SHARP ELECTRONICS CORPORATION, Appellant, v. John McHUGH, Secretary of the Army, Appellee.
No. 2012-1299.
United States Court of Appeals, Federal Circuit.
Feb. 22, 2013.
1367
The majority errs in failing to apply that framework here. Nevertheless, by deciding that the case in fact was not ripe, the majority implicitly decides that the Ninth Circuit‘s conclusion was clearly erroneous. I disagree with this implicit conclusion. In any event, the majority correctly concludes that McGuire‘s claim must fail due to his lack of a cognizable property interest. This alone is dispositive and requires this court to affirm, and I therefore concur in the judgment.
Andrew Kenneth Wible, Cohen Mohr, LLP, of Washington, DC, argued for the appellant. Of counsel was Andrew J. Mohr.
Nicholas Jabbour, Trial Attorney, Commercial Litigation Branch, Civil Division, United States Department of Justice, of Washington, DC, argued for appellee. With him on the brief were Stuart F. Delery, Acting Assistant Attorney General, Jeanne E. Davidson, Director, and Harold D. Lester, Jr., Assistant Director.
Before DYK, PLAGER, and CLEVENGER, Circuit Judges.
Opinion for the court filed by Circuit Judge DYK. Dissenting opinion filed by Circuit Judge PLAGER.
DYK, Circuit Judge.
BACKGROUND
I
Historically, government agencies entered procurement contracts and purchased supplies and services on an individual basis. Contract disputes were initially directed to the agency contracting officer, and appeals went to an agency Board of Appeals under the contract‘s disputes clause, or, if the contract had no pertinent clause, to a district court or what is now the Court of Federal Claims. See generally 4 Report of the Commission on Government Procurement 11-28 (1972); Joel P. Shedd, Jr., Disputes and Appeals: The Armed Services Board of Contracts Appeals, 29 Law & Contemp. Probs. 39 (1964).
Over time, federal contracting became more centralized. The Federal Property and Administrative Services Act of 1949, Pub.L. No. 81-152, 63 Stat. 377, created the GSA to standardize federal procurement processes and procure, store, and distribute supplies to federal agencies. See generally James F. Nagle, A History of Government Contracting, 450-52 (2d ed. 1999); 3 Report of the Commission on Government Procurement 10-11; 27-37 (1972). Under the current version of the GSA Schedules Program, also called the Federal Supply Schedule Program or Multiple Award Schedule Program, see
Schedule contracts are intended to simplify the acquisition process. However, they have generated jurisdictional uncertainty with respect to disputes, which may involve (1) the correct interpretation of the schedule contract; (2) the correct interpretation of the agency‘s order; (3) the facts relating to the parties’ performance; or (4) some combination of these issues. Prior to 2002, the regulations established that only the schedule office CO (here, the GSA CO) could issue a final decision in a dispute pertaining to an order under a schedule contract. See
Effective July 2002, the FAR was amended,1 authorizing ordering COs to resolve certain “disputes arising from performance of the order.”
II
On September 18, 2001, Sharp and GSA entered into a schedule contract, Multiple Award Schedule Contract No. GS-25F-0037M (“Sharp‘s Schedule Contract“), which allowed agencies to lease or purchase office equipment and supplies from Sharp‘s Schedule Pricelist. The pricelist included Special Item Number (“SIN“) 51-58a, covering monthly lease plans for the operation and maintenance of copier equipment, and setting forth additional terms and conditions applicable to such leases, including provisions pertaining to payment, lease terms, the exercise of options, and early termination fees.
On December 1, 2005, the Army issued delivery order No. W91ZLK-06-F-0028 to Sharp “in accordance with and subject to terms and conditions” of Sharp‘s Schedule Contract. J.A. 18. The order provided for a four-year lease of copier equipment, including one Base Year and three Option Years, with the last Option Year ending on December 1, 2009. Sharp‘s Schedule Pricelist stated that with respect to delivery order leases of this type, “the Government intends to exercise the renewal options contained herein and lease the Equipment for the entire Lease Term.” Option Years One and Two were exercised in full; on November 20, 2008, the Army and Sharp executed Modification No. P00011 (“Mod 11“), which “partially exercise[d] option year three” for six months. J.A. 3. The parties subsequently executed Modification No. P00012 (“Mod 12“), which extended the lease for three more months. The lease finally ended on August 31, 2009. Mods 11 and 12 were silent as to the reservation or release of claims associated with the modifications.
Sharp viewed the Army‘s failure to fully exercise Option Year Three as a premature cancellation, entitling Sharp to fees under the termination provisions of its schedule contract. In January 2011, Sharp filed a formal claim with the Army CO, citing the termination fee provisions of its schedule contract, and seeking $67,928.63 in early termination fees (representing four times the base monthly charge for each unit). The Army CO did not respond, and did not refer Sharp‘s claim to the GSA CO responsible for Sharp‘s Schedule Contract. After sixty days, Sharp appealed the deemed denial of its claim to the ASBCA. See
The ASBCA ”sua sponte [] raised the issue of its jurisdiction to decide th[e] appeal.” Sharp Elecs. Corp., ASBCA No. 57583, 12-1 B.C.A. ¶ 34,903, at 171,621 (”ASBCA Decision“). The jurisdictional issue that concerned the ASBCA arose from the regulatory division of CO authority in disputes involving federal supply service contracts. Under the CDA, codified at
The parties agreed that the termination fees Sharp sought were authorized, if at all, by provisions in Sharp‘s Schedule Contract with GSA. Sharp invoked the “Premature Discontinuance Provisions” of its 2005 GSA-approved schedule pricelist. These provisions, set forth at Special Item Number 51-58a, ¶ 21N(2), and included in Modification No. 32 to Sharp‘s Schedule Contract, stated in relevant part:
If the Government terminates a FMV lease prior to its expiration . . . the Government shall pay all amounts due the Contractor as of that date and a “Premature Discontinuance Fee” (“PDF“). The PDF is the monthly equipment component, for each unit/accessory being terminated times the number of months remaining in the FMV Lease.
For its part, the Army contended that because Mod 11 represented a bilateral agreement to shorten Option Year Three to six months, the lease was not terminated “prior to its expiration,” and the discontinuance provisions were inapplicable.
In their jurisdictional briefings to the ASBCA, both parties argued that the Army CO could resolve the dispute. The Army argued that the dispute pertained solely to the parties’ contractual obligations under Mod 11, an issue that could be decided by the Army CO responsible for the delivery order. Sharp argued that the relevant termination provisions needed only to be applied to the facts, and that this application constituted an issue of performance under the delivery order, which could be decided by the Army CO.
The ASBCA rejected both parties’ arguments. It determined that the “fundamental issue under this appeal is the applicability of the terms and conditions of the Schedule Contract“—i.e., the termination for convenience provisions—“not performance under the [delivery order].” ASBCA Decision, at 171,622. The ASBCA determined that it “d[id] not have jurisdiction to hear appeals from ordering activity COs where ‘the dispute . . . is related solely to the validity and/or applicability of the terms and conditions of the’ schedule contract, not performance of the [delivery order].” Id. (quoting Sharp Elecs. Corp., ASBCA No. 54475, 04-2 B.C.A. ¶ 32,704, at 161,796). Because “the Army CO lacked authority to resolve this dispute,” the ASBCA dismissed Sharp‘s appeal. Sharp timely appealed to this court. We have jurisdiction under
DISCUSSION
In accordance with the CDA,
The CDA requires that “[e]ach claim by a contractor against the Federal Government relating to a contract shall be in writing,” and “shall be submitted to the contracting officer for a decision.”
Pursuant to statutory mandate, the Federal Acquisition Regulatory Council is required to promulgate the FAR, “a single Government-wide procurement regulation,”
As amended,
(a) Disputes pertaining to the performance of orders under a schedule contract.
(1) Under the Disputes clause of the schedule contract, the ordering activity contracting officer may—
(i) Issue final decisions on disputes arising from performance of the order (but see paragraph (b) of this section); or
(ii) Refer the dispute to the schedule contracting officer.
(2) The ordering activity contracting officer shall notify the schedule contracting officer promptly of any final decision.
(b) Disputes pertaining to the terms and conditions of schedule contracts. The ordering activity contracting officer shall refer all disputes that relate to the contract terms and conditions to the schedule contracting officer for resolution under the Disputes clause of the contract and notify the schedule contractor of the referral.
The regulation clearly authorized the ordering CO to decide routine disputes about order performance not involving interpretation of the schedule contract, such as whether the contractor‘s default was excusable. See
On its face,
In theory, the FAR could provide for bifurcation—that is, the portion of a dispute relating to the schedule contract would be referred to the schedule contract CO, and the portion of a dispute requiring interpretation of the order would go to the agency CO. But this procedure would be highly inefficient, and the FAR evidently contemplates that a dispute that involves the interpretation of both contracts, as well as pertaining to performance of the order, would go to the scheduling CO. That is why the FAR allows the ordering CO to “[r]efer dispute[s] [pertaining to the performance of the order] to the schedule contracting officer.”
Thus, we conclude that the FAR creates a bright-line rule—all disputes requiring interpretation of the schedule contract go to the schedule CO, even if those disputes also require interpretation of the order, or involve issues of performance under the order. “Bright line rules upon which the parties’ expectations may be firmly established” are particularly valuable in contracting. Bowsher v. Merck & Co., 460 U.S. 824, 841 n.18 (1983). The FAR and CDA were intended in part to promote uniformity, consistency, and fairness across all contracting agencies. See, e.g., Newport News Shipbuilding & Dry Dock Co. v. Garrett, 6 F.3d 1547, 1551 (Fed. Cir. 1993);
Furthermore, a bright-line rule here will maintain jurisdictional clarity among the Boards, which is particularly important with respect to contractors that supply both civilian and military agencies. If ordering COs could issue decisions interpreting suppliers’ schedule contracts, appeals to the Boards would produce two independent lines of interpretive caselaw: appeals from civilian agency ordering COs would go to the CBCA, while appeals from military ordering COs would go to the ASBCA.2 See generally
We hold that
In this case, the dispute turns on whether the Army incurred premature discontinuance fees when it did not fully exercise Option Year Three. These fees are a contractual remedy provided in Sharp‘s Schedule Pricelist, set forth in Modification No. 32 to Sharp‘s Schedule Contract. As discussed above, the Army argues that the discontinuance provisions are inapplicable because Mod 11 bilaterally specified a new end date for Option Year Three before it was exercised, so there was no premature discontinuance. Sharp does not argue that the Army was contractually obligated to exercise Option Year Three. Rather, Sharp contends that the Army‘s partial exercise of Option Year Three constituted a premature discontinuance under the relevant contractual provisions. The
We recognize that the distribution of contracting officer authority (compelled by the way
Sharp correctly notes that the Army CO failed to refer Sharp‘s claim to the GSA CO as required by
Because Sharp‘s claim cannot be resolved without interpreting the premature discontinuance provisions in Sharp‘s Schedule Contract, the Army CO has no authority to decide the claim or issue a deemed denial, and the ASBCA lacks jurisdiction of Sharp‘s appeal. Since the CDA‘s six-year statute of limitations has not yet run, see
AFFIRMED
PLAGER, Circuit Judge, dissenting.
I respectfully dissent. Admittedly, the FAR dispute provision under review lends itself to several competing interpretations. The interpretation favored by the majority, though hardly dictated by the terms of the disputed provision, if it had been an authoritative agency interpretation under Chevron could be considered to be within the range of reasonable interpretations.1 As a judicial exercise in regulatory construction, however, the majority‘s version of the rule does not comport with the purpose of the Councils that drafted the rule, it adopts a procedure that fails the “bright-line” test the majority claims for it, and, most importantly, it dictates a result that falls short of a common sense solution to the problem presented.2
A.
This is litigation about where to litigate a government contract, and, as has famously been said, “Nothing is more wasteful than litigation about where to litigate, particularly when the options are all [boards] within the same legal system that will apply the same law.”3 What appeared at first reading to be a straight-forward exercise in construction of a regulatory provision, upon closer examination proved to be anything but straightforward. And the consequence of choosing between competing theories of how this contract dispute should be resolved—more accurately, who should resolve it—is of considerable significance for the administration of government contracts.
The disagreement in this case is over which Contracting Officer (CO)—the Army‘s agency CO or the schedule contract CO (the GSA CO), and derivatively which Board of Contract Appeals—is the correct authority to decide this particular contract dispute. As the majority explained, the schedule contract, negotiated with the supplier by and prepared under the supervision of a GSA contracting officer (GSA CO) responsible for government-wide contracting for that group of products, describes in general terms the range of such products being offered by the particular supplier. The schedule contract spells out the terms on which the products are being offered, and the permissible parameters for any order (or delivery) contract an agency contracting officer may wish to enter into on behalf of the agency.4
The agency CO with a need for such products then initiates with the supplier an order contract for the specific products desired for the particular agency facility. This could be an outright purchase order, or, as was the case here, a lease of products for a period of years.
The order contract may expressly incorporate the governing provisions of the schedule contract, as was done in this case,5 and is written to comply with its terms and conditions. For example, the schedule contract might authorize a range of years, such as 1 to 5, during which a lease for the products could be made. The order contract would be for a specific term within that range, say for one year. If initial term extension options are desired, the order contract will spell out those options consistent with the provisions in the schedule contract for such term extensions, up to a maximum of five years total.6
The uninitiated might say that the question of who initially gets to decide the dispute is easily answered—it depends on which contract‘s provisions govern the alleged breach. If the order contract, then the agency CO who negotiated and administers the order contract with the supplier has first dibs; if the schedule contract, then the GSA CO who negotiated the authorizing schedule contract. But when the two contracts are written to interact intimately with each other and deal with the same legal issues, and in places may have similar if not identical terminology, it may not be obvious in a given dispute which contract‘s terms govern, and thus which
In this case, the contract dispute, the merits of which are not now before us, turns on provisions in both the order contract and schedule contract dealing with leases and extension of the lease terms for additional option years over the initial year provided in the order contract, plus modifications to the order contract later added.7 Sharp alleges the Army prematurely cancelled the third option year of the order contract, entitling it to the specified discontinuance fees, to which the Army responded that the modifications to the order contract, agreed to by the parties, authorized the early termination.
Both parties understood that the current default rule—
To the parties’ surprise, the ASBCA sua sponte ruled that, since language in the schedule contract as well as in the ordering contract dealt with the mechanics of term extensions, the ASBCA did not have jurisdiction to decide the dispute. In the Board‘s view, the appropriate CO for ruling on the dispute was the GSA CO and not the agency CO. Sharp promptly appealed that ruling here. The issue to be decided in this appeal is whether the ASBCA applied the proper default rule in refusing to decide the merits issue that the dispute presented. I think the Board erred; for the reasons I shall explain, I would reverse the ruling of the ASBCA and remand the matter to the ASBCA for decision on the merits.
B.
The default rule presently in place is
In 2000, the Civilian Agency Acquisition Council and the Defense Acquisition Regulations Council (the Councils), which is the group responsible for such matters, proposed to amend
But keeping a clear distinction between the order contract and the schedule contract when writing the new rule was not so easy. At the outset, in announcing the purpose of the proposed amendment to the rule, the Councils stated that it was “to permit the ordering office contracting officer to issue a final decision regarding disputes pertaining solely to performance of schedule orders.” The use of the term “schedule orders” blended the two contract descriptors together, and introduced the question of what is “performance” of “schedule orders.”
This blending problem was carried over into the amended rule. As the issue in the case before us illustrates, and as the majority opinion correctly notes, since its adoption
C.
I begin with the relevant language of the current rule:
8.406-6 Disputes.
(a) Disputes pertaining to the performance of orders under a schedule contract.
(1) Under the Disputes clause of the schedule contract, the ordering activity contracting officer may—
(i) Issue final decisions on disputes arising from performance of the order (but see paragraph (b) of this section); or
(ii) Refer the dispute to the schedule contracting officer.
(2) The ordering activity contracting officer shall notify the schedule contracting officer promptly of any final decision.
(b) Disputes pertaining to the terms and conditions of schedule contracts. The ordering activity contracting officer shall refer all disputes that relate to the contract terms and conditions to the schedule contracting officer for resolution under the Disputes clause of the contract and notify the schedule contractor of the referral.
As a close reading reveals, and as I will further detail,
By its terms, subsection (a) addresses performance issues arising under the terms of order contracts issued pursuant to a schedule contract. The subsection consists of instructions regarding actions to be taken by the ordering activity contracting officer (the agency CO), leaving no doubt that the contracting party with a complaint—the supplier here—is to address the complaint to that officer in the first instance. In response to the complaint filed by the supplier, the ordering activity contracting officer is instructed to take one of two actions: (1) issue a final decision under the Disputes clause of the schedule contract on a dispute arising from performance of the order contract; or (2) refer the dispute to the schedule contracting officer (the GSA CO).8 Note that the
Subparagraph (b) addresses disputes pertaining to the “terms and conditions of schedule contracts.” But again, the subsection describes only actions to be taken by the ordering activity contracting officer, confirming the point made about subsection (a)—it is the duty of the agency CO, not the complainant supplier or the GSA CO, to determine whether it is necessary for the GSA CO to become involved. The agency CO is to refer the complaint to the GSA CO for resolution if the dispute “relate[s] to the contract terms and conditions.” Though not entirely clear, presumably the unqualified reference to contract terms and conditions at this point in the text means the schedule contract‘s terms and conditions, since that is the heading of the subsection and the provision would make even less sense otherwise.9
The plain language of the rule tells us at least this much:
- All contract disputes between a supplier and the ordering agency that relate to the Disputes clause of the schedule contract are addressed to the ordering activity contracting officer (the agency CO) for initial decision;
- Nothing in either subsection (a) or (b) refers to disputes that might arise directly under an order contract and its disputes clause, if any;
- The agency CO may decide the dispute, even though it relates to the disputes clause of the schedule contract, or may refer the dispute to the GSA CO—the decision which to do lies with the agency CO;
- The only guidance given the agency CO about whether to decide or refer is that, if the dispute “relate[s] to” the “contract terms and conditions” (as noted presumably of the schedule contract), the agency CO shall refer it to the GSA CO.
The reader at this point should have little problem seeing that
Note that I refer to a performance breach in both situations though performance is mentioned only in subparagraph (a). Without an alleged breach in contract performance by one of the parties, a contract dispute would not seem to involve the terms and conditions of either contract. That is, a dispute about whether a contract was actually formed in the first instance would not necessarily implicate subsequent performance of the contract, but that kind
It is the search for how to draw that line—to find a sensible default rule to be applied by the ordering contracting officer in performing the tasks assigned by
D.
It is possible to read into the language of the rule a meaning that any time the terms and conditions of the schedule contract are relevant in any material way to the dispute, even though the alleged breach is also a breach of the order contract‘s terms, the dispute shall be referred to the GSA CO by the agency CO. This would in effect reinstall the earlier version of the rule before its amendment in 2002, as if it read: “The ordering activity contracting officer shall refer all disputes that relate, in any way, to the contract terms and conditions of the schedule contract to the schedule contracting officer . . . ” (italics added for clarity). I will refer to this as the “GSA CO/default” rule.
One alternative reading of the rule arrives at the opposite outcome, as if subparagraph (b) read: “The ordering activity contracting officer shall refer only those disputes that relate solely to the contract terms and conditions [of the schedule contract] to the schedule contracting officer . . . .” Put another way, a dispute that can be decided under the terms of the agency ordering contract should be decided by the agency CO, even if there is related language in the schedule contract. I will refer to this as the “agency CO/default” rule.
What are the consequences of picking one or another of these alternative readings? Turning first to the ‘GSA CO/default’ rule, and given the likely overlap in purpose and terminology of the two contracts, this rule would again have the effect of sending most contract disputes to the schedule contracting officer, the GSA CO. Even if a case does not immediately invite that result, it may provide the opportunity for forum shopping. A reasonably creative attorney for a supplier who believes the agency CO to be unfriendly can seek out some language in the schedule contract that arguably relates to the dispute, and then argue for a referral to the GSA CO.
Furthermore, one wonders how many contract disputes there are in which some language from the schedule contract cannot be found relevant? That is to say, how many contract disputes turn solely upon performance requirements found only in the order contract, when the agency order contract is intentionally designed and written to piggy-back on the terms and conditions of the schedule contract? As earlier noted, there could be a few such disputes. Others are suggested by the majority, based on related provisions of the FAR which spell out provisions that should be in an order contract, though without indicating whether they may also be found in the schedule contract. In any event, these kinds of disputes are likely to be easily resolved with little litigation.
The more difficult disputes, those for which a workable rule is needed, are those about issues that turn on contract terminology, but terminology likely found both in the agency contract and, in some form or other, in its underlying schedule contract. This case is perhaps a good example. Interestingly, both the agency and the supplier thought this case was in fact one that turned on the term extension provisions of the agency‘s ordering contract as subsequently modified, even though they disagreed as to exactly which of the provisions controlled. Thus, when the agency CO failed to act on the dispute, the parties asked the agency contract ap-
The ASBCA, ignoring its own precedents holding that it had jurisdiction unless the dispute was related “solely to the validity and/or applicability of the terms and conditions of the [schedule contract],” In re Spectrum Healthcare Res., Inc., ASBCA No. 55120, 06-2 B.C.A. ¶ 33,377 (citing In re Appeal of Sharp Electronics Corp., ASBCA No. 54475, 04-2 B.C.A. ¶ 32,704), held that jurisdiction lay exclusively with the GSA CO (and thus the Civilian Agency Board of Appeals) because the merits related to language found in the schedule contract. Under this GSA CO/default rule, the determination of who decides a contract dispute will turn on whether one can find language in both documents that seems to bear somehow on the outcome of the dispute; if so, it goes exclusively to the GSA CO. This suggests that, except in the simplest of disputes, the case will more often than not be one in which there is some relevant language to argue over, since the two contracts are inextricably intertwined. A bright line this is not.
Though only time will tell for sure, it would seem that under the GSA CO/default rule the GSA contracting officers responsible for the overall schedule contracts will again become immersed in any number of order contract disputes that turn on local events and local understandings, regarding which the agency contracting officers may be better positioned to deal. Returning priority for dispute resolution to the central agency GSA CO under the GSA CO/default rule can only make contracting with the Government more drawn out and complex, and therefore more expensive; the Councils were correct in trying to find a way to give more decisional authority to the ordering agency CO, even though the Councils did not get it quite right.
The alternative default rule—agency CO/default—means that a dispute that can be decided under the terms and conditions of the agency order contract should be decided by the agency CO, even if there can be found some language in the schedule contract that appears presumptively relevant. This default rule seems better designed to produce efficient and acceptable outcomes since it utilizes the available knowledge and expertise of the agency contracting officer. And a decision by the agency CO, even if it necessarily implicates in some small measure language in the schedule contract, remains controlling only as to the facts of the local dispute, and does not govern future application of the schedule contract in other contexts. Thus the concern for uniformity in the interpretation of the schedule contract is not implicated; ultimately, control over the broad meaning of the schedule contract remains a matter for the GSA CO and the Civilian Board of Contract Appeals.
Instructive on this point is a recent case, decided under the current version of
E.
As presented, it is necessary in order for us to decide the case before us to choose one or the other of these default rules, since the FAR itself does not. The rather confused and redundant language of
Unlike my colleagues in the majority, I opt for the rule that seems most likely to promote efficient, prompt, and knowledgeable decisions, the rule that gives the agency CO initial responsibility to decide the case presented to it unless it is necessary to invoke the special expertise of the schedule CO to construe the schedule contract provisions. Thus, if the issue is one which reasonably turns on the performance requirements of the order contract, regardless of whether it can also be said to be within the terms and conditions of the schedule contract as well, the agency CO should initially decide the matter, with appeals taken to the agency CO‘s applicable contract appeals board.
On the other hand, if the dispute directly raises the terms and conditions of the schedule contract and cannot be decided without a determination of the meaning of those terms and conditions, then the agency CO should refer the dispute to the appropriate schedule CO. This is a default rule that requires little guessing, and is not dependent on the lawyering skills of the parties.
I say unlike my colleagues in the majority. As I understand it, we agree that the FAR does not authorize an ordering agency CO to issue decisions interpreting the schedule contract—all cases requiring interpretation of the schedule contract must be resolved by the GSA CO. See Maj. Op. at 1372-73. However, if I read the opinion correctly, the majority concludes that a dispute that involves a party‘s performance under the ordering contract, based on an interpretation of the ordering contract, nevertheless goes to the scheduling contract (GSA) CO if the dispute may be argued to involve interpretation of related language in the schedule contract—even if the dispute could be resolved without resorting to the latter interpretation issue. Id. at 1373.
They try to soften what appears to be a classic GSA CO/default position by noting that “the ordering CO is certainly authorized to construe the language of the order (or its modifications),” id. at 1373-74, unless of course the dispute also relates to language in the schedule contract that would appear to be subject to interpretation. They call this a “bright line” rule, but how bright it is can be seen by asking, since the issue in the case before us is a question of performance of the order contract and of interpretation of the provisions of that contract as modified by the parties, why under the majority‘s rule does this case not fall within the purview of the agency CO? Is it because there is lan-
As the majority notes, should either my understanding or the majority‘s fail to capture the main thrust of whatever it was the authoring Councils had in mind when they amended the FAR by adding the revised
Given my understanding of
On the record before us, this is such a case, a conclusion regarding which the parties were from the outset in agreement: the merits of this contract dispute should be resolvable under the terms and conditions of the order contract since the scope of the contract extension provision and the modification at issue were essentially questions regarding the order contract. But what if the appearance from the record, and the parties, are in error, and the schedule contract‘s interpretation is an essential ingredient in the resolution? The appeal from the decision of the agency CO properly is before the ASBCA, and one of the issues subject to appeal is whether, applying the correct test, the agency CO had authority to decide the case—that is, whether the case cannot be decided without a determination of the meaning of the applicable terms and conditions of the schedule contract. The ASBCA exercising its appellate powers is of course free to make such a determination, as it purported to in this case.
Under
I would reverse the decision of the Board preemptively denying jurisdiction over this dispute.10
