Lead Opinion
{¶ 1} In this appeal arising from a public-road-construction contract, we consider our precedent on contractual liquidated-damages provisions. We expressly extend that precedent to public-works contracts, vacate the judgment of the court of appeals, and remand this cause to that court for reconsideration in light of our opinion.
Relevant Background
{¶ 2} In 2007, appellant, the village of Piketon, solicited bids for the “Pike Hill Roadway and Related Improvements” project. The project included the installation of a traffic light at the intersection of U.S. Route 23 and Market Street in Piketon and improvements to the roadway.
{¶ 4} The date of commencement of the project was set for July 30, 2007. Thus, the contract required that the project be substantially completed 120 days later on November 27, 2007. Piketon granted Boone Coleman’s first request for an extension, which moved the completion date to May 30, 2008. But when Boone Coleman sought another extension, Piketon refused to grant it and notified Boone Coleman that it would assess the contractually specified liquidated damages of $700 per day if the project was not completed by May 30, 2008. Boone Coleman did not finish the project by then and on July 7, 2008, Piketon informed Boone Coleman that it was assessing damages of $700 per day as of May 31, 2008, until the completion of the project.
{¶ 5} Boone Coleman did not complete the project until July 2, 2009 — well over a year (397 days) after the parties’ extended completion date of May 30, 2008.
{¶ 7} Piketon moved for summary judgment. The trial court granted Piketon’s motion and entered judgment in its favor, awarding Piketon $277,900 in liquidated damages.
{¶ 8} Boone Coleman appealed, asserting that the trial court erred in awarding Piketon liquidated damages. The appellate court agreed. Citing our decision in Samson Sales, Inc. v. Honeywell, Inc.,
{¶ 9} We granted Piketon’s request for discretionary review and agreed to address two related propositions of law:
When evaluating the enforceability of a liquidated damages provision in a construction contract, the court must conduct its analysis prospectively, based on the per diem amount of the liquidated damages at the time the contract is executed, and not retrospectively, based on the total liquidated damages that ultimately accrue.
*453 Liquidated damages are not deemed a penalty simply because a project consists of new construction of an improvement that did not exist previously and no proof of actual damages is required to enforce liquidated damages pursuant to such a contract.
See
Analysis
Standard of Review for Contractual Liquidated-Damages Provisions
{¶ 10} We review the interpretation of a contract, a question of law, de novo. Arnott v. Arnott,
Substantive Law on Liquidated Damages
{¶ 11} Simply stated, liquidated damages are damages that the parties to a contract agree upon, or stipulate to, as the actual damages that will result from a future breach of the contract. Sheffield-King Milling Co. v. Domestic Science Baking Co.,
{¶ 12} “ ‘The effect of a clause for stipulated damages in a contract is to substitute the amount agreed upon as liquidated damages for the actual damages resulting from breach of the contract, and thereby prevents [sic] a controversy between the parties as to the amount of damages.’ ” Dave Gustafson & Co., Inc. v. South Dakota,
{¶ 13} The common law viewed liquidated-damages provisions “with a gimlet eye,” Dist. Cablevision Ltd. Partnership v. Bassin,
{¶ 14} “Today the law does not look with disfavor upon ‘liquidated damages’ provisions in contracts. When they are fair and reasonable attempts to fix just
{¶ 15} Part of the appeal of liquidated-damages provisions is that they allow the contracting parties to “protect themselves against the difficulty, uncertainty, and expenses that necessarily follow judicial proceedings when trying to ascertain damages.” Carrothers Constr. Co.,
{¶ 16} Ohio has long recognized liquidated-damages provisions as valid and enforceable, see Samson Sales,
{¶ 17} In addressing whether a contract includes a permissible liquidated-damages provision or an unenforceable penalty, one of our appellate courts has explained that a “penalty” is
“a sum inserted in a contract, not as the measure of compensation for its breach, but rather as a punishment for default, or by way of security for actual damages which may be sustained by reason of nonperformance, and it involves the idea of punishment. A penalty is an agreement to pay a stipulated sum on breach of contract, irrespective of the damage sustained. Its essence is a payment of money stipulated as in terrorem of the offending party, while the essence of liquidated damages is a genuine*455 covenanted, pre-estimate of damages. The amount is fixed and is not subject to change; however, if the stipulated sum is deemed to be a penalty, it is not enforceable and the nondefaulting party is left to the recovery of such actual damages as he can prove.”
(Emphasis sic.) Piper v. Stewart & Inlow, 5th Dist. Licking No. CA-2530,
{¶ 18} In Samson Sales, we set forth Ohio’s tripartite test to determine whether a contractual provision should be considered a liquidated-damages provision or an unenforceable penalty. We held:
Where the parties have agreed on the amount of damages, ascertained by estimation and adjustment, and have expressed this agreement in clear and unambiguous terms, the amount so fixed should be treated as liquidated damages and not as a penalty, if the damages would be (1) uncertain as to amount and difficult of proof, and if (2) the contract as a whole is not so manifestly unconscionable, unreasonable, and disproportionate in amount as to justify the conclusion that it does not express the true intention of the parties, and if (3) the contract is consistent with the conclusion that it was the intention of the parties that damages in the amount stated should follow the breach thereof.
Samson Sales,
{¶ 19} Valid and enforceable liquidated-damages provisions are those intended by the parties to give reasonable compensation for damages, but provisions that impose amounts that are “manifestly inequitable and unrealistic” are deemed unenforceable penalties. Id. at 28. Since Samson Sales, we have reiterated its holding once, in Lake Ridge Academy v. Carney,
Liquidated Damages in Public-Works-Construction Contracts
{¶ 20} The benefits of liquidated-damages provisions in building and construction contracts are well documented. R. Harper Heckman & Benjamin R. Edwards, Time is Money: Recovery of Liquidated Damages by the Owner, 24 Constr.Lawyer 28, 29 (Fall 2004). The provisions create firm expectations and allow the parties to allocate damages caused by delays in completing construction. Id. The ability to agree about damages is particularly important in public-works-
{¶ 21} In a public-roadway-construction contract, each delay in completing the project adds to inconvenience, increased costs, and loss of use of the roadway. Dave Gustafson & Co.,
{¶ 22} We recognize that liquidated-damages provisions in public-construction projects play an important civic purpose in that they help foster timely completion of the projects, thereby avoiding the loss of billions of taxpayers’ dollars caused by contractors’ delays. See, e.g., Scott M. Tyler, No (Easy) Way Out: “Liquidating” Stipulated Damages for Contractor Delay in Public Construction Contracts, 44 Duke L.J. 357, 358-359 (1994); Christian, Public Entities in Nevada Beware, 12-OCT Nevada Lawyer 16. We are not alone in that recognition. The Supreme Court and many state and federal appellate courts also recognize that liquidated-damages provisions in public contracts are particularly valuable given the unique difficulty in calculating the damages associated with a public contractor’s breach of its promise to timely complete a public-improvement project. See, e.g., Priebe & Sons,
{¶ 24} With these principles in mind, we turn to the appellate court’s opinion in this case.
The Appellate Court’s Analysis of the Liquidated-Damages Provision
{¶ 25} In considering whether the liquidated-damages provision in this case constituted an unenforceable penalty, the court of appeals properly applied the first and third parts of the test in Samson Sales,
{¶ 26} Even though the appellate court had already determined that the provision reflected the parties’ intentions, the appellate court focused solely on the aggregate amount of the penalty, $277,900, in relation to the total value of the contract, $683,300. See
{¶ 27} First, the appellate court relied heavily on a decision of one of its sister courts, Harmon v. Haehn, 7th Dist. Mahoning No. 10 MA 177,
{¶ 29} Here, Harmon is of limited value because it arose from a private commercial real-estate lease rather than a public-works-construction contract.
{¶ 30} Moreover, Harmon involved a liquidated-damages provision that contemplated a lump sum. Piketon and Boone Coleman did not contract for a lump sum. Rather, the parties contracted for a per diem measure of damages which, as Chief Justice Marshall recognized, is more likely to be an enforceable liquidated-damages provision than an unenforceable penalty: “[T]he agreement to pay a specified sum weekly during the failure of the party to perform the work, partakes much more of the character of liquidated damages than the reservation of a sum in gross.” Tayloe v. T. & S. Sandiford,
{¶ 31} More importantly, the appellate court’s myopic focus on the reasonableness of the total amount of liquidated damages in application, rather than on the reasonableness of the per diem amount in the contract terms, was not proper. The correct analysis looks at whether it was conscionable to assess $700 per day in liquidated damages for each day that the contract was not completed rather than looking at the aggregate amount of the damages awarded. Accord Carrothers Constr. Co.,
{¶ 32} Although per diem amounts vary greatly in the case law, courts have upheld liquidated-damages provisions in public-construction contracts with per diem amounts similar to those at issue here. See, e.g., Sec. Fence Group, Inc. v. Cincinnati, 1st Dist. Hamilton No. C-020827,
{¶ 33} Moreover, the per diem liquidated damages imposed by the contract between Piketon and Boone Coleman reflect the Ohio Department of Transportation’s 2013 Construction and Material Specifications. Those specifications not only require liquidated damages to be deducted from any sum owed the contractor for each day by which the contractor exceeds the completion date, but set out the specific amount of the per diem damages.
{¶ 35} We reaffirm that Ohio law requires a court, when considering a liquidated-damages provision, to “examine it in light of what the parties knew at the time the contract was formed.” Jones,
{¶ 36} This prospective or “front end” analysis of a liquidated-damages provision focuses on the reasonableness of the clause at the time the contract was executed rather than looking at the provision retrospectively, i.e., ascertaining the reasonableness of the damages with the benefit of hindsight after a breach. See generally Heckman & Edwards, 24 Constr.Law. at 30-31; Hovas Constr.,
{¶ 38} By the appellate court’s reasoning, the same provision might have been enforceable if Boone Coleman’s delay had been briefer, e.g., two days, two weeks, or even two months, but not so long as to accrue the significant damages that arose here. It is a perverse rule of law to hold that a court can relieve a breaching party of the consequences it agreed to by refusing to enforce a per diem liquidated-damages provision solely because the breach was an egregious one. We decline to adopt that rationale, and we vacate the judgment of the appellate court in this cause.
{¶ 39} We remind our appellate courts that in engaging in prospective analysis, the appellate court’s role is not to determine what the parties should have contracted for based on the court’s understanding of the damages after the breach. Lake Ridge Academy,
*462 “The parties themselves best know what their expectations are in regard to the advantages of their undertaking and the damages attendant on its failure, and when they have mutually agreed on the amount of such damages in good faith and without illegality, it is as much the duty of the court to enforce that agreement as it is the other provisions of the contract.”
Sheffield-King Milling Co.,
Conclusion
{¶ 40} Benjamin Franklin advised us to remember that “time is money.” United States v. One 1971 Corvette Stingray, E.D.Pa. No. 89-5398,
{¶ 41} Boone Coleman entered a contract that required it to perform the project within 120 days. It took four times that long to do so. It may not avoid the result of the valid liquidated-damages provision it negotiated through able counsel. “There is no sound reason why persons competent and free to contract may not agree upon this subject [of liquidated damages] as fully as upon any other, or why their agreement, when fairly and understandingly entered into with a view to just compensation for the anticipated loss, should not be enforced.” Wise,
{¶ 42} The appellate court erred in its use of a retrospective analysis to find that the total amount of damages awarded to Piketon was so unreasonable as to constitute a penalty, and in failing to focus on the per diem nature of the liquidated damages. Accordingly, we vacate the judgment of the Fourth District Court of Appeals and remand the cause to that court to reconsider the enforceability of the liquidated-damages provision in light of this opinion.
Judgment vacated and cause remanded.
Notes
. The relevant provisions of the contract stated:
ARTICLE 4 — CONTRACT TIMES
4.01. Time of the Essence
A. All time limits for Milestones, if any, Substantial Completion, and completion and readiness for final payment as stated in the Contract Documents are of the essence of the Contract.
4.02 Days to Achieve Substantial Completion and Final Payment
A. The Work will be substantially completed within 120 days after the date when the Contract Times commence to run as provided in paragraph 2.03 of the General Conditions, and completed and ready for final payment in accordance with paragraph 14.07 of the General Conditions within 120 days after the date when the Contract Times commence to run.
4.03 Liquidated Damages
A. CONTRACTOR and OWNER recognize that time is of the essence of this Agreement and that OWNER will suffer financial loss if the Work is not completed within the time(s) specified in paragraph 4.02 above, plus any extensions thereof allowed in accordance with Article 12 of the General Conditions. The parties also recognize the delays, expense, and difficulties involved in proving in a legal or arbitration [proceeding] the actual loss suffered by OWNER if the Work is not completed on time. Accordingly, instead of requiring any such proof, OWNER and CONTRACTOR agree that as liquidated damages for delay Gout not as a penalty), CONTRACTOR shall pay OWNER $700.00 for each day that expires after the time specified in paragraph 4.02 for Substantial Completion until the Work is substantially complete.
(Boldface, underlining, and capitalization sic.)
. In its complaint, Boone Coleman asserted that the liquidated-damages provision was a penalty and also argued that it should have been awarded additional compensation based on work it performed to correct subsurface road problems and to perform revisions on the retaining wall and traffic signal. The trial court denied that relief and the appellate court affirmed, holding that “Boone Coleman did not follow the parties’ unambiguous notice provisions to claim additional compensation. And the contract explicitly precluded recovery for additional costs related to subsurface conditions encountered by Boone Coleman.”
. The Ohio Department of Transportation’s 2013 document entitled “Construction and Material Specifications” is available at http://www.dot.state.oh.us/Divisions/ConstructionMgt/Specifieation% 20Files/2013% 20CMS% 2011142012% 20FINAL.PDF. Section 108.07 provides:
Failure to Complete on Time. If the Contractor fails to complete the Work by the Completion Date, then the Director, if satisfied that the Contractor is making reasonable progress, and deems it in the best interest of the public, may allow the Contractor to continue in control of the Work. The Department will pay the Contractor for Work performed on the Project less any liquidated damages incurred.
(Boldface sic.)
The 2013 schedule of liquidated damages, found in Table 108.07-1, provides that the amount of liquidated damages to be deducted for each calendar day of an “overrun in time” varies depending on the original amount of the contract. For contracts between 0 and $500,000, the amount of per diem liquidated damages is $500; for contracts between $500,000 and $2,000,000, the amount of per diem liquidated damages is $1,000; for contracts between $2,000,000 and $10,000,000, the amount of
Concurrence Opinion
concurring.
{¶ 43} I agree with the majority opinion. However, I would exclude the first paragraph of the majority’s conclusion.
{¶ 44} Therefore, I respectfully concur.
Dissenting Opinion
dissenting.
{¶ 45} We should dismiss this case as having been improvidently accepted and allow the court of appeals decision to stand. That court reached a sound and proper conclusion that is fair to both parties. Furthermore, no new legal issue is at stake.
{¶ 46} Instead, this court has taken a bad situation and made it worse. Boone Coleman already suffered a loss from performing additional work for which it was not paid. On top of that, this court now determines that Boone Coleman must pay a penalty because it didn’t complete the contract on time, never mind that Boone Coleman claims that part of the problem was that Piketon provided inaccurate site information. This is akin to frontier justice: we do it because we can, not because it makes sense.
{¶ 47} Barring a dismissal, the sensible approach to this case, the approach taken by the court of appeals, is to declare the liquidated-damages clause to be unreasonable and disproportionate. Equities do matter — even in a contract case. Given the circumstances of this case, which include Piketon allegedly providing inaccurate site plans to Boone Coleman, the court of appeals got it right. It disallowed Boone Coleman’s requests for additional payment because they were not properly submitted and refused to enforce the liquidated-damages clause because it was so unreasonable and disproportionate as to amount to a penalty.
{¶ 48} Because the court is neither dismissing the ease nor affirming the court of appeals, I dissent.
