CROWN COAT FRONT CO., Inс., Plaintiff-Appellant, v. UNITED STATES of America, Defendant-Appellee.
No. 34, Docket 29710.
United States Court of Appeals Second Circuit.
Argued Oct. 5, 1965. Submitted to the in banc court Dec. 9, 1965. Decided June 22, 1966.
Certiorari Granted Oct. 10, 1966. See 87 S.Ct. 87.
407
Edwin J. McDermott, Philadelphia, Pa. (Jasper I. Manning, New York City, on the brief), for plaintiff-appellant.
Arthur M. Handler, Asst. U. S. Atty., Southern District of New York (Robert M. Morgenthau, U. S. Atty., and Alan G. Blumberg, Asst. U. S. Atty., Southern District of New York, on the brief), for defendant-appellee.
Before LUMBARD, Chief Judge, and WATERMAN, MOORE, FRIENDLY, SMITH, KAUFMAN, HAYS, ANDERSON and FEINBERG, Circuit Judges.
WATERMAN, Circuit Judge (with whom Chief Judge LUMBARD, Judges MOORE and SMITH, and in a separate statement, Judge FRIENDLY, concur. Judge ANDERSON dissents in a separate opinion with whom Judges KAUFMAN, HAYS and FEINBERG concur):
Plaintiff-appellant, on July 31, 1963, commenced its action against the United Statеs in the United States District Court for the Southern District of New York. After the Government answered, pleading
The Government, meeting this thrust, briefed its case on the sole issue whether, “pursuant to
On May 14, 1956 the appellant entered into a contract with the Government to manufacture and deliver 89,786 felt canteen covers for a total agreed price of $60,691.76. The contract called for the use of mildew-resistant felt, made in accordance with certain established specifications, and provided for the submission of samples to the Government for testing and inspection, prior to manufacture. It also stipulated that if these samples did not meet specifications, the Government had “the right either to reject them or to require their correction.” In addition, the agreement included the standard “disputes” clause which required that, in the first instance, “any dispute concerning a question of fact arising under this contract which is not disposed of by agreement shall be decided” by the Contracting Officer, from whose decision an appeal could be taken to the Armed Services Board of Contract Appeals (ASBCA).2
In accordance with the contract, appellant submitted four lots of felt samples for testing and inspection. After making laboratory tests in October and November 1956, the Government rejected the samples. Thereupon the appellant requested, and the Government agreed to accept, the delivery of the canteen covers made from the non-conforming felt. A contract modification of $.005 less per unit—a total of $270.01—was agreed upon. Final delivery was made on December 14, 1956, and in all other respects the modified contract was fully performed.
The appellant claims that it was not until nearly five years later that it first learned the Government had improperly tested the samples by submitting them to a different test than contemplated by the contract. On October 4, 1961, appellant‘s counsel wrote the Contracting Officer and demanded (1) a refund of the $270.01 price adjustment, and (2) an equitable adjustment for alleged increased extra production costs resulting from the initial rejection of the samples. On Febru
Following McMahon, and after the passage of the Wunderlich Act, May 11, 1954, c. 199, 68 Stat. 81,
In fact, in States Marine we disposed of every claim appellant makes here. We held that the contractor should not await final decision of the ASBCA, in accord with his agreement to submit disputes to the agency officers, before commencing a protective suit, and that the time-bar period did not begin to run from the time of the final decision of the ASBCA, but, as the right of action accrued at the time of the breach, the time-bar began to run then. Moreover, we held, supra at 779, that the running of the time-bar was not tolled during the periоd when the claim was under administrative consideration.
Unless a reason exists for differently treating a suit brought pursuant to the permission granted by the Tucker Act from a suit brought pursuant to the permission granted by the Suits in Admiralty Act, we would be required to overrule the law of this circuit laid down in States Marine and reaffirmed in Isthmian S. S. Co. v. United States, 302 F.2d 69 (2 Cir. 1962) if we were to grant relief to the appellant here.
After final briefs had been filed by the parties the Third Circuit handed down its opinion in Northern Metal Co. v. United States, 350 F.2d 833 (3 Cir. 1965). In that case McMahon was followed as to the fixing of the time when the two-year time-bar began to run, but, in direct conflict with the opinion of our court in States Marine Corp. of Del. v. United States, supra, and the decisions following it (including the district court opinion appealed from in Northern Metal Co. v. United States, 230 F.Supp. 38 (E.D.Pa. 1964)) the Third Circuit held that the running of this time-bar was tolled dur-
Though the more recent Suits in Admiralty Act appears in the U. S. Code, section for section, much as it was when adopted in 1920, and the various provisions, section for section, of the eighty-year old Tucker Act are split up, here and there, in Titlе 28 of the Code, both Acts of Congress are grants of rights to sue the Government, which, being the sovereign, has full immunity from standing any suit at all. As such, both Acts set forth the kinds of claims that may be brought, the courts within which these specified claims are to be litigated, and the length of time within which these specified claims may be presented after the causes of action arose, or accrued. These built-in limitations upon a more complete waiver of sovereign immunity spell out the ambit within which a would-be litigant seeking recovery from the sovereign must operate; in short, unless the would-be litigant operates within the area of the statutory grant, he is outside the jurisdiction the sovereign granted him, whether his cause of action is an impermissible one, he is in the wrong forum, or his time in which to act has expired.
Of the time-bar condition, we said in States Marine:
“The two year time-bar of the Suits in Admiralty Act is unlike a time-bar period prescribed under an ordinary Statute of Limitations. Under an ordinary time-bar statute a claim is not extinguished after the statutory period has elapsed. It is only unenforceable. The time-bar of the Suits in Admiralty Act renders a claim against the United States not only unenforceable, but extinguishes the claim itself, for when the sovereign, immune from suit, consented to be sued it was made a condition of the right to sue that suits so authorized had to be brought within the time-bar periоd. McMahon v. United States, supra [342 U.S. 25, 72 S.Ct. 17, 96 L.Ed. 26 (1951)]; Sgambati v. United States, supra [172 F.2d 297, 298, cert. denied, 337 U.S. 938, 69 S.Ct. 1514, 93 L.Ed. 1743 (1949)].”
“It therefore follows that despite any maritime contractual agreements that parties may enter into with the United States such contractual agreements may not extend the time-bar period of two years prescribed by Section 5 of the Suits in Admiralty Act within which suit against the United States may be commenced. United States v. Wessel, Duval & Co., D.C.S.D.N.Y.1953, 115 F.Supp. 678. Accord, Atlantic Carriers, Inc. v. United States, D.C.S.D.N.Y.1955, 131 F.Supp. 1. Jurisdiction to hear a case brought at a later date than two years after the cause of action arose cannot be awarded to the court by agreement.” 283 F.2d 776, 778.
What we said in States Marine about the time-bar of the Suits in Admiralty Act apрlies to the time-bar of the Tucker Act. A Tucker Act claim is extinguished when the limiting time expires. The claim being extinguished, the court‘s jurisdiction is gone, and jurisdiction to adjudicate the claim cannot be conferred upon the court by any agreement.
Prior to the passage of the Tucker Act in 1887, a suit could be brought against the United States in the Court of Claims provided it was brought within six years after the right to suit had accrued. The
In October 1887, the same year that the Tucker Act was adopted, in deciding an appeal to the U.S. Supreme Court from a decision of the Court of Claims, Justice Harlan stated in Finn v. United States, 123 U.S. 227, 232-233, 8 S.Ct. 82, 85, 31 L.Ed. 128, with reference to the permissive six-year period then, and now, applicable to that Court, the following:
The general rule that limitation does not operate by its own force as a bar, but is a defence, and that the party making such a defence must plead the statute if he wishes the benefit of its provisions, has no application to suits in the Court of Claims against the United States. An individual may waive such a defence, either expressly or by failing to plead the statute; but the government has not expressly or by implication conferred authority upon any of its officers to waive the limitation imposеd by statute upon suits against the United States in the Court of Claims. Since the government is not liable to be sued, as of right, by any claimant, and since it has assented to a judgment being rendered against it only in certain classes of cases, brought within a prescribed period after the cause of action accrued, a judgment in the Court of Claims for the amount of a claim which the record or evidence shows to be barred by the statute would be erroneous.
In United States v. Greathouse, 166 U.S. 601, 17 S.Ct. 701, 41 L.Ed. 1130 (1897) the Tucker Act was construed, again by Mr. Justice Harlan. Finn v. United States was cited and followed. The Court held:
We may add that it was not contemplated that the limitation upon suits against the Government in the District and Circuit Courts of the United States should be different from that applicable to like suits in the Court of Claims. 166 U.S. at 606, 17 S.Ct. at 703. (Emphasis supplied.)
Shortly thereafter, in United States v. Wardwell, 172 U.S. 48, 19 S.Ct. 86, 43 L.Ed. 360 (1898) the matter has been laid to rest in the Supreme Court for seventy years. Mr. Justice Brewer, beginning the opinion for the unanimous Court in that case stated, p. 52, 19 S.Ct. p. 88:
Section 1069, Rev.St., is not merely a statute of limitations, but also jurisdictional in its nature, and limiting the cases of which the Court of Claims can take cognizance. Finn v. United States, 123 U.S. 227 [8 S.Ct. 82, 31 L. Ed. 128].
This “jurisdictional” interpretation of the six-year time-bar has never been overruled by the United States Supreme Court. And the Court, consistent with this interpretation, has rejected the contention that the jurisdictional time-bar should not begin to run until after an administrative denial of a claimant‘s claim when that contention has been advanced оn the theory that there is no ground for a suit in court until all administrative remedies have been exhausted. Soriano v. United States, 352 U.S. 270, 77 S.Ct. 269, 1 L.Ed.2d 306 (1957).
Appellant states in his complaint that the decision of the Armed Services Board of Contract Appeals “is not entitled to
Even as we cannot accept February 28, 1963 as the date when appellant‘s claim accrued we also cannot accept November 14, 1962 as the date of accrual, the date the Government refunded the erroneously withheld prompt payment discounts. A refunding adjustment made years after the final delivery of goods and the submission of a voucher for payment of those goods is not a “final voucher” submitted by the contractor, and, as pointed out by the court below, appellant‘s right to sue accrued when its work was completed and its final voucher was submitted. See B-W Construction Company v. United States, 100 Ct.Cl. 227 (1943); Austin Engineering Co. v. United States, 88 Ct.Cl. 559; Acorn Decorating Corporation v. United States, 174 F.Supp. 949, 146 Ct.Cl. 394 (1959). As was said by the Court of Claims in Pink v. United States, 85 Ct.Cl. 121, cert. denied, 303 U.S. 642, 58 S.Ct. 641, 82 L.Ed. 1102 (1938):
* * * It has been repeatedly held by this court that under a contract to perform work, the completion and acceptance date starts the statute to run. It is the completion of the service called for under the contract, and not the date of any payment subsequently made.
Finally, it is clear that when Congress passed the Wunderlich Act that body did not intend to grant any new period of permissive delay within which the built-in six-year time-bar of the Tucker Act might be tolled. The House Committee Report is explicit on the point and demonstrates that Congress was fully aware of the established law and did not intend to affect it.
In view of the foregoing, we reiterate what we said in States Marine Corp. of Del. v. United States, supra, 283 F.2d at 779, and hold here that inasmuch as the six-year limitation is a restriction upon the jurisdiction of the district court, the running of the six-year time-bar could not be extended by the Disputes Clause agreement of the parties, or tolled during the period that appellant‘s claim was being administratively considered.
In general, see Unitеd States v. Utah Construction and Mining Co., 86 S.Ct. 1545 (June 6, 1966) and United States v. Carlo Bianchi & Co., 373 U.S. 709, 83 S.Ct. 1409, 10 L.Ed.2d 652 (1963), if a claimant is uncertain whether he should proceed at once with a Tucker Act suit or first submit a dispute, pursuant to his agreement, to the ASBCA, he may always protect himself by instituting a “protective suit” within the six-year period permitted by the Tucker Act, staying its progress until after a final administrative decision, and then bringing it forward if the administrative decision is adverse to him.
The judgment below is affirmed.
FRIENDLY, Circuit Judge (concurring):
If the issue here were now arising in this court for the first time, I might well be persuaded to the position
ANDERSON, Circuit Judge, with whom Judges KAUFMAN, HAYS, and FEINBERG concur (dissenting):
I dissent. I do, however, agree with the majority that the period of limitations began to run on the date of the alleged breach of the contract. The claim for breach accrued at the latest on December 14, 1956, the date of the final delivery, which wаs more than six years prior to the commencement of this action. The Supreme Court decided in McMahon v. United States, 342 U.S. 25, 72 S.Ct. 17, 96 L.Ed. 26 (1951) that a seaman‘s claim for injuries accrued at the date of the injury, and not at the date when his claim was rejected by administrative officers.1
A similar result has been reached in our own circuit in States Marine Corporation of Delaware v. United States, 283 F.2d 776, 778 (2d Cir. 1960), and more recently by the Third Circuit in Northern Metal Co. v. United States, 350 F.2d 833 (3d Cir. 1965).
I am of the opinion, however, that the decision below should be reversed because the limitations period was tolled during the pendency of the administrative proceedings required by the disputes clause.
As the Supreme Court stated in Burnett v. New York Cent. R. Co., 380 U.S. 424, at 426, 85 S.Ct. 1050, at 1053, 13 L.Ed.2d 941 (1965),
“The basic question to be answered in dеtermining whether, under a given set of facts, a statute of limitations is to be tolled, is one of ‘legislative intent whether the right shall be enforceable * * * after the prescribed time.‘”
The Court went on to say at 427, 85 S.Ct. at 1054,
“In order to determine congressional intent, we must examine the purposes and policies underlying the limitation provision, the Act itself, and the remedial scheme developed for the enforcement of the rights given by the Act.”
The statutes of limitations are statutes of repose, designed to put an end to litigation.
“The primary consideration underlying such legislation is undoubtedly one of fairness to the defendant. There comes a time when he ought to be secure in his reasonable expectation that the slate has been wiped clean of
ancient obligations, and he ought not to be called on to resist a claim when ‘evidence has been lost, memories have faded, and witnesses have disappeared.‘” Note, 63 Harv.L.Rev. 1177, at 1185 (1950).
“This policy of repose, designed to protect defendants, is frequently outweighed, however, where the interests of justice require vindication of the plaintiff‘s rights.”
Burnett v. New York Cent. R. Co., supra, 380 U.S. at 428, 85 S.Ct. at 1055. Thus courts have engrafted numerous exceptions upon statutory periods of limitations. Sеe, e. g., Urie v. Thompson, 337 U.S. 163, 69 S.Ct. 1018, 93 L.Ed. 1282 (1949); Bailey v. Glover, 88 U.S. (21 Wall.) 342, 22 L.Ed. 636 (1874). The otherwise mechanical results, to which the unbated application of the limitations periods would lead, have thus been mitigated by familiar principles such as the one that a period of limitations is tolled until fraud is discovered. Bailey v. Glover, supra. Similarly it is accepted that,
“Where the plaintiff is prevented from finding timely suit by force of law, it is manifestly unjust to penalize him by barring the suit.” 63 Harv.L.Rev. at 1233.
And in Urie v. Thompson, supra, the Supreme Court recognized that a claim for an injury caused by a slow and continuing process was not barred if brought within three years of discovery of the ailment. Finally, in other instances it is recognized that the principles of estoppel may prevent a defendant from raising the defense of the statute of limitations, “when his representations or conduct have induced the plaintiff to forbear from prosecuting his known cause of action, and the limitations period has expired while the plaintiff continues to forbear.” 63 Harv.L.Rev. at 1222. The application of these principles should not depend upon whether the statute of limitations involved is one which may be characterized as “substantive” or “procedural.” Nor does the fact that a newly created right of action sprang from a waiver of sovereign immunity render the statute of limitations impervious to the appliсation of those same mitigating considerations. In every case inquiry should be directed to the basic question of “legislative intent.” Burnett v. New York Cent. R. Co., supra. By making the administrative proceedings a mandatory prerequisite to the seeking of relief in such cases from the courts, Congress did not intend that the statute of limitations would run during the pendency of those administrative hearings and deliberations.
Looking to the scheme of the Tucker Act,
“Since the Government through its contracting officer and the Armed Services Board of Contract Appeals not only was aware of the claim but was engaged in deciding its merits, it would be harsh and out of harmony with the purpose and intention of Congress to hold that the statutory time ran during the pendency of the administrative proceedings.”
I do not believe that the contractor‘s ability to bring a protective suit is a satisfactory solution to the problem. Such a рrocedure would inevitably lead to the defeat of many legitimate claims in the cases of claimants who are unaware of the need for bringing such protective actions. Furthermore, it would have the unfortunate effect of increasing the burden of the district courts by causing still more crowding of already crowded dockets with lawsuits which will languish for years during the pendency of administrative proceedings, and which in all probability will never come up for trial. Therefore, as a matter of sound judicial administration the requirement that a protective suit be commenced within the period of limitations has little to commend it.
The statutory period of limitations (
Notes
Appellant‘s brief sets forth the questions involved as follows:
“1. Where the ‘Changes’ clause of the contract provides that any failure to agree to a contract price adjustment is a dispute concerning a question of fact within the meaning of the ‘Disputes’ clause, and the ‘Disputes’ clause provides a procedure for the settlement of disрutes arising under the contract, must not the contractor pursue such administrative remedy and secure a final decision thereof before he may institute suit? Negatived by the Court below.
“2. Where the plaintiff-appellant brings suit within the statutory period of six years after the final decision of the Armed Services Board of Contract Appeals under the ‘Disputes’ article of the contract, is plaintiff-appellant barred by the statute of limitations? Affirmed by the Court below.”
In its reply brief, filed August 27, 1965, appellant reiterated the position that “Since plaintiff-appellant‘s suit was filed within six years from the date that its right of action accrued, it was timely,” and that it “сould not have sued until the decision of the Armed Services Board of Contract Appeals was rendered on February 28, 1963.”
In McMahon the Supreme Court left open the question of whether the statutory period there in question had been tolled, since a decision on that point would not have affected the result. 342 U.S. at 28, 72 S.Ct. at 19.Such a clause is required for most government contracts. See 32 C.F.R. § 7.103-12 and 32 C.F.R. § 596.103-12. The clause in question in this case reads as follows:
“Except as otherwise provided in this contract, any dispute concerning a question of fact arising under this contract which is not disposed of by agreement shall be decided by the Contracting Officer, who shall reduce his decision to writing and mail or otherwise furnish a copy thereof to the Contractor. Within 30 days from the date of receipt of such copy, the Contractor may appеal by mailing or otherwise furnishing to the Contracting Officer a written appeal addressed to the Secretary, and the decision of the Secretary or his duly authorized representative for the hearing of such appeals shall, unless determined by a court of competent jurisdiction to have been fraudulent, arbitrary, capri-
Cf. Carnation Co. v. Pacific Westbound Conference, 383 U.S. 213, 86 S.Ct. 781, 15 L.Ed.2d 709, 851 (1966), wherе, in another context, the Supreme Court, in a dictum stating that it was error to dismiss an action which the Court of Appeals had decided should have been presented first to an administrative tribunal, noted that:
“Such claims are subject to the Statute of Limitations and are likely to be barred by the time that the [administrative agency] acts. Therefore, we believe that the Court of Appeals should have stayed the action instead of dismissing it.” 383 U.S. at 223, 86 S.Ct. at 787.
While the subject matter in Carnation is certainly different from the one which is now before our court, nevertheless the same considerations apply and dictate that the Statute of Limitations should be tolled during the pendency of the administrative proceedings before the ASBCA.
“§ 1346. United States as defendant.
(a) The district courts shall have original jurisdiction, concurrent with the Court of Claims, of:
*
*
*
*
*
(2) Any other civil action or claim against the United States, not exceeding $10,000 in amоunt, founded either upon the Constitution, or any Act of Congress, or any regulation of an executive department, or upon any express or implied contract with the United States, or for liquidated or unliquidated damages in cases not sounding in tort.”
The Tucker Act was a comprehensive statute and also included among other provisions a predecessor provision to the present
“§ 2401. Time for commencing action against United States.
(a) Every civil action commenced against the United States shall be barred unless the complaint is filed within six years after the right of action first accrues. The action of any person under legal disability or beyond the seas at the time the claim аccrues may be commenced within three years after the disability ceases.”
