History
  • No items yet
midpage
Boone Coleman Construction, Inc. v. Village of Piketon
50 N.E.3d 502
Ohio
2016
Read the full case

Background

  • Piketon contracted with Boone Coleman for a $683,300 public road/traffic-signal project with an express 120‑day substantial‑completion deadline and a $700 per day liquidated‑damages clause.
  • Commencement was July 30, 2007; initial 120‑day deadline extended once to May 30, 2008; Piketon refused a further extension and began assessing $700/day from May 31, 2008.
  • Boone Coleman completed the work on July 2, 2009, 397 days after the extended completion date; Piketon claimed $277,900 in liquidated damages and moved for summary judgment, which the trial court granted.
  • The Fourth District reversed, holding the liquidated‑damages award (about one‑third of the contract price) was an unenforceable penalty based on the aggregate amount.
  • The Ohio Supreme Court granted review to decide whether enforceability should be judged prospectively (per‑diem at contracting) and whether public‑works contracts change the analysis; it vacated the appellate judgment and remanded.

Issues

Issue Plaintiff's Argument (Boone Coleman) Defendant's Argument (Piketon) Held
Whether the clause is an unenforceable penalty or enforceable liquidated damages The clause is a penalty because the aggregate assessment ($277,900) is disproportionate to the contract price The clause is a valid per‑diem liquidated‑damages provision enforceable as written; analysis should focus on reasonableness at formation Enforceability judged prospectively; court must assess per‑day amount at contracting, not aggregate hindsight; appellate court erred reversing on aggregate amount
Proper temporal lens for analysis (prospective v. retrospective) Court should consider actual accrued total damages to determine disproportionality Court should analyze reasonableness based on facts known when contract was formed (per‑diem) Use prospective (front‑end) analysis based on parties’ expectations at formation; retrospective aggregate focus is improper
Whether public‑works context affects enforceability analysis Public nature does not justify per‑diem here given alleged factual inequities Public‑works contracts justify deference to liquidated damages because actual public damages are hard to quantify Public‑works context weighs in favor of enforcing reasonable liquidated‑damages clauses; legislature and precedent support this view
Whether per‑diem vs lump‑sum structure matters Aggregate result controls regardless of per‑diem form Per‑diem structure is more indicative of liquidated damages (not a lump‑sum punitive reservation) and should be evaluated per day Per‑diem measures are more likely to be enforceable; courts must examine the per‑day rate’s reasonableness at formation, not the total incurred amount

Key Cases Cited

  • Samson Sales, 12 Ohio St.3d 27 (sets Ohio tripartite test for liquidated damages vs. penalty)
  • Lake Ridge Academy v. Carney, 66 Ohio St.3d 376 (reiterates Samson Sales and prospective reasonableness standard)
  • Priebe & Sons, Inc. v. United States, 332 U.S. 407 (liquidated damages are permissible when damages are uncertain)
  • Wise v. United States, 249 U.S. 361 (courts should enforce fair, deliberate liquidated‑damages agreements made by informed parties)
  • Sheffield‑King Milling Co. v. Domestic Science Baking Co., 95 Ohio St. 180 (historical discussion of stipulated damages and enforcement)
  • Carrothers Construction Co. v. South Hutchinson, 288 Kan. 743 (public‑works damages are uniquely difficult to quantify; prospective analysis of per‑diem reasonable)
Read the full case

Case Details

Case Name: Boone Coleman Construction, Inc. v. Village of Piketon
Court Name: Ohio Supreme Court
Date Published: Feb 24, 2016
Citation: 50 N.E.3d 502
Docket Number: 2014-0978
Court Abbreviation: Ohio