude that the physical attributes of ProCollect‘s Section 1692g(a) notice do not cause an overshadowing. The notice is located on the same page as the language contested by McMurray, is in bold typeface (unlike the contested language), and of the same size and font as the rest of the letter. Also significant is that the notice is located immediately above the line provided for tearing off the payment form, and thus, by this spacial proximity, provided visual confirmation that payment was not the only option. Cf. Sims v. GC Servs. L.P., 445 F.3d 959, 963-64 (7th Cir.2006) (concluding statement on letter‘s front in prominent, red, bold, capital lettering that “important consumer information” on back was not overshadowed by text on front asking for prompt payment of debts, despite notice text on back being more difficult to read than text on front).
ProCollect‘s collection letter was not inconsistent with and did not overshadow the letter‘s Section 1692g(a) notice. Therefore, a least-sophisticated or unsophisticated consumer would not be confused by the letter.
AFFIRMED.
Henry A. King (argued), John A. Cangelosi, Timothy S. Madden, King, Krebs & Jurgens, P.L.L.C., New Orleans, LA, for Defendant-Appellant.
Before DeMOSS, CLEMENT and ELROD, Circuit Judges.
JENNIFER WALKER ELROD, Circuit Judge:
DynMcDermott Petroleum Operations Company (DM) appeals the district court‘s confirmation of an arbitration award in favor of Petrofac, Incorporated. Because DM fails to show any reversible error, we AFFIRM.
I.
DM operates the Strategic Petroleum Reserve for the Department of Energy. DM subcontracted with Petrofac to design and install a transportable degas plant to service the reserve. On July 30, 2003, DM and Petrofac agreed to resolve any claim under the subcontract through binding arbitration. The contract stated:
Petrofac and DM agree to enter into binding arbitration for any Request for Equitable Adjustment or claim submitted against the referenced subcontract, in lieu of litigation, in the event that a mutually agreeable resolution cannot be bilaterally achieved between DM and Petrofac through negotiations.
In May 2004, Petrofac sent DM a multivolume Request for Equitable Adjustment (REA). There, Petrofac asserted that DM disrupted Petrofac‘s ability to perform its work and sought damages for differing site conditions, delays, disruption costs, lost productivity, and acceleration costs.
On December 6, 2005, Petrofac agreed to release DM from all but a few specifically preserved claims. Among these preserved claims, the release included Petrofac‘s REA “as may be amended or supplemented.”1 By July 2006, the parties had failed to resolve the REA dispute via negotiation.
Petrofac subsequently filed its demand for arbitration. In June 2008, Petrofac provided DM the report of its damages expert, Frank Adams. The Adams report calculated Petrofac‘s damages using a different methodology and reached a different amount than the original REA. The arbitration began in March 2009. After five days of hearings, however, the arbitration panel recessed for seven months. When the arbitration reconvened, DM objected to the arbitration panel hearing any claims stemming from the different damages methodology used in the Adams report, claiming that it effectively created a new constructive change claim outside the parties’ agreement to arbitrate.
The arbitration panel dismissed DM‘s objection because “the arbitration agreement is clear and encompasses all of the issues between the parties arising out of this contract. It is also clear that DM waived any objection it had to the arbitration of a constructive change claim.” The arbitration panel subsequently awarded Petrofac damages for the “contract balance, damages for a constructive change to the contract, an award for the benefit of Womack, and interest from August 24, 2006 to July 26, 2010” to be paid “within thirty days of the Award.”
The district court confirmed the award. The district court rejected DM‘s argument that the REA and the Adams report represented different claims. Therefore, the district court ruled that the arbitration panel did not exceed its authority by awarding damages as presented in the Adams report. The court also determined that the award was not procured through fraud or undue means under
II.
This court reviews “a district court‘s confirmation of an award de novo, but the review of the underlying award is exceedingly deferential.” Apache Bohai Corp. LDC v. Texaco China BV, 480 F.3d 397, 401 (5th Cir.2007) (internal quotation marks omitted).
A.
On appeal, DM argues that the arbitration panel exceeded its powers by issuing an award on a claim not covered by the parties’ arbitration agreement.
We first consider if the arbitration panel properly determined the initial
Here, the parties expressly incorporated into their arbitration agreement the AAA Rules. These rules state that “[t]he arbitrator shall have the power to rule on his or her own jurisdiction, including any objections with respect to the existence, scope or validity of the arbitration agreement.” We agree with most of our sister circuits that the express adoption of these rules presents clear and unmistakable evidence that the parties agreed to arbitrate arbitrability. See Fallo v. High-Tech Inst., 559 F.3d 874, 878 (8th Cir.2009) (“[W]e conclude that the arbitration provision‘s incorporation of the AAA Rules ... constitutes a clear and unmistakable expression of the parties’ intent to leave the question of arbitrability to an arbitrator.“); Qualcomm Inc. v. Nokia Corp., 466 F.3d 1366, 1372-73 (Fed. Cir.2006) (same); Terminix Int‘l Co., LP v. Palmer Ranch Ltd. P‘ship, 432 F.3d 1327, 1332-33 (11th Cir.2005) (same); Contec Corp. v. Remote Solution Co., 398 F.3d 205, 208 (2d Cir.2005) (same); Apollo Computer, Inc. v. Berg, 886 F.2d 469, 473 (1st Cir.1989) (same result under the similar ICC Rules). But see Riley Mfg. Co. v. Anchor Glass Container Corp., 157 F.3d 775, 780 (10th Cir.1998).2 Therefore, the arbitration panel properly made the decision that the damages calculations in the Adams report fell within the agreement to arbitrate.3
B.
Next, DM contends that Petrofac procured the overtime premium portion of the award through fraud or undue means.
C.
Finally, DM argues the district court committed reversible error by ordering prejudgment interest. “Texas law governs the award of prejudgment interest on the [arbitration] award,” and “[u]nder Texas law, prevailing parties receive prejudgment interest as a matter of course.” Executone Info. Sys., Inc. v. Davis, 26 F.3d 1314, 1329 (5th Cir.1994). On July 26, 2010, the arbitration panel ruled that Petrofac was entitled to interest, calculated the amount of interest as of the date of the award, and ordered payment of “interest from August 24, 2006 to July 26, 2010, within thirty days of the Award.” DM did not pay within the required thirty-day period. The district court ordered that DM pay additional interest, reasoning that by ordering payment by August 25, 2010, the arbitration panel created “a thirty-day interest-free window from the date of the award,” and DM “is not permitted to discount the arbitration panel‘s award by recalcitrantly delaying payment.” We agree. The district court properly reinstated the arbitration panel‘s interest award after DM refused to pay within the required period.5
III.
The district court properly confirmed the arbitration panel‘s arbitration award. On appeal, DM has failed to demonstrate reversible error. Consequently, the judgment of the district court is AFFIRMED.
GUIDEONE SPECIALTY MUTUAL INSURANCE COMPANY, Plaintiff-Appellee, v. MISSIONARY CHURCH OF DISCIPLES OF JESUS CHRIST; Michael A. Meyer; Amando Salgado, Defendants-Appellees, v. Sonya Gilmore, Defendant-Appellant.
No. 11-10894.
United States Court of Appeals, Fifth Circuit.
July 17, 2012.
Notes
In consideration of payments made heretofore, or to be made, by DM ... [Petrofac] hereby unconditionally releases DM from any and all liens and claims whatsoever arising out of or during the performance of said Subcontract other than such claims, if any, that may be specifically excepted from the terms of this Release and Certificate, stated below:
- Request for Equitable Adjustment submitted by Petrofac, Inc. as may be amended or supplemented;
- Invoice No. 2004-79-855 in the amount of $995,718.00...;
- Invoice No. 2005-01-855 in the amount of $338,400.00;
- All rights and claims of [Petrofac] in connection with its disputes and objections to DM‘s Unilateral Change Orders 17, 18, and 22;
- Claim for Equitable Adjustment in the amount of $536,128.08 submitted by L.S. Womack, Inc. a subcontractor of Petrofac, Inc.; and
- Specified claims in full and precise amounts to be received by the Subcontract Manager within ninety (90) calendar days from the issuance of final acceptance by the Subcontract Manager.
