Anton's Services v. Hagen CA4/1Anton's Services v. Hagen CA4/1
Silver Law Firm and Zvi Silver for Appellant.
No appearance for Respondents.
Lance A. Grucela for Real Party in Interest and Respondent.
Plaintiff and appellant Anton‘s Services Inc. allegedly violated state labor statutes and regulations applicable to public works by misclassifying and underpaying workers and failing to comply with apprenticeship requirements. Real party in interest and respondent Division of Labor Standards Enforcement (DLSE) cited Anton‘s for those violations and assessed penalties. Anton‘s administrative appeal was unsuccessful, and it thereafter filed a petition for writ of administrative mandamus under
On appeal, Anton‘s contends the superior court erroneously upheld administrative findings that: (1) Anton‘s misclassified workers on two public works projects; (2) Anton‘s is liable for penalties for failing to pay these workers the prevailing wage; (3) Anton‘s is liable for liquidated damages; (4) Anton‘s failed to comply with apprenticeship requirements; and (5) Anton‘s is liable for penalties for failing to comply with apprenticeship requirements. Finding no error, we affirm.
BACKGROUND
A. Prevailing Wage Law
Under the Prevailing Wage Law,
The DLSE is charged with enforcing these prevailing wage and apprenticeship requirements. (
B. Factual Background
1. The Torrey Pines Road Project
In 2017, the City of San Diego (City) awarded Hazard Construction Company (Hazard) a contract for road improvement and slope restoration along Torrey Pines Road (the Torrey Pines Road Project). The contract specified that California prevailing wage rates applied to the project. The scope of work under the contract included: excavation of the slope to achieve the required space for a sidewalk; removal of sloughing soil and debris from the slope face; installation of permanent soil-nails wall; installation of new sidewalk, retaining curb, and walls; installation of a pedestrian crossing with street lighting and crosswalk systems; asphalt concrete overlay with striping of buffered bike lanes; and installation of a flush stamped and painted asphalt median.
Hazard contracted with Anton‘s as a “Clearing/Demolition Constructor” on the Torrey Pines Road Project. According to inspection reports, Anton‘s work included “clearing and grubbing” the slope. Generally, “[c]learing and grubbing consists of methodically ‘scarifying’ or tilling the soil on a construction
As the work continued, concerns arose that a Torrey pine tree might fall if the slope became unstable. After consulting with the City, Anton‘s stabilized the tree with cables and belts and trimmed it back before proceeding with additional clearing and grubbing.
Following an investigation, the DLSE issued a civil wage and penalty assessment, concluding that Anton‘s had failed to properly classify workers, failed to pay prevailing wages, and had committed apprenticeship violations.
From the start of its work at the Torrey Pines Road Project, Anton‘s paid workers the rates for “Tree Maintenance.” The scope of work for the “Tree Maintenance (Laborer)” classification includes:
“2. tree maintenance, including trimming, pruning, topping, tree/stump removal, grinding of stumps, root pruning and root barrier installation; handling, piling, hauling and chipping of brush and limbs; removal and replacement of trees; The operation of all vehicles, tools and equipment including but not limited to hand tools of any type, chainsaws, pole saws, pruners, stump grinders for trees, boom trucks, loaders and trucks for personnel, material and equipment, debris removal and towing.
“3. This [classification] does not cover (a) any work of any employee performing construction or landscape construction work (including work incidental to construction or post-construction maintenance during the plant installation and establishment period) and (b) tree trimmer utility line clearance work within the scope of work in any pre-existing prevailing wage determinations for Tree Trimmer (High Voltage Line Clearance) and Tree Trimmer (Line Clearance), issued by the Director of Industrial Relations.”
The DLSE determined Anton‘s should have paid its workers the prevailing wage under the “Laborer (Engineering Construction)” classification, a broad category that includes:
“(2) Street and highway work, grading and paving, excavation of earth and rock, including non-destructive utility line location (hydrovac operations),
grade separations, elevated highways, viaducts, bridges, abutments, retaining walls, subways, airport grading, surfacing and drainage, electric transmission line and conduit projects, underground communication and conduit installation, fiberoptic installation, blowing, splicing, testing and related work for telephone, T.V. or other communication transmission through underground conduit, water supply, water, development, reclamation, irrigation, draining and flood control projects, water mains, pipe lines, sanitation and sewer projects, dams, aqueducts, canals, reservoirs, intakes, channels, levees, dikes, revetments, quarrying of breakwater or riprap stone, foundations, pile driving, piers, locks, river and harbor projects, breakwaters, jetties, dredging, tunnels. [¶] . . . [¶] “(11) All work in connection with excavation for incidental building and other construction including digging of trenches, piers, foundations and holes; digging, lagging, sheeting, cribbing and bracing of foundations, holes, caissons, cofferdams, manning, setting and moving all manually movable pumps. [¶] . . . [¶]
“(14) All work in the excavation, grading, preparation, concreting, asphalt and mastic paving, paving, ramming, curbing, flagging, traffic control by any method, and laying of other stone materials, . . . and bridges. [¶] . . . [¶]
“(16) All work in connection with the cutting of streets and ways for all purposes, including aligning by any method, digging of trenches, manholes, etc., handling and conveying of all materials for same; concrete of same; and the backfilling, grading and resurfacing of same.”
Based on the misclassification of workers, the DLSE determined that Anton‘s owed additional wages and apprenticeship training fees.
The DLSE also found that Anton‘s failed to submit contract award information to applicable apprenticeship committees before starting work, failed to request dispatch of apprentices from the applicable apprenticeship committees, and did not employ apprentices in the required ratio. The Civil Wage and Penalty Assessment for the Torrey Pines Road Project, which totaled $36,626.30, included $22,526.30 in unpaid prevailing wages, $12,720 in penalties under
2. The Voltaire Street Project
Also in 2017, the City awarded Hazard a public works contract to renovate an overpass on Voltaire Street in San Diego County (the Voltaire Street
Following an investigation, the DLSE issued a Civil Wage and Penalty Assessment for the Voltaire Street Project. As on the Torrey Pines Road Project, DLSE found Anton‘s had classified workers under “Tree Maintenance” instead of “Laborer,” thus underpaying workers and failing to pay appropriate apprenticeship fees. This Civil Wage and Penalty Assessment totaled $10,653.88, including $1,653.88 in unpaid prevailing wages and $9,000 in penalties under
C. Administrative Proceedings
Anton‘s challenged both Civil Wage and Penalty Assessments under
The Director first found that Anton‘s had misclassified workers on both projects. The Director found “the nature of work” for each project was “construction work,” and noted that “the applicable scope of work for the Tree Maintenance classification . . . specifically excluded coverage of construction or landscape construction work, including work incidental to construction.”
The Director rejected Anton‘s argument that the tree work on the Torrey Pines Road Project was not incidental to construction “because it was the subject of a [change order] that expanded the contract to include additional work on the tree.” Rather, the Director found “the additional work on the Torrey [p]ine tree was part of the construction project, because the tree had to be trimmed before clearing work could continue on the soil nail wall.”
Although Anton‘s argued “that it ‘received no compensation for [its] work [on the Voltaire Street Project] because the City determined this was outside the original contract scope of work,‘” the Director noted Anton‘s had not cited any “evidence to support this claim.” Similarly, although Anton‘s argued it could have properly classified its workers as “Tree Trimmer (High Voltage
Next, the Director addressed the $120 per-day penalties imposed under
The Director also found Anton‘s liable for liquidated damages under
The Director upheld the DLSE‘s finding that Anton‘s failed to comply with the apprenticeship requirements of
D. Mandate Proceedings
Anton‘s filed a petition for writ of mandate under
DISCUSSION
A. Standard and Scope of Review
Several of Anton‘s arguments rely on documents outside the administrative record. Evidence outside the administrative record is generally not admissible in proceedings filed under
Anton‘s does not challenge the trial court‘s exclusion of this evidence and does not explain why this court should consider evidence not contained in the administrative record. Anton‘s has forfeited such arguments. (See, e.g., Asaro v. Maniscalco (2024) 103 Cal.App.5th 717, 728, fn. 4 (Asaro) [a party forfeits arguments not briefed on appeal].) We thus limit our review to the administrative record and will not consider arguments that rely on extra-record evidence.
B. Misclassification
1. Torrey Pines Road Project Classification
Anton‘s principally argues it properly classified workers on the Torrey Pines Road Project because they performed work on a Torrey pine tree. However, Anton‘s does not dispute that the Torrey Pines Road Project was a construction project. Anton‘s was designated as a “Clearing/Demolition Constructor.” (Italics added.) Anton‘s actual work performed principally consisted of “clearing and grubbing,” which is the removal of vegetation. As Anton‘s concedes, this work was necessary preparatory work for the slope stabilization, and thus incidental to construction work. Anton‘s work stabilizing and trimming the Torrey pine tree was also incidental to the broader construction project, as the tree only needed to be stabilized so the slope work could proceed. The Tree Maintenance classification expressly “does not cover . . . any work of any employee performing construction or landscape construction work (including work incidental to construction or post-construction maintenance during the plant installation and establishment period).”
Anton‘s argues, in several different ways, that its work on the Torrey pine tree should be considered separate from, and not incidental to the broader Torrey Pines Road Project. Anton‘s cites no authority in support of its various arguments. Nor do we find them persuasive.
Anton‘s argues: (1) it holds an arborist license, was acting as an arborist when working on the tree, and invoiced the services as “Arborist Services“; (2) other work stopped while waiting for the tree to be stabilized; and (3) the
Anton‘s also claims the tree work was not part of the original scope of work for the project. But the additional tree work only became necessary to further the broader construction project, so remains incidental to that work. Relatedly, Anton‘s argues that because the work was performed pursuant to a change order, it could have simply passed along costs to the City and made additional profit, as it was entitled to five percent profit on the amount of the change order. Whether or not this is true does not affect our analysis. Regardless of motives, substantial evidence supports the finding that Anton‘s failed to properly classify its workers and thus underpaid them.
Separate from the Torrey pine work, Anton‘s argues that its clearing and grubbing involved removal of a “small palm tree” that should qualify as Tree Maintenance work. This assertion and much of Anton‘s related
arguments rely on evidence outside of the record, which we will not consider.4
2. Voltaire Street Project Classification
Anton‘s also fails to demonstrate that the Director erred by finding Anton‘s misclassified workers on the Voltaire Street Project. The Voltaire Street Project involved renovating an overpass, and Anton‘s was contracted to “[r]emov[e] [a] bridge sidewalk, railing, and edge concrete.” Anton‘s fails to cite any evidence in the administrative record supporting its claim that its work on this project involved any tree maintenance or removal at all. Anton‘s provides no basis to assess the nature of the alleged tree-related work and thus no grounds to conclude that the Director erred.
Anton‘s makes regarding the Voltaire Street Project in the “Summary of the Significant Facts” section of its opening brief are not supported by any record citations in violation of California Rules of Court, rule 8.204, subdivision (a)(1)(C). (Ibid. [an appellate brief must “[s]upport any reference to a matter in the record by a citation to the volume and page number of the record where the matter appears“].) “We are not required to search the record to ascertain whether it contains support for [Anton‘s] contentions.” (Mansell v. Board of Administration (1994) 30 Cal.App.4th 539, 545.) With one immaterial exception,6 the limited evidence Anton‘s cites in this portion of the brief is outside of the administrative record, and (as discussed above) not cognizable in these proceedings. In light of these deficiencies, we decline to further address the merits of Anton‘s arguments regarding the Voltaire Street Project misclassification.
C. Penalties under Section 1775
Under
“(A) The amount of the penalty shall be determined by the Labor Commissioner based on consideration of both of the following:
“(i) Whether the failure of the contractor or subcontractor to pay the correct rate of per diem wages was a good faith mistake and, if so, the error was promptly and voluntarily corrected when brought to the attention of the contractor or subcontractor.
“(ii) Whether the contractor or subcontractor has a prior record of failing to meet its prevailing wage obligations.” (
§ 1775, subd. (a)(2)(A) .)
“[I]n reviewing the penalty imposed by an administrative body, . . . an appellate court is [not] free to substitute its own discretion as to the matter.” (Nightingale v. State Personnel Board (1972) 7 Cal.3d 507, 515.)
Anton‘s also argues its good faith is evidenced by the fact that its classification of workers was against its own interests, suggesting that it would not have intentionally underpaid workers because it could have passed along higher costs to the City and increased its own profit margin. Anton‘s adds that it properly classified and paid workers on portions of each project. Anton‘s ignores the countervailing evidence that bears directly on the statutorily mandated considerations: Anton‘s failure to “promptly and voluntarily correct[]” its underpayment in connection with these projects and a prior record of prevailing wage violations and penalties under
D. Liquidated Damages on the Torrey Pines Road Project
Anton‘s argues the Director improperly imposed liquidated damages under
“(a) After 60 days following the service of a civil wage and penalty assessment under Section 1741 or a notice of withholding under subdivision (a) of Section 1771.6, the affected contractor, subcontractor, and surety on a bond or bonds issued to secure the payment of wages covered by the assessment or notice shall be liable for liquidated damages in an amount equal to the wages, or portion thereof, that still remain unpaid. If the assessment or notice subsequently is overturned or modified after administrative or judicial review, liquidated damages shall be payable only on the wages found to be due and unpaid. Any liquidated damages shall be distributed to the employee along with the unpaid wages. . . .
“(b) Notwithstanding subdivision (a), there shall be no liability for liquidated damages if the full amount of the assessment or notice, including penalties, has been deposited with the Department of Industrial Relations, within 60 days following service of the assessment or notice, for the department to hold in escrow pending administrative and judicial review. . . .”
It claims that, because Hazard withheld $36,626.30 from Anton‘s and transmitted those funds to the City under
Statutory interpretation is “a question of law that we review de novo.” (Bruns v. E-Commerce Exchange, Inc. (2011) 51 Cal.4th 717, 724.) “Our fundamental task in interpreting a statute is to determine the Legislature‘s intent so as to effectuate the law‘s purpose. We first examine the statutory language, giving it a plain and commonsense meaning. We do not examine that language in isolation, but in the context of the statutory framework as a whole in order to determine its scope and purpose and to harmonize the various parts of the enactment.” (Coalition of Concerned Communities, Inc. v. City of Los Angeles (2004) 34 Cal.4th 733, 737.) “If the language is clear, [we] must generally follow its plain meaning unless a literal interpretation would result in absurd consequences the Legislature did not intend.” (Ibid.)7
Under a plain and commonsense meaning, withholding money due under a contract is not the payment of “wages.” While Anton‘s correctly notes that
This provision is not satisfied by the contractor withholding funds from the responsible subcontractor under
review. Thus, they remain “unpaid.” Nothing in the language of
Anton‘s nonetheless claims its position is supported by the clause specifying: “If the assessment or notice subsequently is overturned or modified after administrative or judicial review, liquidated damages shall be payable only on the wages found to be due and unpaid.” (
We appreciate that automatically withholding money from a subcontractor under
But these are policy concerns for the Legislature to weigh, not this court when faced with the application of clear statutory language. (See, e.g., Standon Co. v. Superior Court (1990) 225 Cal.App.3d 898, 904 [“Unless the plain language of a statute leads to absurdity, a court may not so construe it as to substitute its wisdom for that of the legislature.“].) We are not at liberty to rewrite the plain language of
Anton‘s also suggests that, because
However, the Legislature chose only to insulate a party from liability for liquidated damages if it deposits money directly with the Department, and it
Anton‘s argues the DLSE should be “equitably estopped” from pursuing liquidated damages because it directed Hazard to transfer the withheld money to the City. Under
Anton‘s also briefly raises a constitutional argument, but fails to explain its theory or provide supportive authority. “We are not bound to develop appellants’ arguments for them. [Citation.] The absence of cogent legal argument or citation to authority allows this court to treat the contentions as [forfeited].” (In re Marriage of Falcone & Fyke (2008) 164 Cal.App.4th 814, 830 (Falcone).)
Anton‘s remaining arguments iterate on these contentions and fail to change our view of the relevant statutes. Again, while there appears to be some redundancy built into the statutory scheme, we do not see any absurd
results that would warrant a departure from the plain language of
E. Apprenticeship Violations on the Torrey Pines Road Project
Anton‘s was held liable for three apprenticeship-related violations: (1) failure to give timely notice of the Torrey Pines Road Project; (2) failure to
Second, Anton‘s fails to show it employed an adequate number of apprentices on the Torrey Pines Road Project. (See
Third, Anton‘s does not dispute that it failed to request the dispatch of apprentices from appropriate committees. (
Next, Anton‘s challenges the DLSE‘s imposition of penalties under
Anton‘s fails to argue that its violations of
Moreover, Anton‘s does not address the Director‘s finding that there was an “irrebuttable presumption that Anton‘s knew or should have known of the
Finally, Anton‘s claims it should not be liable for underpaying workers due to excessive payment to apprenticeship funds. Anton‘s fails to provide any record citations for its factual assertions or any authority for its arguments, which are thus forfeited. (See Falcone, supra, 164 Cal.App.4th at p. 830.)
DISPOSITION
The judgment is affirmed. Respondents are entitled to costs on appeal.
BUCHANAN, J.
WE CONCUR:
McCONNELL, P. J.
O‘ROURKE, J.