History
  • No items yet
midpage
Brown Plumbing & Heating, Inc v. Homeowner Construction Lien Recovery Fund
500 N.W.2d 733
Mich.
1993
Check Treatment

*1 179 v Const Lien Fund Brown 1993] HEATING, v HOMEOWNER PLUMBING & INC BROWN FUND CONSTRUCTIONLIEN RECOVERY 5). (Calendar 8, Argued 1992 No. De- Docket No. 92347. December May cided 1993. subcontractor, Inc., Plumbing, Heating & a licensed against brought in the Montcalm Circuit Court an action others, Recovery Lien Fund and seek- Homeowner Construction by ing Leonard an amount owed it E. Cruz Ortiz and collect Ortiz, Homes, Energy general doing Primus its business as contractor, misrepresented possession of a valid build- who had J., court, Banks, granted summary The James L. er’s license. holding plaintiff disposition plaintiff, that because the substantially complied licensing requirements of with the 203(3)(h) Act, person seeking Lien that a of the Construction § recovery or subcon- from the fund establish that the contractor the fund claimant contracted is licensed as tractor with whom law, recovery required by from the fund. The it was entitled Hood, P.J., Appeals, Fitzgerald, and McDonald Court of JJ., curiam, opinion per finding in an that because the affirmed nature, liberally interpreted it should act is remedial claimants, compliance and that favor lien substantial (Docket permit recovery from the fund is sufficient to § 127345). appeals. No. The defendant opinion joined by Levin, Brickley, In an Justice Justices Supreme Boyle, Riley, Griffin, Court held: Act, requires 302 of the Lien Section Construction compliance perfect liens and to substantial construction acquire part permit jurisdiction, apply not a court to does collect from which enumerates Recovery Fund. the Homeowner Construction unambiguous expressly provides 1. The act is clear and perfec- compliance applies only to the in 302 that substantial § liens addressed in 1 and court tion way suggests jurisdiction. It in no that substantial referring By to the to collect from the fund. not is sufficient expressly limits its fund or application part 1. placement 2. of 302 in 3 does not evidence rather, act; legislative intent to the entire [May- Mich expressed placement merely ambiguous. actual as intent unambiguous language precedence takes over of 302 Likewise, placement. parts essentially the fact that and 3 are lien identical to the former mechanics’ act and *2 at of the current act confirms that added the time enactment applies only parts 302 1 and 3. § 3. of the first sen- While the liberal construction act, applies it cannot and should not tence the entire § §203(3)(h) requirement nullify unambiguous the clear fund, that, seeking it from the must be established the contractor licensed. validity 4. 2 does deal with the of construc- Because not liens, provisions tion tested a its cannot be substantial compliance standard. Reversed. Cavanagh, joined by Justice Justice Chief dissent-

ing, statutory the rules of stated that on basis of the construc- Act, it tion and the remedial nature of the Construction Lien substantially comply sufficient for a lien claimant' with 203(3)(h)in order to recover from the Homeowner Construc- § Recovery tion Lien Fund. only protect Lien intended to not Construction Act was a materials, wages right payment lien claimant’s for or but multiple payments same also a land owner from for the ser- 203(3)(h)provides that in lien claim- vices. Section order for a ant to from the the contractor must be licensed. recover provides compliance with Section 302 that substantial permit recovery the act is from sufficient Recovery placement Homeowner Construction Lien Fund. The deliberate, of 302 in 3 of act was a affirmative evidencing Legislature, its that § decision intention including Reading applicable throughout act 2. entirety, Act in that § Construction Lien is clear applicable should be made collection 203(3)(h). fund, including (1991) App reversed. Mich NW2d Richard D. Palmer for the plaintiff. Kelley, L.

Frank J. Thomas General, Attorney Casey, A. and Michael Lock- General, Solicitor man, General, for the defen- Attorney Assistant dant. Plumbing

1993] Brown Lien Fund v Const Opinion of the Court granted leave to determine J. We Brickley, provision, compliance” the "substantial whether Act, MCL 570.1101 Lien of the Construction 26.316(101) applies seq., seq.; §to et et requires who seeks that one of the recovery Construction the Homeowner person Recovery with Fund establish if re- is licensed contracted the claimant whom quired to be licensed.

i dispute. On not of this case are The facts plaintiff April 14, 1987, plumbing properly Heating, Inc., licensed heating contract contractor, entered a written general Energy Homes, contractor Primus building provide homes, in plumbing business of on a residential and materials labor *3 fraudulently job. informed Primus construction plaintiff provided license a that it was licensed belonging unrelated, licensed, to a but number construction Mayflower

company, Construction.1 the license or an asked to see Plaintiff never card. identification and failed to Primus became insolvent

When completed, pay the work for the subcontractors proceed- filed and foreclosure of lien were claims begun property. ings The Homeowner on the were Recovery named as a Fund was Construction 26.316(203X4). 570.1203(4); party. The MSA MCL they stating that filed an affidavit homeowners Primus, misrepresented Ortiz, to the homeown- co-owner of Cruz a number license and used the license had a builder’s ers that he building permits for belonging Mayflower Construction obtain co-owner, Ortiz, statements filed sworn job. the other Leonard general bank, Mayflower alleging contractor. was misrepresented themselves to Additionally, Cruz and Leonard Ortiz Mayflower Energy in association with Homes as "Primus others Construction, . . . .” License Builder’s # [May- Opinion op the Court thereby completed, for the work Primus paid 570.1203(l)(a); liability. MCL themselves of relieved 26.316(203)(l)(a). MSA through payment to seek then resorted

Plaintiff seq.; MCL 570.1201 et MSA Fund. Recovery 26.316(201) plain seq. et pay The fund refused to compli failure show plaintiff’s tiff because recovery under prerequisites ance with a licensed residen that Primus was namely, Michigan law.2 required as under contractor tial filed motions for and the fund plaintiff Both the granted the The trial court disposition. summary motion, had holding plaintiff plaintiff’s and, therefore, the act complied with substantially from the fund. entitled to recover Noting that one of the dual appealed.3 fund The protect Act is to Construction Lien purposes or perform provide labor rights of those who property, of real improvement for the materials stated Appeals affirmed. Court the Court nature, is remedial the act that because required they may to be licensed before 2Kesidential builders are 18.425(601X1); 339.601(1); provide MCL services. MCL 18.425(2401)(a). 339.2401(a);MSA specific prerequisites the fund are found in to recover from 203(3), provides part: Subject person who has recorded a claim to section recovering precluded a construction lien from lien and who (1) may fund amount for recover from the under subsection which the fund shall establish all of the person A the lien is established. who seeks following: (h) subcontractor, with whom the That the contractor or the with, person claiming contracted is li- the construction lien 570.203(3)(h); required by if law to be licensed. [MCL censed *4 26.316(203)(3)(h).] preserve there did not the issue whether We note the defendant compliance with the for reimbursement was substantial general spite fact that the from the lien contractor address this issue. 203(3)(h).Thus, required by we do not not licensed as Fund v Const Lien 1993] op Opinion the Court lien in favor of interpreted liberally should be result, the court held that substan- As a claimants. is sufficient compliance tial with § 709, App the fund. 190 Mich permit recovery from (1991). granted We leave 476 NW2d (1992), and now reverse. 440 Mich 889 we appeal,

ii of provides: the act Section statute, and a remedial This act is declared the liberally to secure beneficial shall be results, intents, construed of Substan- purposes and this act. act provisions of this compliance with the tial validity of the construc- be sufficient for shall give provided for in this and tion liens [Empha- to the to enforce them. jurisdiction court sis added.] unambiguo clear provision find this to be

We provides that substan express language us.4 1) applicable aspects: is in two compliance only tial provided liens the construction perfection 2) give jurisdiction. for in court states Although the first sentence the section act liberally, the entire is to be construed that qualified sentence second language above only two described instances compli that way suggests in no substantial from the fund. ance is sufficient to collect pro- Legislature persuasive findWe intention demonstrating express language vided should language substantial act act. 1 of the 1 of the Part apply only points legislative derived from out that intent must be The dissent statute, language is clear and and when the actual unambiguous, necessary. interpretation Post at 188. no further 368, 376; [1988].) Inc, Storey Meijer, (Citing Mich 429 NW2d v *5 442 Mich 179

184 Opinion the Court of acquire procedures enforce- an the establishes able piece particular of on a construction lien part property; words, 1 the in establishes other acquire procedures lien.” a "valid Lien 2 the Homeowner Construction Part Recovery creates the Fund and enumerates fund. to collect from the must be established that recovery referring Therefore, the fund or not validity referencing only "the from the language liens,” of the actual the construction of application part expressly 1. limits its 302 placement plaintiff argues §of 302 that the Legislature intended in 3 is evidence that the possi It also that 302 to the entire act. Legislature, of the with the addition the ble repositioning recovery of the sections fund and the up previous act, consider did not that made the Legis application § 302.5 the of Where current may placed § more a matter 302 have been lature example, arranging utility. the various For of provisions particularly, case, statute, in this of a as greater provisions part of a former become where put statutory scheme, it is reasonable sub beginning place in the of the statute stance interpretive at the end. appeared part it § If 302 would would have argument pale beyond to which applies. § found in The fact that is not unambiguous language. We should not defeat question case, it is a think that in this where language language where the the actual versus paramount. appears, actual parts 1 and of the The dissent indicates substantially from the former mechan- act borrow "[virtually fact, In all of the sections lien act. ics’ predecessor, part of this statute’s fund was not the current act was a new mechanics’ lien act. Part former in 1982. the enactment of this statute addition with Lien Fund Const v 1993] Brown Opinion Court con are now lien act former mechanics’ parts 3 of the Construction 1 and within tained new creation 190. 2 was a at Part Act.” Post dissent statute. The of this the enactment original quotes the current version of at 193. 1897. Post lien act of mechanics’ essentially has remained that section The fact that *6 century that demonstrates same for almost the parts changed. meaning 1 and Because not has act, it lien former mechanics’ 3 are taken parts. applies § to those that is obvious part applies 2, question § to is whether recovering specific criteria for enumerates equal argued with think it can be the fund. We apply Legislature to had intended that if the force part newly 2, have it would created § 302 to the nearly language has existed for that the amended expressly provide years new for its hundred one application.6 Legislature not the did The fact that meaning language confirms that its amend application changed, and, therefore, § 302 not have parts only applies 1 and 3. that the substantial conclusion

Because of our provision § 302 does not of question part whether 2, the now becomes Appeals on can be based the Court of decision acknowledge §of 302. While we the first sentence language the first that the liberal applies nonetheless the entire we sentence nullify liberality not cannot and should that find unambiguous requirement._ clear and states: The dissent only apply to the Legislature intended §302 If the perfecting under then procedures lien a construction provided placed the act or 302 in have it would language expressly application limiting 302 to 1. of § at 191.] [Post Dissenting Opinion 203(3)(h): the actual We take notice of from the fund shall person A who seeks following: . . . That the con- establish all of subcontractor, per- with whom the or the tractor son is licensed with, contracted claiming the construction lien required by licensed. if law to be [Em- phasis added.] provision construe this liberally cannot

One without particular plaintiff this relief provide There is meaning of the statute. destroying general to indicate that nothing the record during at time any contractor was licensed provision relationship parties. between the steps claimant shall take does not say that, if, he believe subjectively determine or that Therefore, we hold party the other is licensed.7 does not that a liberal construction plaintiff’s claim. save

iii *7 conclusion, 2 of the act does not In because liens, its of construction validity deal with a com- cannot be tested substantial provisions we reverse the deci- pliance Accordingly, standard. Appeals. sion of Court JJ., concurred Levin, Riley, Griffin, Boyle, J. Brickley, majority opin- J. dissent from the Mallett, We themselves to a liberal con- Some of the act do lend struction, degree. particularly question of The where there a .is 203(l)(c) provide example: (cooperating following in the an sections 203(3)(a) (entitled lien), fund), to a construction defense of the (not 203(3)(e) fund), colluding payment obtain from the to § §203(3)(g) (making payment to obtain a reasonable effort subcontractor). or contractor 1993] Lien Fund Const v Dissenting Opinion Court of the decision affirm ion and would majority Appeals. the substantial holds applies only to §302 perfecting lien under a construction for details part against claims and not to the act complete result, adherence 2. As a fund under 203(3) a condi- §in set forth to the precedent the fund. We to tion disagree.

i Act 1980, the Construction Enacted purpose. protective It a dual to achieve seeks aspires right only protect lien claimant’s not to wages payment materials, also or but for to multiple payments the same for landowner from Churchfield, 180 Fischer-Flack, Inc v services. Mich (1989). pream App 606; 447 NW2d pur broadly defined forth its to the act sets ble pose. establish, by lien protect, and enforce An act providing performing labor or rights persons improvement of real equipment for material or property; spect tion lien with re- provide for certain defenses construc- thereto; a homeowner to establish department of recovery fund within powers for the regulation; provide licensing and oflicers; for provide state duties of certain and the assessments pre- occupations; of certain acts and repeal certain penalties; and

scribe parts of acts.

Although preamble au- considered is not construing thority inter- act, it is useful for an scope. purpose preting v East Malcolm (1991); Detroit, NW2d (5th *8 Statutory Singer, Construction 2A Sutherland ed), pp 47.04, 145-150.

188 179 442 Mich Opinion Dissenting A statutory construction rules of fundamental determining applicability of are instructive held occasions, Court has this § 302. several On clear of a statute are that where applied (After Remand), they unambiguous, writ- as are be Corp Gilroy Motors v General ten. (1991); v 271 Selk 341; 475 NW2d

438 Mich 1, 9; 345 Products, 419 Mich NW2d Detroit Plastic (1984). provisions, construing statutory 184 When and effectuate is to discover the court’s task legislative Legislature. intent intent language of a stat- from the actual to ute, derived unambig- is clear and when necessary. interpretation uous, further no Storey Meijer, 429 169 Inc, 431 Mich NW2d v (1988). give ambiguity exists, must a court Where construction reasonable a valid and the statute give any inconsistencies reconcile that will Wagenmaker, parts. 437 Girard v to all of its effect (1991); Aikens v 231, 238; 470 NW2d Mich Dep’t 495, 499; Conservation, 387 Mich (1972). "the A must also ascertain court NW2d designed remedy, it is mischief which evil or construction a reasonable and will purpose.” accomplishes Pittsfield the statute’s best App Twp 99, 105; Saline, 103 Mich v Charter (1981). are to be Remedial statutes NW2d persons liberally in- in favor of the construed Bierbusse v the statute. to be benefitted tended App Group, 34, 37; Ins Farmers (1978). NW2d statutory precepts these

With Act, a lien mind, under the Construction plaintiff must as such claimant recovering from before several elements establish *9 Lien Fund v Const 1993] Dissenting Opinion Mallett, J. Among fund.1

defendant 203(3)(h),2 provides: which 204,[3] has re person who Subject to section precluded from who is of lien and corded a claim (1) subsection lien under recovering a construction the amount the fund recover from may recov person A who seeks lien is established. of the follow establish all the fund shall ery from ing: subcontractor, (h) with or That the contractor lien claiming the construction person whom with, required by law to if is licensed contracted licensed.[4]

be provides a self-contained act 302 of the Section directive. statute, and a remedial declared to be This act is to secure beneficial liberally construed shall be results, intents, act. Substan- purposes of this of this act compliance with tial validity of the construc- for the sufficient shall be act, give and to in this provided for tion liens [Empha- them. to enforce to the court jurisdiction sis added.]_ MCL Section See MCL 570.1203(3)(h); MSA 570.1203(3); MCL 570.1204; MSA MSA 26.316(203)(3)(h). 26.316(203X3). 26.316(204), provides: pay to subcontrac- department out of the fund shall not $75,000.00 per

tors, residen- suppliers, more than and laborers appears claimed from the amount tial structure. When the structure, respect will exceed to a residential delay payment $75,000.00, may until the total department If the total amount paid ascertained. can be amount subcontractors, suppliers, laborers exceeds payable $75,000.00, proportional of that they paid shares their shall be amount. 339.2401; 18.425(601), 339.601; MSA MCL MSA See MCL 18.425(2403). 339.2403; 18.425(2401), and MCL Dissenting Opinion Mallett, the substantial to ascertain whether We are asked applies §to § 302 .5 the act B separated into Lien Act The Construction parts.6 act borrow 1 and 3 of the three Parts substantially lien act.7 the former mechanics’ repeal following lien mechanics’ fact, In "disposition Legislature provided table” *10 corresponding in the sections indicates Virtually all of the sections Lien Act. Construction of now con lien act8 are the former mechanics’ parts 1 3 of the Construction and tained within Thus, 3 of the Construction Lien Act. including 302, of Act, was a substantial original particularized laws, consisted of lien mechanics’ qualifications

procedures for and recovery of a lien. entirely of new set 2 of the act was an Part adoption in at the time of the act’s concerning disagreement term "substantial whether the 5 There is Churchfield, ambiguous compliance” See Fischer-Flack v nature. (the ambiguous). phrase compliance”

supra Cf. "substantial at 611 Associates, App unambiguous). Co v Turner-Fisher Norcross (1987) (the language of 302 is clear and NW2d extrapolate However, upon today to the term is not called this Court plaintiff’s compliance” actions or determine whether the "substantial conform to that term’s definition. 26.316(101)- 570.1101-570.1128; act, MSA 6 Part 1 of the MCL 26.316(128), filing 570.1201-570.1207; procedures ery 26.316(305), guidelines procedures for establishes detailed act, recovery MCL liens. Part of construction 26.316(201)-26.316(207), provides creates and MSA recovery lien recov the homeowner construction for under 26.316(301)- act, 570.1301-570.1305; MCL MSA fund. Part 3 of the application and construction. sets forth the act’s 26.281-26.310, 570.1-570.30; repealed by 1980 PA MCL MSA §303. inconsequential exceptions a of the that did not become The (liens upon 570.2; land MCL MSA 26.282 Construction Lien Act are 26.284(1)(false 570.4a; wife); by jointly MCL husband and held defraud); 570.28; by intent to MCL made contractor with statements MSA 26.308 (notice proceedings by publication). 1993] Lien Fund v Const by Dissenting Opinion Mallett, homeowner the defendant 1982. Part established promulgated rules and fund and lien fund, procedures its administration. for periodic resi on various assessments financed Depart licensees, was created within dential Regulation.9 Licensing fund cre ment against an action to foreclose ated defenses Thus, con lien. while a residential may entirely valid, homeowners lien struction may protect multiple payments from themselves indicating they paid filing an affidavit department cooperated with the contractor and not colluded and have the defense of person payment any other to obtain purposes, importantly present fund.10 More provides remedy for lien fund also defendant precluded from otherwise be claimants who would recovering of the lien because a construction protection under the act. homeowner’s imprecise § 302 and the Given unique statutory history becomes Legislature’s quite intention difficult to discern the plain language Clearly, of the statute. designed protect the conscien In from fraudulent contractors. tious tradesmen *11 purpose, attempt this this Court an should to achieve § and 302 a liberal construction applicable part 2 If the it of the act. find that is Legislature only apply the §302 intended that perfecting procedures part lien under for a construction placed part § in 1 of 1, it 302 then would have limiting language expressly provided the the act or application that the § 302 to 1. We believe of placement more in 3 of the act was of 302 9 Licensing Regulation Department now known as the is Regulation. Occupational See Executive and Professional Bureau of No. 1991-9. Order 10 26.316(203X1). 570.1203(1); MCL 442 179

192 Mich Dissenting Opinion Mallett, utility”;11 deliberate, it was than "a matter of a Legislature, on the affirmative decision evidencing applicable § 302 its intention that be including part throughout 2. provision statutory its en

A be read in should tirety with rest in connection provision statute, an act to be read and each is every provision as so with reference other produce an In re Forfeiture of harmonious whole. (1989); 242, $5,264, 251; 432 439 246 Mich NW2d Ass’n, v Police 408 Mich Detroit Detroit Officers (1980). words, 481; 68 In 294 other due NW2d given be to all sections to consideration must produce an harmonious and consistent enactment Dep’t Treasury, v of the entire statute. Preston (1991). Reading App 491; 476 455 190 Mich NW2d entirety, in its the Construction Act applicable to. should made clear 302 be includ for collection from 203(3)(h).12 ing § urges a

The defendant this Court to consider development of line of that illustrate the cases compliance Contrary to the doctrine.13 substantial defendant’s

assertions, substantial judicially In mechanics’ not a lien act of rent created doctrine. original

1897,14 the cur version of appears § 302 in 27._ 11Ante at 184. 12Admittedly, difficulty requiring in is an inherent subcon- there comply statutory provision substantially re- tractor quires However, party. another this Court is not licensure of compli- upon today called to determine the standard substantial 203(3)(h). fact, adequate safeguards may, in There ance with § difficulty remedy any application. place within the statute Metal, Dufty Properties, Michigan Roofing Inc v Rd & Sheet 732; (1979), App 409 Mich Mich 282 NW2d 809 vacated remanded (On Remand) 577; (1980), App 887; 295 NW2d 230 Mich (1981); (1980), F Hoste v lv den 412 Mich 872 Bernard NW2d (1982);

Kortz, 448; App Superior American 117 Mich 324 NW2d (1983). Fry, App Homes v 343 NW2d

14 1897PA 143. *12 Fund v Const Lien 1993] Dissenting Opinion remedial to be a hereby declared This act liberally to secure construed statute and thereof; results, purposes and intents beneficial pro- compliance with its several and a substantial validity for the be sufficient visions shall for, give provided hereinbefore lien or liens enforce the same. to the courts to jurisdiction PA [1897 143.] state for

Thus, has existed this the doctrine role has an essential played nearly century lien laws. development property proffered by the cases to follow We decline residen involve the then-existent defendant which Act or act,15 Construction Lien not the tial builders theory behind predecessor. .licensure cases, recovery In those is deterrence. requirement By an unlicensed contractor. being sought by was contractor, to an unlicensed a claim denying unlicensed enti sought discourage Legislature De in residential construction. engaging ties from denying plain not be achieved by terrence would pur from the fund Plumbing recovery tiff Brown Lien Act. Brown Plumb to the Construction suant contributed to the ing fully licensed and Primus Energy denied because of but was Legislature licensure. Should the Homes’ lack of compli that strict and not substantial determine in the fu required ance with shall be ture, made. change easily can be would affirm the decision of the

Accordingly, we trial court Appeals properly Court disposition plaintiff’s summary motion granted 2.116(C)(9) (10). to MCR On the basis pursuant construction, and the statutory the rules of Act, we remedial nature of the Construction to sub- it is sufficient for a lien claimant believe MCL 338.1501 et seq.; 18.86(101) et seq. 442 Mich 179 *13 Dissenting Opinion by Mallett, J. re- in order stantially comply Lien Re- from the Homeowner Construction cover Fund. covery C.J.,

Cavanagh, concurred with

Case Details

Case Name: Brown Plumbing & Heating, Inc v. Homeowner Construction Lien Recovery Fund
Court Name: Michigan Supreme Court
Date Published: May 18, 1993
Citation: 500 N.W.2d 733
Docket Number: 92347, (Calendar No. 5)
Court Abbreviation: Mich.
AI-generated responses must be verified and are not legal advice.