UNITED STATES of America FOR the USE OF LIGHTING AND POWER SERVICES, INC., Plaintiff-Appellee,
v.
INTERFACE CONSTRUCTION CORPORATION, Defendant-Appellant.
United States Court of Appeals, Eighth Circuit.
*1152 Joshua Michael Avigad, Michael P. Stephens, St. Louis, MO, for appellant.
Joseph C. Blanner, St. Louis, MO, for appellee.
Before LOKEN, Chief Judge, COLLOTON, Circuit Judge, and PIERSOL,[*] District Judge.
LOKEN, Chief Judge.
When the government awarded Interface Construction Corp. ("Interface") a substantial contract to renovate portions of a federal building in St. Louis, the Miller Act required that Interface obtain a payment bond "for the protection of all persons supplying labor and material in carrying out the work provided for in the contract." 40 U.S.C. § 3131(b)(2). Interface subcontracted electrical work to Henderson Electrical Systems, LLC ("Henderson"), which in turn contracted with Lighting and Power Services, Inc. ("LPS"), to perform that work. When Interface and Henderson ignored LPS's repeated demands for unpaid progress payments, LPS stopped work and commenced this action against Interface, Henderson, and Western Surety Company, which had issued the payment bond to Interface, to recover the amount allegedly due LPS for unpaid labor and materials furnished for the Interface contract. Interface moved to compel arbitratiоn and now appeals the district court's[1] denial of that motion, an interlocutory appeal expressly authorized by the Federal Arbitration Act. See 9 U.S.C. § 16(a)(1)(B). We affirm.
I. Background
Interface presented its motion to compel arbitration as a Rule 12(b)(1) motion to dismiss on a limited record. Thus, our cupboard of facts is relatively bare. We know that, on April 12, 2006, Henderson submitted a proposal to Interface to provide *1153 electrical work for $237,760. The proposal stated, "This Proposal is to be made an Attachment to the Sub-contract." On April 17, LPS submitted to Hendersоn a proposal identical in all material respects to Henderson's proposal to Interface, including the contract amount and the statement, "This Proposal is to be made an Attachment to the Sub-contract." On April 21, Interface entered into the Prime Contract with the United States. That same day, Western Surety issued the Payment Bond required by the Miller Act in favor of "all persons having a direct relationship with [Interface] or a subcontractor of [Interface] for furnishing labor, material or both in the prosecution of the work рrovided for in the [Prime Contract]."
On April 27, Henderson gave LPS written notice "to proceed with providing labor for electrical work" on the project. On May 5, Interface and Henderson signed a Standard Form of Agreement Between Contractor and Subcontractor (AIA Document A401-1997) (the "Subcontract"), presumably for the work and on the terms set forth in Henderson's April 12 proposal (that portion of the Subcontract was not included in the record on appeal). So far as we know, the Subcontract did not refer to LPS or to its April 27 contraсt with Henderson to perform the electrical work, nor was LPS's April 17 proposal attached to the Subcontract.
LPS stopped work on the project after its demands for the unpaid balance of $98,516.04 in progress payments went unheeded. LPS then commenced this action, asserting a claim under the Miller Act to recover that amount under the Western Surety bond. The Miller Act creates a federal cause of action "separate and distinct from state law breach of contract actions." United States ex rel. Consol. Elec. & Mechs., Inc. v. Biggs Gen. Contracting, Inc.,
This appeal concerns only whether LPS must arbitrate its Miller Act claim. As arbitration is a matter of contract, "a party cannot be required to submit to arbitration any dispute which he has not agreed so to submit." AT & T Techs., Inc. v. Communications Workers of Am.,
LPS argues that it never agreed, and may not be compelled, to arbitrate its Miller Act claim. Interface argues that LPS is subject to the agreement to arbitrate in the Subcontract because the statement in its proposal to Henderson, "This Proposal is to be made an Attachment to *1154 the Sub-contract," incorporated the terms of Henderson's Subcontract with Interface by reference. Moreover, Interface arguеs, LPS is equitably estopped to claim benefits under the Subcontract and yet refuse to arbitrate in accordance with its terms. We review these issues de novo. See Nitro Distrib., Inc. v. Alticor, Inc.,
II. Who Decides Arbitrability?
Interface argues that the issue of arbitrability must be determined by an arbitrator, not by the court. We disagree. "A dispute ... over whеther the parties agreed to arbitrate [ ] will be resolved by the district court `[u]nless the parties clearly and unmistakably provide otherwise.'" Express Scripts, Inc. v. Aegon Direct Mktg. Servs., Inc.,
III. Arbitrability of the Miller Act Claim
Interface's principal argument turns on two premisesthat LPS's Complaint asserted a breach of contract claim against Interface, and that the only possible basis for this contract claim is the Subcontract. Therefore, Interface argues, LPS is bound by the arbitration provision in the Subcontract, either because LPS stated that its proposal was to be "made an Attachment to the Sub-contract," or by reason of equitable estoppel. We conclude that the first premise is faulty because LPS's Complaint asserted only a Miller Act claim to recover under the Western Surety bond. Interface asserts that "hidden within the Complaint [is] a breach of contract claim" against Interface. In support, it cites an allegation in paragraph 11: "Defendants Interface and Henderson breached their contract with [LPS]." But the Complaint did not allege a breach of contract cause of action. Rather, the paragraph alleging breach of a contractual obligation to LPS wаs an integral part of LPS's Miller Act claim for unpaid labor and material "provided for in a contract for which a payment bond is furnished." 40 U.S.C. § 3133(b)(1). Whether the alleged payment default was committed by Henderson or by Interface may become an issue, but it seems unlikely to affect whether LPS may recover under the Miller Act.
LPS as bond obligee could have asserted its Miller Act claim against only the bond issuer, Western Surety, without joining Interface and Henderson, as the obligee did in AgGrow Oils, L.L.C. v. Nat'l Union Fire Ins. Co. of Pittsburgh,
When LPS as bond obligee chose to join both obligor Interface and subcontractor Henderson as defendants in its Miller Act claim under the Western Surety bond, it could have joined state law breach of contract claims with its Miller Act claim. See United States ex rel. Consol. Elec. & Mechs., Inc. v. Biggs Gen. Contracting, Inc.,
Stripped of its faulty premise concerning the nature of LPS's claim, Interface's incorporation by reference argument must fail. Interface relies on LPS's proposal, stating that it should be "made an Attachment to the Sub-contract." Under Missouri law, merely saying a contract is "attached" is insufficient to incorporate an arbitration clause in that contract by reference. See Dunn Indus. Group, Inc. v. City of Sugar Creek,
*1156 Interface's equitable estoppel argument fares no better. Interface argues that it would be inequitable to allow LPS to pursue a breach of contract claim without enfоrcing the arbitration provision because the Subcontract is the only basis for a contract claim against Interface. The principle is soundunder Missouri law, "A party will not be allowed to assume the inconsistent position of affirming a contract in part by accеpting or claiming its benefits, and disaffirming it in part by repudiating or avoiding its obligations, or burdens." Dubail v. Med. West Bldg. Corp.,
For these reasons, we conclude that the district court correctly denied Interface's motion to compel arbitration of LPS's Miller Act claim.[5] Accordingly, the order of the district court is affirmed.
NOTES
Notes
[*] The HONORABLE LAWRENCE L. PIERSOL, United States District Judge for the District of South Dakota, sitting by designation.
[1] The HONORABLE E. RICHARD WEBBER, United States District Judge for the Eastern District of Missouri, affirming the Report and Recommendation of the HONORABLE DAVID D. NOCE, United States Magistrate Judge for the Eastern District of Missouri.
[2] As subcontractоrs may not place liens on government property, the Miller Act bond ensures full recovery of a subcontractor's out-of-pocket expenditures for labor and materials, regardless of the general contractor's fault.
[3] In that case, bond obligor Interface might well have sought to intervene to pursue contract issues such as arbitration. See United States ex rel. MPA Constr., Inc. v. XL Specialty Ins. Co.,
[4] Interface submitted by Supplemental Appendix an affidavit asserting that LPS during settlement negotiations confirmed that it is also seeking state law breach of contract relief. This affidavit was not part of the district court record and is not a proper part of the record on appeal. See F.R.A.P. 10(a). Accordingly, LPS's motion to strike the Supplemental Appendix is granted.
[5] Even when a claim or issue is not subject to an agreement to arbitrate, "the district court has discretion to stay third party litigation that involves common questions of fact that are within the scope of the arbitration agreement." AgGrow Oils,
This bill does not void subcontract provisions requiring arbitration or other alternative methods of resolving disputes. Such provisions would remain enforceable with a claimant's Miller Act rights preserved by a timely suit that can be stayed pending the outcome of the subcontract dispute resolution procedure. The bill respects the freedom of the parties to the subcontract to specify means to resolve their disputes and the exclusive jurisdiction of the district court to decide issues arising under the Miller Act.
H.R.Rep. No. 106-277(I), at 5 (1999). However, this issue was not raised in the district court.
