CGI FEDERAL INC., Plaintiff-Appellant v. UNITED STATES, Defendant-Appellee.
No. 2014-5143.
United States Court of Appeals, Federal Circuit.
March 10, 2015.
779 F.3d 1346
William Porter Rayel, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, DC, argued for defendant-appellee. Also represented by Joyce R. Branda, Robert E. Kirschman, Jr., Kirk Manhardt.
Michael J. Schaengold, Greenberg Traurig LLP, Washington, DC for amicus curiae. Also represented by Melissa Paige Prusock, Aaron S. Ralph.
Before MOORE, TARANTO, and CHEN, Circuit Judges.
MOORE, Circuit Judge.
In this pre-award bid protest appeal, CGI Federal Inc. challenges the payment terms of requests for quotes (“RFQs“) is-
BACKGROUND
In the contracts at issue, CMS uses contractors, such as CGI, to determine if Medicare claims were correctly paid. If the contractor identifies an overpayment, CMS sends a demand letter to the provider seeking repayment and pays the contractor a contingency fee. Pursuant to the original contracts from 2008, the contractors invoiced CMS for the contingency fee when the overpayment was collected from the provider, typically 41 days after the demand letter. In 2014, CMS issued new RFQs for these recovery services. The 2014 RFQs included additional payment terms requiring the contractors to wait to invoice CMS until a provider‘s challenge to the repayment request passed the second level of a five-level appeal process, which typically occurs somewhere between 120 and 420 days after the demand letter.
Five different contractors bid on the 2014 RFQs, but CGI did not. Instead, before bidding closed, CGI filed a timely pre-award protest at the Government Accountability Office (“GAO“) challenging the revised payment terms. While the GAO protest was pending, the bidding period closed. The GAO subsequently denied the protest. Three business days later, CGI filed a protest in the United States Court of Federal Claims. CGI and the government then filed cross-motions for judgment on the administrative record, and the government moved to dismiss for lack of standing. The Court of Federal Claims denied the government‘s motion to dismiss but granted its motion for judgment on the administrative record, holding that the modified payment terms do not violate statutory or regulatory provisions. CGI Fed. Inc. v. United States, No. 14-cv-00355-MCW, slip op. at 9-10, 18-21 (Fed. Cl. Aug. 15, 2014) (“Opinion and Order“). It also held that the payment terms do not unduly restrict competition. Id. at 22.
CGI appeals. We have jurisdiction under
DISCUSSION
I. Standing
Whether a party has standing is an issue of law that we review de novo. Am. Fed‘n of Gov‘t Emps. v. United States, 258 F.3d 1294, 1298 (Fed. Cir. 2001) (“AFGE“). To have standing to bring a bid protest in the Court of Federal Claims, a plaintiff must be an “interested party.”
A. Prospective Bidder
CGI never submitted a bid in response to the 2014 RFQs and thus is not an actual bidder. CGI must therefore show that it was a prospective bidder at the time it filed its protest in the Court of Federal Claims. We hold that it has made such a showing.
The parties primarily debate the implications of four cases in which we have opined on the meaning of “prospective bidder.” A brief description of each case is helpful. In MCI Telecommunications Corp. v. United States, we considered the meaning of “prospective bidder” within the now-defunct Brooks Act,
One year later in Federal Data Corp. v. United States, we held that Federal Data was not a “prospective bidder” within the meaning of the Brooks Act because it withdrew from the bidding process prior to filing a protest. 911 F.2d 699, 702-05 (Fed. Cir. 1990). “Federal Data knowingly took itself out of the bidding prior to filing its amended protest,” and therefore “relinquished any chance of receiving the contract by that action.” Id. at 703-04. We noted that Federal Data “could have continued to compete for the contract award . . . and could have utilized the protest procedures available to an interested party to correct any deficiencies it perceived in the procurement process,” but did not. Id. at 705. We stated that a “prospective bidder” “does not include one who only intends to bid in the event of a reprocurement.” Id. at 704.
We considered the meaning of “prospective bidder” in the context of an interested party under
Finally, in Digitalis, we held that a protestor that failed to submit the required statement of capability to the agency in the allotted time period and filed its Court of Federal Claims protest more than two months after the contract was awarded was not a prospective bidder. 664 F.3d at 1383-86. Citing to both MCI and Rex, we again noted that “the opportunity to become a prospective bidder ends when the proposal period ends.” Id. at 1385.
While none of these cases is directly on point, together they are instructive. In each case, the party failed to obtain prospective bidder status because it did not diligently pursue its protest rights, e.g., by failing to file any protest until well after a contract award (MCI, Digitalis), affirmatively abandoning any interest in the contract (Federal Data), or delaying months after both denial of a timely protest and the award of a contract before filing the protest at issue (Rex).
The same cannot be said of CGI, which diligently and continuously pursued its rights in the GAO and then, immediately upon dismissal by the GAO, in the Court of Federal Claims.1 Neither party disputes
While we recognize that the government has been guided in its view by language in Rex, we agree with the Court of Federal Claims, which concluded that CGI‘s position is readily distinguishable from the protestor in Rex. In Rex, the protestor waited nearly three months after the agency denied its initial protest before filing the protest at issue and, in the interim, the agency awarded the contract to another bidder. Rex, 448 F.3d at 1307. Here, CGI filed its Court of Federal Claims protest within three business days of receiving its dismissal from the GAO and before CMS had awarded the contract.3 CGI, having secured prospective bidder status by filing its timely GAO protest, did not lose it in the three business days it took to file in the Court of Federal Claims.4 We acknowledge that Rex explained that the
Were we to adopt the government‘s argument that CGI is not a prospective bidder, it would create a chasm between an actual bidder and a prospective bidder in terms of the review rights accorded to each. For example, an actual bidder would undisputedly have the right to serially file a protest in the GAO and then, if the GAO protest were denied, in the Court of Federal Claims. If we accepted the government‘s position, this sequence of redress would not be available to a prospective bidder. It would be virtually impossible to file a timely GAO protest, wait for a GAO decision, and then file a protest in the Court of Federal Claims prior to the close of bidding. By the time the GAO protest concluded, bidding would almost certainly be closed. Oral Argument 30:30-31:15. And the two cannot proceed simultaneously.
CGI was a prospective bidder when it promptly initiated and diligently pressed its protest in the GAO forum, which Congress has encouraged protestors to use before suing in court. Unsuccessful in the GAO, it immediately filed for relief in court. We do not think that Congress meant for a protestor in CGI‘s position to lose its entitlement to sue just because delays engendered by the GAO adjudicatory process pushed completion past the closing date for bid submissions. Concluding, as we do, that CGI filed a protest prior to the close of bidding and thereby established its prospective bidder status, and that CGI thereafter diligently pursued its rights, CGI has prospective bidder status to pursue its Court of Federal Claims protest.
B. Direct Economic Interest
To have standing, CGI must also have a direct economic interest affected by the award of the contract. Digitalis, 664 F.3d at 1384. CGI can satisfy this requirement by showing that it suffered “a non-trivial competitive injury which can be redressed by judicial relief.” Weeks Marine, Inc. v. United States, 575 F.3d 1352, 1361-62 (Fed. Cir. 2009). CGI has made such a showing. CGI argues that the payment terms in the 2014 RFQs are illegal and that they caused CGI to protest instead of bid. Reply Br. at 26. This injury is both non-trivial and competitive, and CGI has sought judicial relief via its protest in the Court of Federal Claims. As the Court of Federal Claims correctly concluded, “CGI had a definite economic stake in the solicitation being carried out in accordance with applicable laws and regulations.” Opinion and Order at 17 (quoting Weeks Marine, 575 F.3d at 1362).
The government argues that the revised payment terms are not a competitive injury because the payment terms “‘equally disadvantaged’ all prospective bidders.” Appellee‘s Br. at 32 (quoting Opinion and Order at 24). This argument is unavailing. The government made the same argument
* * * * *
Because CGI was a prospective bidder with a direct economic interest affected by the award of the contract, we conclude that CGI had standing to file its protest in the Court of Federal Claims. We therefore turn to the merits.
II. Challenge to Payment Terms
A. Background
The Federal Acquisition Streamlining Act of 1994 (“FASA“) was implemented to “revise and streamline the acquisition laws of the federal government” and “facilitate the acquisition of commercial products.” S.Rep. No. 103-259, at 1 (1994), 1994 U.S.C.C.A.N. 2598. To that end, FASA reformed government procurement by requiring the federal government to purchase commercial items under commercial terms to the extent practicable. In particular, FASA provides that the Federal Acquisition Regulations (“FAR“) include “a list of contract clauses to be included in contracts for the acquisition of commercial end items,” and that the list, to “the maximum extent practicable . . . shall include only those contract clauses that are . . . determined to be consistent with standard commercial practice.”
FAR Part 12 was created to implement FASA. FAR Part 12 states that it “shall be used for the acquisition of supplies or services that meet the definition of commercial items.”
The Federal Supply Schedule (“FSS“) program provides a simplified process for the government to obtain commercial supplies by negotiating underlying FSS contracts with suppliers of commercial products and then allowing executive agencies to issue orders for those commercial products pursuant to the underlying FSS contract. See Sharp Elecs. Corp. v. McHugh, 707 F.3d 1367, 1369 (Fed. Cir. 2013). FAR Subpart 8.4 governs the FSS program.
B. Whether the 2014 RFQ Payment Terms Violate FAR Part 12
The 2014 RFQs being challenged here were issued pursuant to the Financial and Business Solutions Schedule, an underlying FSS contract. The Court of Federal Claims found, and neither party disputes, that the services solicited in the 2014 RFQs are commercial items and that the revised payment terms therein are inconsistent with customary commercial practice. Opinion and Order at 9, 19; see Oral Argument 37:45-41:45. We affirm these undisputed fact findings.5 Thus, the
Before the Court of Federal Claims, the government does not appear to have disputed that FAR Part 12‘s proscription against terms inconsistent with customary commercial practice applies to solicitations for the underlying FSS contracts themselves. Opinion and Order at 12. However, the government argued that FAR Part 12‘s proscription does not apply to orders made pursuant to the existing FSS contracts. The Court of Federal Claims agreed. Opinion and Order at 19-22. It reasoned that FAR Subpart 8.4, which governs the FSS program, does not expressly state that FAR Part 12 applies to orders made pursuant to an existing FSS contract. Opinion and Order at 20. It similarly found that FAR Part 12 does not expressly state that its provisions apply to such orders. Opinion and Order at 20-21. We review the Court of Federal Claims interpretation of the applicable regulations de novo. Abbott Labs. v. United States, 573 F.3d 1327, 1330 (Fed. Cir. 2009).
We conclude that FAR Part 12‘s proscription against terms inconsistent with customary commercial practice applies to the 2014 RFQs and therefore that the RFQs violate that proscription.6 On a general level, FAR Part 12 applies to the 2014 RFQs because it makes clear that it “shall be used for the acquisition of [commercial items].”
Acquisition begins at the point when agency needs are established and includes the description of requirements to satisfy agency needs, solicitation and selection of sources, award of contracts, contract financing, contract performance, contract administration, and those technical and management functions directly related to the process of fulfilling agency needs by contract.
The government and the Court of Federal Claims are correct that FAR Subpart
CONCLUSION
Because FAR Part 12 applies to the 2014 RFQs and the revised payment terms violate FAR Part 12‘s prohibition against including contract terms inconsistent with customary commercial practice, we reverse the Court of Federal Claims grant of judgment on the administrative record to the government. We remand to the Court of Federal Claims for proceedings consistent with this decision.
REVERSED AND REMANDED
