Lead Opinion
{¶ 2} We conclude that the board's extension of Black Fork's certificate constitutes an amendment and that the board acted unlawfully in granting Black Fork's motion rather than following the statutory procedures for amending a certificate. Because this error prejudiced appellants, we reverse the board's orders and remand this cause for further proceedings consistent with this opinion.
Facts and Procedural Background
{¶ 3} This is the second appeal involving the proposed Black Fork Wind Energy Project. As we previously explained:
In March 2011, Black Fork filed an application to construct a wind farm consisting of up to 91 turbines in portions of Crawford and Richland Counties. In addition to the turbines, Black Fork's project includes access roads, electrical collection lines, a construction-staging area, a concrete-batch plant, a substation, and an operation and maintenance facility. The project area covers approximately 24,000 acres of land, and the facilities will be located on approximately 14,800 acres of leased private land with 150 participating landowners. According to Black Fork's application, voluntary agreements have been signed by the participating property owners within the project area. Black Fork claims that the facility will provide up to 200 megawatts of renewable energy "with effectively zero air emissions and waste generation."
In re Application of Black Fork Wind Energy, L.L.C. ,
{¶ 4} After Black Fork filed its initial application, several local political subdivisions and individuals-including the appellants in this case, who claimed to live near the leased land or within the project boundaries-intervened in the board proceeding. In October 2011, the board conducted an evidentiary hearing, and in January 2012, it granted Black Fork a certificate to construct the proposed wind farm.
{¶ 5} The board's order adopted stipulated conditions agreed to by several of the parties and the board's staff (but not by the appellants in this case), including "condition No. 70," which stated that the certificate "shall become invalid if the Applicant has not commenced a continuous course of construction of the proposed facility within five (5) years of the date of journalization of the certificate." Because the board journalized its decision on January 23, 2012, Black Fork had until January 23, 2017, to commence construction.
{¶ 6} Five of the seven appellants involved in the present case appealed to this court, but in December 2013, we affirmed the board's order granting Black Fork's certificate. See Black Fork Wind Energy at ¶ 23-24.
{¶ 7} On September 12, 2014, Black Fork filed the motion that is the subject of this appeal with the board under the same case number (No. 10-2865-EL-BGN) in which Black Fork's certificate had been granted, seeking to extend its certificate by two years, with a new commencement-of-construction deadline of January 23, 2019. Black Fork argued that the delay caused by the prior appeal to this court combined with recent changes in the energy market had hampered its ability to commence construction of the project. Most of the appellants-who were then acting pro se-filed responses opposing Black Fork's motion to extend the certificate.
{¶ 9} As will be explained more fully below, Ohio law requires the board's staff to investigate any application to amend a siting certificate and to issue a report of its findings. Accordingly, the board's staff investigated Black Fork's amendment application in case No. 14-1591-EL-BGA and, in August 2015, filed a report recommending approval of the application. Later that month, on August 27, 2015, the board issued an order formally approving it. Notably, the board determined that the turbine-setback requirements in place at the time it initially certified Black Fork's proposed wind farm continued to apply to Black Fork's project-notwithstanding the legislature's enactment of a more stringent
{¶ 10} About seven months later, on March 24, 2016, the board in the case now before us granted Black Fork's motion to extend the certificate. Appellants filed a rehearing application, which the board denied in an order issued on February 2, 2017. Appellants then filed this appeal, raising four propositions of law. We granted Black Fork's motion for leave to intervene to defend the board's orders.
{¶ 11} We will reverse, modify, or vacate an order of the Power Siting Board "only when our review of the record reveals that the order is unlawful or unreasonable." In re Application of Champaign Wind, L.L.C. ,
R.C. Chapter 4906 and related Administrative Code provisions
{¶ 12} The board has exclusive authority to issue certificates of environmental compatibility and public need for construction, operation, and maintenance of "major utility facilities" such as the proposed wind farm at issue in this case. In re Application of Buckeye Wind, L.L.C. ,
{¶ 13} Most importantly for purposes of this case, to commence the amendment process, a litigant must first file an application with the board that is "in such form and contain[s] such information as the board prescribes." R.C. 4906.06(E). Applications for amendments must contain the information enumerated in R.C. 4906.06(A) and must "be submitted in the same manner as if they were applications for a certificate." Former Ohio Adm.Code 4906-5-10(B), 2008-2009 Ohio Monthly Record 2-4257. After receiving an amendment application, board staff must investigate the application and submit a report containing recommended
{¶ 14} The parties here appear to agree on the correct process for amending a certificate. They disagree, however, on the meaning of "amendment" and, more specifically, on whether extending a certificate constitutes an "amendment" of the certificate. Neither the Revised Code in Chapter 4906 nor the board's applicable administrative rules define what constitutes an "amendment" or when an amendment is necessary. Accordingly, the primary issue before us is whether the board's two-year extension of Black Fork's certificate amounted to an "amendment" of that certificate.
The two-year certificate extension amounted to an amendment
{¶ 15} Appellants assert that extending Black Fork's certificate was an "amendment" because it modified a material condition of the original certificate-namely, the five-year commencement-of-construction deadline of condition No. 70. Therefore, in their first proposition of law, appellants assert that the board acted unreasonably and unlawfully by amending Black Fork's certificate through the motion Black Fork filed rather than by following the statutory process for amending a certificate. In their second proposition of law, appellants assert that the board lacked authority to alter, waive, or dispense with the statutory procedures.
{¶ 16} In response, the board argues that because R.C. Chapter 4906 does not define "amendment," the board-as the agency entrusted to enforce power-siting laws-has broad discretion to determine whether a particular change to a certificate should be regarded as an "amendment." In consideration of the entire statutory scheme, the board asserts in its brief that "a proposed change to the facility is required" for a change "to constitute an amendment." (Emphasis sic.) And because a "decision whether to modify a procedural timeline involves no change to the facility," the board asserts that the statutory process for amending a certificate was not invoked and did not need to be followed in this case. According to the board, the legislature did not expect the board to "re-litigate a case over a mere timing issue."
{¶ 18} Black's Law Dictionary defines "amendment" as "[a] formal and usu. minor revision or addition proposed or made to a statute, constitution, pleading, order, or other instrument; specif., a change made by addition, deletion, or correction; esp., an alteration in wording." Black's Law Dictionary 98 (10th Ed.2014). Webster's Third New International Dictionary defines "amendment" as the "act of amending esp. for the better; correction of a fault or faults; reformation," "the process of amending (as a motion, bill, act, or constitution)," and "an alteration proposed or effected by such process." Webster's Third New International Dictionary 68 (2002). And "amend" is defined as "to change or alter in any way esp. in phraseology" or "to alter (as a motion, bill, or law) formally by modification, deletion, or addition."
{¶ 19} Under any common, ordinary, and accepted meaning, the board's actions here amounted to an "amendment" of Black Fork's certificate. In its order approving the original certificate, the board adopted condition No. 70, which provided that "[t]he certificate shall become invalid if the Applicant has not commenced a continuous course of construction of the proposed facility within five (5) years of the date of journalization of the certificate." In the orders on appeal, the board altered this deadline by giving Black Fork two additional years to start constructing the proposed wind project and it therefore revised the certificate's original expiration date from January 23, 2017, to January 23, 2019. In other words, the board amended condition No. 70 by changing the compliance deadline.
{¶ 20} Because the board is a creature of statute, it can exercise only those powers the legislature confers on it. See Discount Cellular, Inc. v. Pub. Util. Comm. ,
{¶ 22} Accordingly, we conclude that the board's two-year extension of the certificate amounted to an "amendment" and that the board therefore acted unlawfully by failing to comply with the statutory process for amending a certificate.
Appellants have established prejudice
{¶ 23} This court will not reverse an order of the board "unless the party seeking reversal shows that it has been or will be harmed or prejudiced by the order." In re Complaint of Buckeye Energy Brokers, Inc. v. Palmer Energy Co. ,
{¶ 24} Appellants were harmed in at least two ways. First, they never received the benefit of a staff investigation and report regarding Black Fork's specific request to extend the certificate for two years past the initial expiration date. We have explained that the purpose of a staff report-in that case, in the context of a public utility's rate-increase application-is " 'to facilitate meaningful contest of rate increase applications by providing interested parties with the materials necessary for an informed challenge.' "
{¶ 25} Second, appellants have shown a realistic possibility of a different outcome but for the board's error in extending Black Fork's certificate by granting Black Fork's motion. For example, had the board treated the motion for an extension as an application for an amendment, the current setback provisions in R.C. 4906.20 and 4906.201 may have been triggered. Alternatively, appellants assert that a consequence of the board's error in granting
Appellants' remaining propositions of law
{¶ 26} In appellants' third proposition of law, they assert that the board may not extend a certificate absent a showing of good cause and that "because the Board's staff failed to generate the required report of its investigation, there has been no showing of good cause justifying the extension." Because we determine that the board erred by not following the statutory process for amending a certificate, we need not reach this issue.
{¶ 27} In their fourth proposition of law, appellants claim that the board's orders in the present case and also those issued in the related proceedings have permitted Black Fork to evade the current turbine-setback provisions in R.C. 4906.20(B)(2) and 4906.201, and appellants seek an instruction from this court directing the board to apply the current setback provisions "to any amendment of Black Fork's certificate." Black Fork proffers statutory-construction arguments and arguments based on the Ohio Constitution to oppose application of those setback requirements to its project. The board argues that the setback issues are "irrelevant" to the narrow question before the court in this appeal, but it has nonetheless moved for leave to file a surreply brief to address one-but not all-of Black Fork's constitutional challenges to R.C. 4906.20 and 4906.201.
{¶ 28} R.C. 4906.201(B)(2) provides that the current setback provisions apply to "[a]ny amendment made to an existing certificate after the effective date" of the
{¶ 29} We have long held that "[c]onstitutional questions will not be decided until the necessity for a decision arises on the record before the court." State ex rel. Herbert v. Ferguson ,
{¶ 30} In sum, for the reasons explained above, we hold that the board acted unlawfully by extending Black Fork's certificate
Orders reversed and cause remanded.
O'Connor, C.J., and French, J., concur.
Kennedy, J., concurs, with an opinion joined by DeWine, J.
Fischer, J., dissents, with an opinion joined by O'Donnell, J.
Notes
On August 25, 2017, we granted Black Fork's motion to supplement the appellate record in this case with the board's record for case No. 14-1591-EL-BGA.
Although not part of the record on appeal in the present case, the parties recognize and refer to the fact that after appellants commenced this appeal, Black Fork filed another application to amend its certificate, which created a third related proceeding before the board, under a new case number (No. 17-1148-EL-BGA). In the third proceeding, Black Fork sought to use a new version of one of its previously approved turbine models, and it also asked the board to extend the certificate by another year-from January 23, 2019, to January 23, 2020. The board approved Black Fork's application in case No. 17-1148-EL-BGA on December 7, 2017, and issued an order denying an application for rehearing on June 21, 2018. On August 9, 2018, the appellants in that case-the same seven individuals who are appealing the orders in the present case-appealed those board orders to this court. That appeal is currently pending as case No. 2018-1134.
Although the board amended and renumbered former Ohio Adm.Code 4906-5-10 (see Ohio Adm.Code 4906-3-11 and 4906-6-12 ) and 4906-5-05 (see Ohio Adm.Code 4906-3-06 ), 2015-2016 Ohio Monthly Record 2-1890 and 2-1896, effective December 11, 2015, the former rules remain applicable to this case because they were in effect at the time Black Fork filed its September 12, 2014 motion to extend the certificate for its proposed wind farm.
Concurrence Opinion
{¶ 31} I agree with and join the majority opinion's analysis applying the plain meaning of the word "amendment" as well as its conclusion that the appellants in this case were prejudiced when the Power Siting Board extended the certificate issued to Black Fork Wind Energy, L.L.C., to construct a wind farm without first requiring Black Fork to file an application to amend the certificate. I write
{¶ 32} This case presents a straightforward question of statutory interpretation. Our duty in construing a statute is to determine and give effect to the intent of the General Assembly as expressed in the language it enacted. Griffith v. Aultman Hosp. ,
{¶ 33} R.C. 4906.06(A) provides that an applicant seeking a certificate of environmental compatibility and public need for construction, operation, and maintenance of a "major utility facility" from the board shall file an application "in such form as the board prescribes." This statute requires the application to contain information describing the facility, a summary of environmental-impact studies conducted, and a statement explaining the need for the facility, why the proposed location is best, and how the facility fits into the applicant's forecast report submitted under R.C. 4935.04. The applicant can include any other relevant information.
{¶ 34} R.C. 4906.06 also includes a provision governing the amendment of a certificate. R.C. 4906.06(E) states, "An application for an amendment of a certificate shall be in such form and contain such information as the board prescribes. Notice of such an application shall be given as required in divisions (B) and (C) of this section." Pursuant to this authority, the board has promulgated an administrative rule requiring the application to be submitted in the same form and reviewed in the same manner as an application for a certificate.
{¶ 35} At issue in this case is whether Black Fork could seek a two-year extension of the time for it to commence construction of the facility by filing a motion or whether it was required to apply for an amendment of the certificate in order to extend it.
{¶ 37} Therefore, the obligation to "commence[ ] a continuous course of construction" within five years from the date the certificate was journalized is an express condition of the certificate, and because the motion for a two-year extension of the time for commencement of construction of the facility sought to amend that certificate, Black Fork was required to file an application for amendment in accord with R.C. 4906.06. Only after Black Fork first filed an application to amend the certificate in compliance with R.C. 4906.06 would R.C. 4906.07(B) then be applicable, but the latter statute governs only the board's consideration of whether it is required to hold a hearing similar to a hearing on an application for a certificate. The board therefore erred when it amended the certificate by granting Black Fork's motion without complying with the proper procedure.
{¶ 38} The dissenting opinion, however, focuses on R.C. 4906.07(B) as establishing a limitation on what types of modifications to a certificate amount to an "amendment" that must be requested through the filing of an application. That statute establishes guidelines for conducting a hearing and investigating applications for a certificate and for an amendment to a certificate:
(A) Upon the receipt of an application complying with section 4906.06 of the Revised Code, the power siting board shall promptly fix a date for a public hearing thereon, not less than sixty nor more than ninety days after such receipt, and shall conclude the proceeding as expeditiously as practicable.
(B) On an application for an amendment of a certificate, the board shall hold a hearing in the same manner as a hearing is held on an application for a certificate if the proposed change in the facility would result in any material increase in any environmental impact of the facility or a substantial change in the location of all or a portion of such facility other than as provided in the alternates set forth in the application.
(C) The chairperson of the power siting board shall cause each application filed with the board to be investigated and shall, not less than fifteen days prior to the date any application is set for hearing submit a writtenreport to the board and to the applicant. A copy of such report shall be made available to any person upon request. Such report shall set forth the nature of the investigation, and shall contain recommended findings with regard to division (A) of section 4906.10 of the Revised Code and shall become part of the record and served upon all parties to the proceeding.
R.C. 4906.07.
{¶ 39} The dissent reasons that because R.C. 4906.07(B) requires a hearing only when "the proposed change in the facility" would materially increase the facility's environmental impact or substantially change its location, the General Assembly must have intended that a certificate holder must file an application for amendment of a certificate only when the certificate holder proposes changes to the facility.
{¶ 40} The problem with that analysis, however, is that the legislature did not hide substantive limitations on the amendment of a certificate in a provision that specifically addresses when "the board shall hold a hearing," R.C. 4906.07(B), and nothing more. Rather, a legislature "is generally presumed to act intentionally and purposely when it includes particular language in one section of a statute but omits it in another." NACCO Industries, Inc. v. Tracy ,
{¶ 41} Applying these cardinal principles of statutory construction reveals that R.C. 4906.07(B) simply distinguishes a category of applications to amend a certificate-those proposing a change in the facility-in which a hearing similar to the one required to be held upon an initial application may not be required. It does not demonstrate the legislative intent to limit the types of changes that constitute an "amendment" generally. Otherwise, the General Assembly would have also defined "amendment" to mean "a proposed change in the facility" or included similar language in R.C. 4906.06(E) to require a certificate holder to file an application for an amendment only when the certificate holder proposes changes to the facility. It did not, but rather it provided more general language regarding "[a]n application for an amendment of a certificate." To accept the dissent's view would therefore require adding language to R.C. 4906.06(E) to specify "[a]n application for an amendment of a certificate proposing a change in the facility ." But we may not, in the guise of statutory construction, add limiting language to a statute when the General Assembly did not enact that limitation, Doe ,
{¶ 43} But here, the issue before us is neither highly specialized nor one related to the board's enforcement responsibility but rather requires us to engage in a familiar function-statutory construction-in which we apply fundamental principles. And because the interpretation of a statute is a question of law, we review the board's interpretation de novo and without deference. Stewart v. Vivian ,
{¶ 44} Moreover, the dissenting opinion would rely on the board's "established administrative practice of considering certificate extensions based on motions rather than on amendment applications," noting that " 'long-standing administrative interpretations are entitled to special weight,' " dissenting opinion at ¶ 59, quoting Cleveland v. Pub. Util. Comm. ,
{¶ 45} In any case, an agency cannot change the meaning of a statute or a rule simply by misapplying it repeatedly; because an agency has no authority beyond that which is conferred by statute, it cannot-through an errant course of practice-grant itself power withheld by the General Assembly. See State ex rel. Lucas Cty. Bd. of Commrs. v. Ohio Environmental Protection Agency,
In construing such grant of power, particularly administrative power through and by a legislative body, the rules are well settled that the intention of the grant of power, as well as the extent of the grant, must be clear; that in case of doubt that doubt is to be resolved, not in favor of the grant, but against it. It is one of the reserved powers that the legislativebody no doubt had, but failed to delegate to the administrative board or body in question.
State ex rel. A. Bentley & Sons Co. v. Pierce,
{¶ 46} Here, no statute gives the board authority to modify the certificate by granting Black Fork's motion. Rather, the only method specified by the relevant statute, R.C. 4906.06(E), for modifying a certificate is for the certificate holder to file an application for an amendment. If the dissent is correct that an "amendment" is at issue only when there is a proposed change in the facility, then there is no authority in R.C. Chapter 4906 for the board to modify any other conditions of the certificate. That view, however, cannot be squared with the broad language of R.C. 4906.06(E).
{¶ 47} Contrary to the dissent's reasoning, it does not make sense to require the same public notice, investigation, and review as that applicable to an initial application when a certificate holder proposes some change to the facility-regardless of how material the change is-but then to permit modification of all of the other substantive conditions of a certificate by granting a certificate holder's motion without complying with any of the procedural safeguards mandated
{¶ 48} By deferring to the board's interpretation of law and past practice, the dissent disregards the judicial and legislative checks on the executive branch that are essential to our tripartite form of state government. A majority of this court therefore correctly rejects the dissent's reasoning.
DeWine, J., concurs in the foregoing opinion.
Dissenting Opinion
{¶ 49} I respectfully dissent. The Power Siting Board interprets R.C. 4906.07(B) both workably and reasonably. The majority opinion, by contrast, creates an unworkable rule that will result in a significant increase in the situations in which a certificate holder must file an application for an amendment of a siting certificate that was previously granted by the board. Further, the majority opinion relies on a plain-meaning definition of the term "amendment," but it reads the term in isolation. The majority opinion does this despite the fact that its plain-meaning interpretation is unsupportable when the term "amendment" is read in the context of the complete statutory scheme.
{¶ 50} As a starting point, the majority opinion notes that the General Assembly has not defined "amendment" in R.C. Chapter 4906. This is true, but only to the limited extent that R.C. 4906.01, which provides explicit definitions of several terms used in the statutory scheme, does
{¶ 51} Relying on R.C. 4906.07(B), the board in its brief argues that only "a proposed change to the facility " constitutes an amendment. (Emphasis sic.) And because an extension of a certificate's duration does not involve any change to the facility , the board argues that it properly approved the extension of the certificate previously granted to Black Fork Wind Energy, L.L.C., even though Black Fork did not file an application for an amendment of the certificate. The board
{¶ 52} R.C. 4906.07(B) provides:
On an application for an amendment of a certificate, the board shall hold a hearing in the same manner as a hearing is held on an application for a certificate if the proposed change in the facility would result in any material increase in any environmental impact of the facility or a substantial change in the location of all or a portion of such facility other than as provided in the alternates set forth in the application.
(Emphasis added.) The board argues that the italicized portion of the statute demonstrates that the legislature presupposed that an "amendment" of a certificate is at issue only when changes in the facility are proposed. Therefore, argues the board, R.C. 4906.07(B) is good evidence that the General Assembly intended that only proposed changes to a facility require an "amendment" of the certificate.
{¶ 53} Reading the statute in context, particularly the phrase "the proposed change in the facility," R.C. 4906.07(B) provides that the board can approve some proposed changes to a certificate only if the certificate holder has filed an application for an amendment of the certificate. R.C. 4906.07(B), by implication, authorizes the board to consider and approve other changes to a certificate even if the certificate holder submits the request for a change in some other form, e.g., by motion. The remainder of the language in R.C. 4906.07(B) explains which types of applications for amendments necessitate that the board hold a hearing prior to rendering its decision.
{¶ 54} The phrase "the proposed change in the facility" (emphasis added), as used in R.C. 4906.07(B), makes sense only if there is a proposed change in the facility. If the legislature intended that a certificate holder needs to file an application for an amendment when the proposed change is not to "the facility," the statute would be worded to specify "any proposed change in the facility" or "the proposed change in the certificate ." Under R.C. 4906.07(B), an "amendment" of a certificate is necessary only when the change proposed is a change to the facility.
{¶ 55} The concurring opinion speculates that "the legislature did not hide substantive limitations on the amendment of a certificate in a provision that specifically addresses when 'the board shall hold a hearing.' " Concurring opinion at ¶ 40, quoting R.C. 4906.07(B). The limitation, however, is in the text of the statutory scheme. The court's role is to interpret the statutory scheme, not to
{¶ 56} Here, the board determined that an amendment of a certificate is at issue only when the proposed alteration to the certificate relates to a proposed change to the facility. The board's interpretation is consistent with the statutory scheme, and, as noted above, statutes relating to the same subject matter should be construed by considering them together. South ,
{¶ 57} Moreover, the board's interpretation of the statute is workable whereas the majority opinion's interpretation is problematic. Surely, not every proposed minor revision or modification, change made by addition or deletion, correction of a mistake or mistakes, insignificant reformation, nonsubstantive adjustment, or other change or alteration in any way, especially in phraseology, to the original certificate necessitates that the certificate holder file an application for an amendment or that the board treat a motion to change a certificate as if it were an application to amend it. Having to conduct an investigation before approving an "amendment" every time a certificate holder requests a minor change to a certificate would create a substantial burden for the board in certain cases and, for that reason, would be unworkable in those cases. More importantly, such a reading of R.C. 4906.07(B) takes the phrase "the change in the facility" out of the context provided by the statute. Indeed, a plurality opinion of this court aptly described the power-siting statutes as authorizing "a dynamic process that does not end with the issuance of a construction certificate." In re Application of Buckeye Wind, L.L.C. ,
{¶ 58} The concurring opinion states that "an application for an amendment is required to be filed only when the proposed change to the certificate amounts to an 'amendment' of it." Concurring opinion at ¶ 47. I respectfully disagree on this point because, as stated above, R.C. 4906.07(B) provides that an application for an amendment is required only when the change proposed is "a change in the facility " (emphasis added) not a change in the certificate .
{¶ 59} Further, the board has an established administrative practice of considering certificate extensions based on motions rather than on amendment applications. The board states in its brief that it has considered such motions in seven other siting cases starting with an order it issued in 1996. "This court has long recognized that long-standing administrative interpretations are entitled to special weight." Cleveland v. Pub. Util. Comm. ,
{¶ 61} In conclusion, after reasonably interpreting R.C. 4906.07(B), the board determined that an amendment of a certificate is required only when the change
{¶ 62} Here, the certificate extension does not involve a change "in the facility" and the board has acted in accordance with its longstanding administrative practice, which does not conflict with the statute. Hence, the board properly granted Black Fork's motion to extend the time to commence construction.
{¶ 63} I would affirm the board's decision and, therefore, I respectfully dissent.
O'Donnell, J., concurs in the foregoing opinion.
