CITY OF BENKELMAN, NEBRASKA, A Political Subdivision, Plaintiff-Appellant v. BASELINE ENGINEERING CORPORATION, A Colorado Corporation, Defendant-Appellee Layne Christensen Company, a Delaware Corporation, Defendant
No. 16-1949
United States Court of Appeals, Eighth Circuit.
Submitted: August 1, 2017. Filed: August 11, 2017
867 F.3d 875
Randall L. Goyette, BAYLOR & EVNEN, Lincoln, NE, Linwood Tyrone Holt, Kevin D. Poyner, Kevin Patrick Walsh, THE HOLT GROUP, Denver, CO, for Defendant-Appellee.
Before RILEY, BEAM, and SHEPHERD, Circuit Judges.
SHEPHERD, Circuit Judge.
A rural Nebraska community seeks federal review of its multi-million dollar claims against a Colorado corporation. A United States District Court in Nebraska determined that it lacked jurisdiction over the claims and issued a final judgment1 ordering the parties to proceed to arbitration in Colorado. With jurisdiction under
I.
The City of Benkelman is a community of less than one thousand residents located in Dundy County, Nebraska. In 2005, the state health and human services department ordered the City to address the excessive amounts of uranium, arsenic, and other contaminants in the City‘s drinking water supply. The City subsequently contracted with Baseline Engineering Corporation, a Colorado organization, to assist with the permitting, design, and construc
The project began in July 2009 and the plant was operating by May 2012. In June 2012, however, laboratory tests of treated water samples showed that the uranium levels still did not comply with federal drinking water standards. Around five months later, the state denied final approval of the plant for failure to effectively treat the City‘s water supply.
The City sued Baseline2 in federal court in Nebraska, alleging breach of contract, negligence and professional malpractice, fraud, and negligent misrepresentation. Seeking damages in excess of $5.5 million, the complaint averred that Baseline failed to properly design the treatment plant, misrepresented itself as a water engineering expert, and gave false information about how to bring the City‘s water supply into compliance with state and federal laws.
Baseline moved to dismiss the complaint. Citing generally
The City opposed Baseline‘s motion, arguing that the July 2009 Contract does not control because it was superseded by a second contract that the parties signed on or slightly before August 27, 20094 (the “August EJCDC Agreement“). The August EJCDC Agreement, comprised of thirteen pages and ten exhibits, is a standard form contract prepared by the Engineers Joint Contract Documents Committee (the “EJCDC“). The City claims that, because the treatment plant was funded in part by USDA-RD, the parties were required to execute the EJCDC agreement and have it approved by USDA-RD. In
The August EJCDC Agreement has its own arbitration provision, although the provision is not mandatory and is triggered only if a dispute survives the parties’ good faith negotiation and mediation. In such an event the August EJCDC Agreement states that “either party may seek to have the [d]ispute resolved by a court of competent jurisdiction.” Alternatively, if less than $200,000 is in controversy, the dispute may be resolved by a method mutually agreed upon by the parties, “including but not limited to arbitration.”
In addition to conflicting arbitration and forum selection clauses, the July and August contracts contain the following terms relevant to Baseline‘s motion to dismiss:
(1) Incorporation by reference. Though the August EJCDC Agreement was signed around a month after the July 2009 Contract, it is twice incorporated by reference as “Exhibit B” to the July 2009 Contract. First, page 1 of the July 2009 Contract contains a box titled “Job Description” followed by an instruction to “[s]ee Exhibit B hereto—for accompanying EJCDC agreement.” Second, a provision on page 3 titled “Entire Contract” states, “Exhibits A and B hereto are incorporated into this Agreement as fully set forth herein.”
(2) Choice-of-law. The July 2009 Contract contains a choice-of-law provision stating that the parties’ agreement “shall be governed by the laws of the State of Colorado.” Under the August EJCDC Agreement, however, “the law of the state in which the Project is located“—Nebraska—controls.
(3) Merger clauses. Each contract purports to represent the entire agreement between the parties and to trump any prior or inconsistent agreements. The July 2009 Contract states:
This Agreement and the documents set forth in Exhibits A and B hereto shall supersede any other contract between [the City] and [Baseline], relating to the subject matter thereof. This is a fully integrated Contract. Any previous statements, representations, agreements, negotiations or discussions are null and void, and are fully merged herein. In case of a conflict or inconsistency between this Agreement and any other contract documents, this Agreement shall control. [Baseline] makes no promises or agreements written or oral except for the provisions herein set forth.
The August EJCDC Agreement likewise states:
This Agreement (consisting of pages 1 to 13, inclusive, together with the exhibits identified above) constitutes the entire agreement between [the City] and [Baseline] for the Project and supersedes all prior written or oral understandings.
In considering Baseline‘s motion to dismiss, the district court first determined that, although the motion cited only generally Rule 12(b), it should be construed as a
Next, applying
The district court then considered which contract governs the parties’ dispute. Applying state-law principles of contract interpretation, the court concluded that “[t]he contracts in this case must be construed as one because they involve the same parties and same transaction, and because the July 2009 Contract expressly states that it incorporates the EJCDC Agreement into it as ‘Exhibit B.‘” The court noted, however, that construing the two documents as one contract brings to light the inconsistencies between the various provisions. Citing Colorado and Nebraska law,5 the court concluded that (1) the inconsistent provisions render the contract ambiguous and (2) extrinsic evidence may therefore be considered in order to discern the parties’ intent.
The only extrinsic evidence was presented for the first time with Baseline‘s reply brief supporting the motion to dismiss. The affidavit of Baseline President John McLain and attachment revealed that in June 2011—two years into the project—the parties executed three orders expanding their initial agreement to include additional engineering services (the “2011 Change Orders“). Each order (1) specifically references and quotes the “Additional Work” clause set forth in the July 2009 Contract and (2) states that “[a]ll [a]dditional [w]ork will be performed under and considered an extension of the above mentioned Agreement.” The district court held that the 2011 Change Orders are extrinsic evidence indicating that the parties intended “that the July 2009 Contract remain operative, controlling, and not superseded by the attached EJCDC Agreement.”
Turning to the July 2009 Contract, the court looked to the provision stating: “In case of a conflict or inconsistency between this Agreement and any other contract documents, this Agreement shall control.” (emphasis added). Thus the court concluded that “the July 2009 Contract ‘controls’ the conflicting provisions regarding applicable law and arbitration, making Colorado law applicable and requiring the parties to submit to binding arbitration in Colorado, to be conducted in the fashion described in the July 2009 Contract.” The court therefore granted Baseline‘s
II.
“We review de novo the grant of a motion to dismiss for lack of subject matter jurisdiction under
A.
The City argues that the motion cannot be construed as a challenge to the district court‘s subject matter jurisdiction under
We first consider the City‘s proposal to treat the motion as a motion to dismiss for improper venue under
But the City overlooks more recent Supreme Court precedent that forecloses its
We next consider the City‘s assertion that the district court erred by analyzing the motion under
Our decision is informed by the Supreme Court‘s reasoning in Atlantic Marine. 134 S. Ct. at 577. The Court concluded that federal venue laws, not forum-selection clauses, govern the propriety of venue under
We therefore hold that, contrary to Baseline‘s contention, the July 2009 Contract‘s arbitration clause does not strip the federal courts of jurisdiction. Accordingly, we agree with the City that the district court erred in construing the motion as a
We are thus left with two alternative classifications:
Baseline offers no reason why
Upon careful review of the relevant authority, we agree with the City that Baseline‘s motion is properly analyzed under either
We decline to press the matter by deciding between
B.
Had the district court analyzed Baseline‘s motion as one for summary judgment, we would review de novo the summary judgment analysis by deciding whether there are genuine issues of material fact and whether Baseline “is entitled to a judgment as a matter of law.” See
Although our rule is not absolute, we think it best in this case that summary judgment proceedings—which are inherently fact intensive and may lead the parties to trial—be held first in the district court. See CMH Homes, Inc. v. Goodner, 729 F.3d 832, 838 (8th Cir. 2013) (indicating that “the district court is better equipped to address [fact-intensive questions] in the first instance.“); United States v. Smith, 665 F.3d 951, 956 (8th Cir. 2011) (suggesting that “the district court [is] in a far better position to address” questions of fact than the appellate court). Accordingly, we reverse the order dismissing the City‘s claims against Baseline and remand for consideration of Baseline‘s motion under summary judgment standards.9
III.
For these reasons, the order of the district court is reversed and the case is remanded for further proceedings.
