CITY OF NEW YORK, Plaintiff, v. NATIONAL RAILROAD PASSENGER CORPORATION, Defendant.
Civil Action No. 11-1169 (RC).
United States District Court, District of Columbia.
Aug. 13, 2013.
The EWA plaintiffs, who filed their lawsuit after the statute of limitations had passed to challenge the 2005 Listing Rule, see supra note 20, have aggressively challenged the Removal Rule, which eliminated the Captive-bred Exemption on which they have relied for many years. The Court, however, rejects all of their arguments that the promulgation of the Removal Rule was arbitrary and capricious and contrary to law, and finds that the agency‘s promulgation of the Removal Rule was a rational response to the 2009 Decision holding the Captive-bred Exemption invalid. Accordingly, the Removal Rule will stand.
V. CONCLUSION
For the reasons explained above, in the SCI Action, the Court denies the SCI plaintiff‘s Motion for Summary Judgment, ECF No. 45, and grants the cross-motions for summary judgment of the federal defendants, the DOW defendant-intervenors, and defendant-intervenor Friends of Animals. ECF Nos. 68, 70, 73. As to the EWA Action, the Court denies the EWA plaintiff‘s Motion for Summary Judgment, ECF No. 78, the Defendant-intervenor Friends of Animals’ Motion to Dismiss, ECF No. 47, the EWA Plaintiffs’ Motion to Supplement the Administrative Record, ECF No. 76, and the Defendant Intervenor Friends of Animals’ Cross-Motion for Summary Judgment (Lack of Standing), ECF No. 87, and grants the cross-motions for summary judgment of the federal defendants and the DOW defendant-intervenors. ECF Nos. 84, 83. As to the Owen Action, the Court denies as moot the Owen Plaintiffs’ Motion for Summary Judgment, ECF No. 43. An appropriate Order will accompany this Memorandum Opinion.
Daniel G. Jarcho, Daniel Carrigan, Craig Rust, McKenna Long & Aldridge LLP, Dennis Merrill Moore, National Railroad Passenger Corporation (Amtrak) Law Department, Washington, DC, for Defendant.
MEMORANDUM OPINION
RUDOLPH CONTRERAS, District Judge.
The City of New York brought this suit to seek a declaratory judgment that the National Railroad Passenger Corporation—better known as Amtrak—is liable for the rehabilitation of a bridge that crosses train tracks in the Bronx. The parties have filed cross-motions for summary judgment.
The City claims that an agreement contained in a 1906 deed, which transferred title to the land supporting the bridge from the City to a predecessor of Amtrak, now obligates Amtrak to maintain the bridge in perpetuity. The parties disagree about whether this agreement was an affirmative covenant running with the land or merely a contract. But however the agreement is characterized, it did not pass to Amtrak in the national rail reorganization that brought that railroad into being. Nor is Amtrak responsible for maintaining the bridge in the absence of any agreement. The court will therefore grant summary judgment to Amtrak on the issue of liability for bridge rehabilitation.
I. BACKGROUND
This case concerns the rehabilitation of a bridge that carries a public road over train tracks in the Bronx. The road was in use by 1849, running across land owned by the family of Robert Bartow. By 1900, a railroad crossed it at grade level. As the result of several condemnations and acquisitions, the Harlem River and Port Chester Railroad Company (the “railroad company“) owned those tracks and the land supporting them, along with a train station, while the City of New York owned the road on both sides of the tracks and other adjacent land. In 1906, the City conveyed some of its land to the railroad company “upon the express condition that the said Railroad Company, its successors, lessees and assigns ... perform” a number of “covenants and conditions,” including the following:
SECOND. The said railroad company shall at its own expense construct a bridge with the necessary abutments and approaches thereto, over the property of the railroad company, east of Bartow Station, the width of such bridge and approaches to be eighty feet.
SEVENTH. The said railroad company shall maintain and keep in repair at its own expense the bridges and abutments hereinbefore agreed to be constructed by it, except the pavement of such bridges.
FIFTEENTH. The said railroad company shall cause permanent rights of way or easements across its property ... at Bartow Station crossing of a width of eighty (80) feet ... to be conveyed by proper instruments in writing to the City of New York within ninety (90) days after the execution of this agreement.
Declaration of Daniel G. Jarcho (Feb. 28, 2012) (“Jarcho Decl.“), Ex. 10 (Deed from the City of New York to the Harlem River and Port Chester Railroad Company (June 30, 1906)) (“1906 Deed“), at 12-15. (A large part of this litigation concerns the present effect of the seventh paragraph, which the court will refer to as the “Maintenance and Repair Agreement.“) If the railroad company did not “fulfill each and every” of these “conditions and covenants,” the lands conveyed would “be forfeited and ... revert to the City of New York.” Id. at 15.
After building the bridge in question here—which the parties call the Shore Road Circle Bridge—the railroad company “grant[ed] and convey[ed] to the CITY OF NEW YORK, a permanent right of way or easement across its property at Bartow Station ... of a width of eighty (80) feet ... which said right[ ] of way or easement[ ]” was “limited for the purpose of the continued existence of a bridge carrying the public highway ... across the railroad tracks of said company.” Jarcho Decl., Ex. 13 (Easement from Harlem River and Port Chester Railroad Company to the City of New York (Aug. 19, 1909)), at 1. The easement accommodated a bridge “at such an elevation as to provide a clear headroom of eighteen (18) feet above the present elevation of the top of the rails of the railroad tracks.” Id. It was “conveyed
In 1927, the Harlem River and Port Chester Railroad Company merged into the New York, New Haven and Hartford Railroad, which declared bankruptcy and had its assets sold to the Penn Central Transportation Company in 1968. As the D.C. Circuit has explained:
By 1971, Penn Central had filed for bankruptcy. It was not alone. By the early 1970s, the railroads in the northeast were failing at such a rapid rate that Congress stepped in to resolve the regional rail crisis. Congress passed the Regional Rail Reorganization Act of 1973,
Pub.L. No. 93-236 , 87 Stat. 985 (1974) (codified as amended at45 U.S.C. § 701 et seq. (1994)) (the “Rail Act“), which allowed the railroads to reorganize into a single entity, and [the Consolidated Rail Corporation, better known as] Conrail was designed to salvage the viable rail properties, leaving much of the debt behind in bankruptcy and beginning with a “clean slate.” ...The Rail Act created the United States Railway Association, see
45 U.S.C. § 711(a) , a non-profit corporation, which in turn prepared a Final System Plan ... which designated how rail properties held by the bankrupt railroads would be distributed, see45 U.S.C. § 716 . The Rail Act also created Conrail, see45 U.S.C. § 741(a) , and mandated that rail properties designated in the Final System Plan be conveyed to Conrail, see45 U.S.C. § 743(b) .
City of Philadelphia v. Consol. Rail Corp., 222 F.3d 990, 991-92 (D.C.Cir.2000) (abbreviation expanded). Those properties “were to be ‘conveyed ... free and clear of any liens or encumbrances.‘” Consol. Rail Corp. v. Ray ex rel. Boyd, 632 F.3d 1279, 1281 (D.C.Cir.2011) (quoting
The Rail Act created a Special Court to order the conveyance and “resolve disputes related to the reorganization.” Id. at 1280.1 The Special Court issued a conveyance order, see City of Philadelphia, 222 F.3d at 992 (citing
In 1997, the City of New York hired an engineering firm to begin preparing to rehabilitate the Shore Road Circle Bridge. In 2003, Amtrak and the City signed an agreement under which Amtrak would “make necessary changes in its railroad facilities” so that the bridge project could proceed. Jarcho Decl., Ex. 41 (Contract between Amtrak and the City of New York (Dec. 22, 2003)), at 3. Those necessary changes included the removal of structures attached to the underside of the bridge, which provided electricity to Amtrak‘s trains and insulated the bridge from that electrical current. In 2004 and 2005, pursuant to the agreement, Amtrak built poles to which its electrical equipment could be attached; the equipment was removed from the bridge and attached to the poles several years later. Decl. of John S. Ramo (Feb., 27, 2012), at ¶ 9. In 2007, the City awarded a contract for the replacement of the bridge.
In 2010, the City brought this suit in the Southern District of New York, alleging that Amtrak was liable under the 1906 Deed for the cost of the bridge rehabilitation. Amtrak‘s primary defense was that the deeds and bills of sale that transferred the real property supporting the bridge and the contracts associated with it did not convey that liability to Amtrak. Because the resolution of that dispute would require the interpretation of the conveyance orders issued pursuant to the Rail Act, the district court found that the Act gave this court—sitting as the Special Court—exclusive jurisdiction over the case, and accordingly transferred it here. Order (June 13, 2011), at 6. The parties have filed cross-motions for summary judgment. The bridge rehabilitation project was ongoing when those motions became ripe.
II. LEGAL STANDARD
Summary judgment may be granted when “the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.”
The principal purpose of summary judgment is to streamline litigation by disposing of factually unsupported claims or defenses and determining whether there is a genuine need for trial. Celotex Corp. v. Catrett, 477 U.S. 317, 323-24, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986). The moving party bears the initial responsibility of identifying those portions of the record which demonstrate the absence of any genuine issue of material fact. Id. at 323, 106 S.Ct. 2548;
On a motion for summary judgment, the court must “eschew making credibility determinations or weighing the evidence,” Czekalski v. Peters, 475 F.3d 360, 363 (D.C.Cir.2007), and all underlying facts and inferences must be analyzed in the light most favorable to the non-moving party, Anderson, 477 U.S. at 255, 106 S.Ct. 2505. Nevertheless, conclusory assertions offered without any evidentiary support do not establish a genuine issue for trial. Greene v. Dalton, 164 F.3d 671, 675 (D.C.Cir.1999).
III. ANALYSIS
A. Liability for Bridge Replacement
The City of New York seeks to hold Amtrak liable for the cost of replacing the Shore Road Circle Bridge. The City‘s primary argument is that the Maintenance and Repair Agreement included in the 1906 Deed is an affirmative covenant that runs with the land, and that it obligates Amtrak to “maintain and keep [the bridge] in repair at its own expense.” 1906 Deed at 13. Amtrak, in turn, argues that the agreement was simply a contract that was not transferred in the rail reorganization. The court need not resolve that dispute, because whether the agreement was a contract or an affirmative covenant, it does not presently obligate Amtrak.
i. Contract
As a general matter, “the [railroad] bankruptcies and the [Regional Rail] Reorganization Act” “absolved [Amtrak] of contractual liability” arising from agreements made by its predecessors. City of Philadelphia, 222 F.3d at 994. Amtrak only assumed the contracts that Conrail expressly assigned to it, and Conrail only received from Penn Central contracts that were “used or useful in the provision of rail services“—and not all of those. Bill of Sale at E1; see also Erie Dock Co., 688 F.Supp. at 1557. Even useful contracts were not assigned to Conrail if they were “construction agreements,” “demolition agreements” or “agreements for rehabilitation or modernization of rail properties” that would require Conrail “to complete said construction .... demolition .... [or] rehabilitation or modernization subsequent to [the] conveyance date, without complete financial remuneration.” Bill of Sale at E2. Amtrak argues that the Maintenance and Repair Agreement was a contract that was not assigned to Conrail, because it was not “used or useful in the provision of rail services” or else required performance “subsequent to [the] conveyance date, without complete financial remuneration.”
The City of New York argues vigorously that the agreement is not a contract—or not exclusively a contract—but rather, at least in part, an affirmative covenant running with the land. The City is so certain that the agreement is a running covenant that it does not take the trouble to deny that if the agreement is a only contract then Amtrak did not assume it. The City has conceded that point, and so the court proceeds to consider what follows from the assumption that the Maintenance and Repair Agreement is indeed a running covenant.
ii. Covenant
The land that Amtrak received in the rail reorganization was, as the Rail Act required, “conveyed free and clear of any liens or encumbrances.”
At the time of FSIA‘s adoption in 1976, a “lien” was defined as “[a] charge or security or incumbrance upon property.” BLACK‘S LAW DICTIONARY 1072 (4th ed.1951). “Incumbrance,” in turn, was
defined as “[a]ny right to, or interest in, land which may subsist in another to the diminution of its value....” Id. at 908.
Ray, 632 F.3d at 1281 (quoting Permanent Mission of India to the United Nations v. City of New York, 551 U.S. 193, 198, 127 S.Ct. 2352, 168 L.Ed.2d 85 (2007)) (alterations in Ray). “Because the Rail Act was passed just three years before the FSIA,” the D.C. Circuit “see[s] no reason to believe ‘liens or encumbrances’ should be understood any differently” when used in the Rail Act than when those terms appear in the Foreign Sovereign Immunities Act. Id.
Amtrak argues that any affirmative covenant to repair and maintain the Shore Road Circle Bridge was a “lien or encumbrance” within the meaning of the Rail Act, because such a covenant would necessarily diminish the value of the land that was subject to it.2 The City does not precisely disagree. Instead the City argues that Congress was legislating pursuant to its bankruptcy power when it passed the Rail Act and that, because restrictions of record running with the land are generally not extinguished in bankruptcy, the court should conclude that the Maintenance and Repair Agreement survived the conveyance “free and clear of any liens or encumbrances.”
One district judge has accepted this argument. In City of New York v. National Railroad Passenger Corporation, as here, 2008 WL 5169636 (E.D.N.Y. Dec. 09, 2008). The City sought to recover for the cost of relocating Amtrak‘s electrical equipment from a bridge. The City argued that it held an easement allowing it to maintain the bridge, and that Amtrak‘s electrical equipment had impermissibly interfered with that easement. Amtrak, in turn, argued that the easement had been extinguished by the Rail Act. The district court “analogize[d] to the principles of bankruptcy law to interpret the intentions of Congress” in passing the Rail Act. Id. at *8. Because “the Bankruptcy Code does not,” in most cases, “allow the Bankruptcy Court to authorize a sale ... ‘free and clear’ of an easement,” the court concluded that “the easement” at issue there “survived the Rail Act.” Id.
The Ray court explicitly rejected this reasoning. In Ray, Conrail argued that the D.C. Circuit should interpret
An affirmative covenant requiring bridge maintenance is clearly an encumbrance as that term is defined by Ray, because it is a “right to, or interest in, land which may subsist in another to the diminution of [the land‘s] value.” Id. at 1281 (internal quotation marks omitted). If Amtrak were bound by such a covenant, that covenant would give the City the right to have the bridge maintained at no cost to itself. The burden of that maintenance obligation would diminish the value of the land with which it ran. Such a covenant would therefore be an encumbrance within the meaning of
The City seems to make a related but subtly different argument: that Congress enacted the Rail Act pursuant to its bankruptcy power, and that the bankruptcy power does not extend to the extinguishment of affirmative covenants running with the land. The first half of that proposition provides less than the whole story: both the Supreme Court and the Special Court have described the Rail Act as drawing on both Congress‘s bankruptcy power and the eminent domain authority derived from its commerce power. See Regional Rail Reorganization Act Cases, 419 U.S. 102, 151, 153, 95 S.Ct. 335, 42 L.Ed.2d 320 (1974) (rejecting argument that “the Rail Act w[as] merely an eminent domain statute” and explaining that Congress also “intended to legislate pursuant to the bankruptcy power“); Norwich & Worcester R.R. Co. v. United States, 408 F.Supp. 1398, 1404 (Reg‘l Rail Reorg.Ct.1976) (Friendly, J.) (explaining that the Rail Act “drew both on the bankruptcy power and on the authority of Congress to exercise eminent domain under the commerce power,” and that “this latter authority ... was the basis for holding that any inadequacies in the compensation afforded under [the Rail Act] could be recovered in an action in the Court of Claims under the Tucker Act“). The second half of the City‘s argument is essentially an assertion that, as the Ray court has interpreted it,
In sum, the parties agree that the Maintenance and Repair Agreement is either a contract or an affirmative covenant—or, perhaps, a hybrid of the two. If it is a contract, that contract was (as the City concedes) not “used or useful in the provision of rail services” or else required performance “subsequent to [the] conveyance date without complete financial remuneration” and so did not pass to Amtrak. See Bill of Sale at E1-E2. If, on the other hand, the agreement is an affirmative covenant, then it is an encumbrance within the meaning of
iii. Ownership
The City offers another theory of Amtrak‘s liability: that Amtrak owns the bridge and is therefore obligated to maintain it, independent of any contract or covenant. This argument is hard to square with the heavy emphasis that the City places on the Maintenance and Repair Agreement. If the City does not own the bridge and never has, and ownership carries with it the obligation of maintenance and repair, then what purpose did the Maintenance and Repair Agreement ever serve? There is no good answer to that question, which suggests that the original parties believed that, in the absence of an agreement, the City would bear the burden of bridge maintenance and repair.
If that is what the parties believed, they were right. Under New York law, “[t]he grantee of an easement to use a bridge is bound to keep it in repair,” Schenectady Ry. v. Greene, 227 A.D. 11, 15, 236 N.Y.S. 477 (3d Dep‘t 1929), aff‘d, 257 N.Y. 610, 178 N.E. 816 (1931), because “the duty to maintain and repair structures or facilities existing under an easement rests on the dominant, not the servient, owner,” Sutera v. Go Jokir, Inc., 86 F.3d 298, 302 (2d Cir.1996) (applying N.Y. law). “This rule is invoked in disputes between servient and dominant owners to decide which party is required to make repairs.” Id.
Because the easement in question here benefits the City of New York and burdens Amtrak‘s land, the City is the dominant owner and, absent any effectual agreement to the contrary, must repair the bridge that supports its easement.
In the early twentieth century, a New York court reached that conclusion in circumstances quite similar to those presented here. An earlier case had addressed the question of whether a railroad owed taxes on highway bridges that it had built; that answer depended on whether the bridges were its property. See People ex rel. N.Y. Cent. & Hudson River R.R. Co. v. Purdy, 149 N.Y.S. 315 (N.Y.Sup.Ct.1914). In Purdy, the City of New York owned the fee of the land over which bridges carried the public highway, and the railroad held an easement allowing train tracks to run beneath those bridges. Id. at 317. The railroad company had paid most of the bridge construction costs. Id. at 316-17. The Purdy court noted that, as a general matter, “structures ... erected by persons not the owners of the land ... become part of the realty, and as such the property of the landowner” but not if “the fee is subject to certain easements, and the structures ... are appurtenant to said easements and not to the fee.” Id. at 317. Ownership of the bridges, therefore, depended on “whether or not the bridges are appurtenant to the easement of the railroad.” Id. The fact that the railroad company had paid most of the bridge construction costs was “not sufficient to give it title to the bridges.” Id. at 318.
In analyzing the question of appurtenance, the Purdy court emphasized that the railroad had not made any use of the bridges, except to attach railroad signals to them. Id.; see also id. (“Were [the bridges] removed by the city, the operation of the railroad would in no way be impaired.“). By contrast, the bridges “form[ed] an essential part of the [City‘s] street system, and were evidently constructed to give effect to the purpose for which” the City acquired the land supporting the bridges from the railroad company, id., that is, to allow the highway to cross the train tracks. The court therefore concluded that the City owned the bridges, because they were not appurtenant to the railroad‘s easement. Id. at 319.
Ward v. Erie Railroad Company, which was decided several months after Purdy, presented the same question as this case: whether a city or a railroad company was
That is precisely the situation here. Nonetheless, the City argues that the language of its easement, which was expressly preserved in the Rail Act conveyance,3 proves that Amtrak owns the bridge, because the City could not have a right of way to cross a bridge that it owned. But the language of the easement clearly encompasses both the bridge structure and the right of way. The City received “a permanent right of way or easement ... for the purpose of the continued existence of a bridge carrying the public highway ... across the railroad tracks” owned by the original railroad company. Jarcho Decl., Ex. 13 (Easement from Harlem River and Port Chester Railroad Company to the City of New York (Aug. 19, 1909)), at 1. The physical description emphasized that the “easement or right of way” was “for the purpose of carrying a street or highway across the tracks ... by means of a bridge or viaduct.” Id. An easement “for the purpose of the continued existence of a bridge” or, alternatively, “for the purpose of carrying a street or highway across the tracks ... by means of a bridge” plainly allows a party to maintain its bridge upon another‘s land. It does not, as the City argues, merely convey the right to cross the other‘s bridge.
For that reason, and in accordance with Ward and Purdy, the City of New York is responsible for the cost of rehabilitating the Shore Road Circle Bridge.
B. Liability for Electrical Work
Although Amtrak is not liable for the entire cost of rehabilitating the bridge, the City argues that Amtrak is nonetheless responsible for the cost of removing its electrical equipment from the bridge to allow that work to proceed. The City invokes New York‘s public utility rule, under which “public service corporations maintain their rights in the streets, subject to reasonable regulation and control, and are bound to relocate their structures at their own expense whenever the public health, safety or convenience requires the change to be made.” Transit Comm‘n v. Long Island R.R. Co., 253 N.Y. 345, 351, 171 N.E. 565 (N.Y.1930). The City argues that when Amtrak attached its electrical
i. Preemption
Amtrak‘s first argument is that, even if it would ordinarily be liable to the City under the public utility rule, that rule was preempted by the Rail Passenger Service Act, which provides that any “State or other law related to rates, routes or service does not apply to Amtrak in connection with rail passenger transportation,”
“Where, as in this case, Congress has superseded state [law] by statute, [a court‘s] task is to ‘identify the domain expressly pre-empted.‘” Dan‘s City Used Cars, Inc. v. Pelkey, — U.S. —, 133 S.Ct. 1769, 1778, 185 L.Ed.2d 909 (2013) (quoting Lorillard Tobacco Co. v. Reilly, 533 U.S. 525, 541, 121 S.Ct. 2404, 150 L.Ed.2d 532 (2001)). “To do so, [a court must] focus first on the statutory language, ‘which necessarily contains the best evidence of Congress’ pre-emptive intent.‘” Id. (quoting CSX Transp., Inc. v. Easterwood, 507 U.S. 658, 664, 113 S.Ct. 1732, 123 L.Ed.2d 387 (1993)). Few courts have interpreted the preemption provision in the Rail Passenger Service Act, but that provision bears a striking similarity to the Federal Aviation Administration Authorization Act of 1994 (“FAAA“), see
Like the Rail Passenger Service Act, the Airline Deregulation Act “prohibit[s] the States from enforcing any law ‘relating to rates, routes, or services’ of any air carrier,” Morales, 504 U.S. at 378-79, 112 S.Ct. 2031 (quoting
The question here is whether a common law rule requiring Amtrak to remove electrical facilities attached to a public bridge is “related to ... routes,” and whether the City seeks to apply that rule “to Amtrak in connection with rail passenger transportation” within the meaning of the Rail Passenger Service Act.
And even if the public utility rule were “related to ... routes,” that alone would not establish preemption. For purposes of preemption under the Rail Passenger Service Act, a state law must be both “related to rates, routes or service” and “appl[ied] to Amtrak in connection with rail passenger transportation.”
One district court has applied a broader interpretation of
Application of the public utility rule would neither alter the course that Amtrak‘s trains travel nor subject the railroad company to the vagaries of varied local ordinances. The rule would impose a cost on Amtrak, but that is not enough to make a law “related to ... routes,” much less “appl[ied] to Amtrak in connection with rail passenger transportation“—and Amtrak could have avoided that cost by placing its electrical equipment on poles (where the equipment is currently located) rather than affixing that equipment to the underside of the City‘s bridge. The court therefore concludes that the public utility rule was not preempted by the Rail Passenger Service Act,
ii. Waiver
Amtrak next argues that the City waived any claims under the public utility rule when it signed the contract under which Amtrak removed the electrical facilities at the City‘s expense. That contract read, in relevant part, as follows:
The City agrees to reimburse [Amtrak] for the entire reasonable cost of any work performed....
The parties agree that the payments made or contract work performed pursuant to this agreement does not constitute release from liability, responsibility, or cost for site reconstruction, replacement, repair, improvement, maintenance or any work whatsoever. Each party shall retain its legal remedies to pursue reimbursement for work done pursuant to this agreement, and all statutory obligations, and in all related issues concerning responsibility for site reconstruction, replacement, repair, improvement, maintenance, or any other work whatsoever.
Jarcho Decl., Ex. 41 (Contract between Amtrak and the City of New York (Dec. 22, 2003)), at 3. Amtrak argues that the City agreed “to reimburse [Amtrak] for the entire reasonable cost of any work performed” and is bound to that promise. The City replies that it only did so with the understanding that “payments made ... pursuant to this agreement” would “not constitute release from liability,” and
The contract plainly supports the City‘s position, and “when parties set down their agreement in a clear, complete document, their writing should be enforced according to its terms.” NML Capital v. Rep. of Argentina, 17 N.Y.3d 250, 259, 928 N.Y.S.2d 666, 952 N.E.2d 482 (N.Y.2011) (internal quotation marks omitted). Amtrak argues that a second contract limited the City‘s right to recover, but the City explains that none of the work at issue here was performed pursuant to that second contract. Amtrak does not respond—and so concedes the point. Amtrak also points to the course of conduct between the parties, arguing that negotiations over the total cost of the work that Amtrak would perform are evidence that the City expected to pay for it. But such extrinsic evidence is inadmissible where, as here, the written contract is unambiguous. See, e.g., R/S Assocs. v. N.Y. Job Dev. Auth., 98 N.Y.2d 29, 33, 744 N.Y.S.2d 358, 771 N.E.2d 240 (N.Y.2002). The City explicitly reserved “its legal remedies to pursue reimbursement for work done pursuant to” the contract that Amtrak claims waived those remedies. It is therefore free to pursue them here.
iii. Emergency Assistance
“New York has adopted the ‘emergency assistance doctrine’ set forth in
A person who has performed the duty of another by supplying things or services, although acting without the other‘s knowledge or consent, is entitled to restitution from the other if
(a) he acted unofficiously and with intent to charge therefor, and
(b) the things or services supplied were immediately necessary to satisfy the requirements of public decency, health, or safety.
RESTATEMENT (FIRST) OF RESTITUTION § 115. “Historically, this rule has had various applications, including burial of the dead and removing an obstruction from or making repairs upon a public road, which had become imminently dangerous to members of the traveling public.” Judge Rotenberg Educ. Ctr. Inc. v. Blass, 882 F.Supp.2d 371, 382 (E.D.N.Y.2012); see also RESTATEMENT (FIRST) OF RESTITUTION § 115, cmnt. b (same). The City argues that the public utility rule placed Amtrak under a duty to remove its electrical equipment from the bridge, that the City paid Amtrak to do so with the intent to recoup that payment, and that the removal of the electrical equipment was immediately necessary to preserve the public safety.
a. Duty
Amtrak disputes that it had any duty to remove its electrical equipment from the bridge. It argues that the public utility rule did not apply because the electrical equipment was located on Amtrak‘s own and not the City‘s property. Amtrak‘s theory is that the equipment occupied Amtrak‘s airspace and merely abutted the City‘s bridge. But that is not so: the equipment was attached to the bridge, as Amtrak concedes elsewhere. The court therefore moves on to the question of whether the removal of that equipment was immediately necessary.
b. Immediate Necessity
Amtrak next argues that the rehabilitation of the bridge (and the concomitant removal of Amtrak‘s equipment) was not immediately necessary to preserve the public safety. Amtrak points to the fact
“Cases applying § 115 illustrate that the nature of the danger must be acute and severe, not merely serious or problematic.” Chase Manhattan Bank, N.A. v. T & N plc, 1996 WL 603934, at *9 (S.D.N.Y. Oct. 22, 1996), aff‘d, 1998 WL 634218, at *3 (2d Cir. Mar. 13, 1998). “The rule ... is not applicable unless there is an immediate necessity for action ....” RESTATEMENT (FIRST) OF RESTITUTION § 115, cmnt. a. In a true emergency, “it is desirable to encourage persons to interfere with the affairs of others.” Id. § 112, cmnt. b (discussing the general rule regarding benefits voluntarily conferred). At most other times, it is not. Whether a danger is sufficiently acute and severe to come within the scope of the emergency assistance doctrine is sometimes a contested question of fact. See, e.g., Chase Manhattan, 905 F.Supp. at 123 (finding that whether asbestos remediation was “immediately necessary is a question of fact very much disputed by the parties” and collecting cases in which the issue of immediate necessity precluded summary judgment); Nat‘l Railroad Passenger Corp. v. New York City Housing Auth., 819 F.Supp. 1271, 1280 (S.D.N.Y.1993) (“[T]he question of whether the removal was immediately necessary to protect the public is one fact which precludes summary judgment at this point.“). But here, it is obvious that the City had ample time to seek a declaratory judgment that Amtrak was obligated to remove its electrical equipment from the bridge. The City began planning for the rehabilitation in 1997 and signed its first agreement with Amtrak in 2003. The electrical equipment was not removed until several years later. Because the City could have sought a judicial declaration of rights and obligations without substantially delaying its rehabilitation project, it should have done so: in these circumstances, no reasonable jury could find that the danger presented by the ongoing bridge decay was sufficiently acute and severe to justify recovery under the emergency assistance doctrine. See, e.g., Chase Manhattan Bank, 1996 WL 603934, at *10 (finding that asbestos abatement program was not “immediately necessary” under § 115 where plaintiff was “aware of the hazard ... for many years,” and concluding that the plaintiff‘s “own delay” was, among other factors, “fatal to its claim for restitution” (citing Corp. of Mercer Univ. v. Nat‘l Gypsum Co., 1986 WL 12447, at *8 (M.D.Ga. Mar. 9, 1986) (no “immediate necessity” where plaintiff delayed over a year))).
iv. Indemnification
The City also argues that it can recover from Amtrak under a theory of indemnification. New York law recognizes “that ‘[a] person who, in whole or in part, has discharged a duty which is owed by him but which as between himself and another should have been discharged by the other, is entitled to indemnity.‘” McDermott v. City of New York, 50 N.Y.2d 211, 428 N.Y.S.2d 643, 406 N.E.2d 460, 462 (N.Y.1980) (quoting RESTATEMENT (FIRST) OF RESTITUTION § 76) (emphasis added). “In indemnity ... a party held legally liable to plaintiff shifts the entire loss to another.” Mas v. Two Bridges Assocs., 75 N.Y.2d 680, 555 N.Y.S.2d 669, 554 N.E.2d 1257, 1262 (N.Y.1990).
The City cites City of New York v. Lead Industries Association, Inc., 222 A.D.2d 119, 644 N.Y.S.2d 919 (N.Y.App.1996), in which the Appellate Division of the New York Supreme Court said that “[a]n implied indemnity action is based upon the law‘s notion of what is fair and proper between the parties and its purpose is equitable distribution of the loss.” Id. at 128, 644 N.Y.S.2d 919. Despite the breadth of that statement, the facts of the case fit comfortably within the indemnification action as the New York Court of Appeals has defined it. Lead Industries concerned a number of City-owned buildings in which lead paint had been applied. The City, as owner of the buildings, owed its tenants a duty to abate the hazard—and the paint manufacturer allegedly owed those same tenants damages for exposing them to an unreasonably dangerous product which (it was alleged) the manufacturer had fraudulently misrepresented. Id. at 122, 644 N.Y.S.2d 919. As the court explained, “[t]he gravamen of an action for indemnity is that both parties, indemnitor and indemnitee, are subject to a duty to a third person under such circumstances that one of them, as between themselves, should perform it rather than the other.” Id. at 125, 644 N.Y.S.2d 919. The City‘s theory was that both it and the paint manufacturer had a duty to the tenants arising from the introduction of lead-based paint into their living residences, and so it would pay to remove the hazard and then sue the manufacturer for indemnification.
Here, by contrast, the City alleges that Amtrak owed the City a duty to remove its electrical equipment from the bridge (which the City owned) and that the City owed the public a duty to keep the bridge in good repair. The City does not argue that, in paying for the removal of the electrical equipment, the City was performing its duty, but rather that it was performing Amtrak‘s duty to it. That does not amount to a claim for indemnification, and so the court will grant summary judgment to Amtrak.
IV. CONCLUSION
For the reasons discussed above, the court will grant summary judgment to Amtrak on all claims.
RUDOLPH CONTRERAS
UNITED STATES DISTRICT JUDGE