Am. Environmental Group, Ltd. v. H.M. Miller Constr. Co.Am. Environmental Group, Ltd. v. H.M. Miller Constr. Co.
JOURNAL ENTRY AND OPINION
JUDGMENT: REVERSED AND REMANDED
Aaron S. Evenchik
Rick L. Amburgey
Andrew J. Natale
Frantz Ward L.L.P.
2500 Key Center
127 Public Square
Cleveland, Ohio 44114
ATTORNEYS FOR APPELLEE
Mark F. Craig
Michael P. O‘Donnell
David Sporar
Brouse McDowell, L.P.A.
600 Superior Avenue, East
Suite 1600
Cleveland, Ohio 44114
{¶1} Defendants-appellants, H.M. Miller Construction Co. (“H.M.M.“) and Ohio Farmers Insurance Company (“OFIC“), collectively (“appellants“), appeal the denial of their motion to quash subpoenas and for protective оrder. We find merit to the appeal, reverse the trial court‘s judgment and remand the case to the trial court for an in camera inspection of the subpoenaed documents.
{¶2} This case arises from a construction project in the city of Fremont, Ohio (“Fremont” or “the city“). The city planned to build a raw water reservoir and hired H.M.M. as the general contractor for the project. Fremont also retained Arcadis, U.S. Inc. (“Arcadis“), as the project engineer. OFIC was the surety for the payment bond on the project.
{¶3} During construction, problems were discovered in the rock floor of the reservoir that necessitated a change from a clay-lined reservoir to a geosynthetic-lined reservoir. In May 2011, H.M.M. subcontracted with plaintiff-appellee, American Environmental Group Ltd. (“AEG“), to install the geosynthetic liner. Payment and contract disputes subsequently arose between Fremont and H.M.M., and H.M.M. failed to pay AEG for the work it performed on the project. Ultimately, AEG filed a lien against public funds, asserted a claim against the payment bond, and filed suit against H.M.M., OFIC, and Fremont in the Sandusky County Court of Common Pleas. The parties recognized that H.M.M.‘s failure to pay AEG was caused, in part, by the city‘s refusal to
{¶4} In June 2012, H.M.M. and Fremont participated in mediation to review the claims and discuss completion of the project. The parties reached an agreement in which Fremont agreed to pay a portion of H.M.M.‘s and AEG‘s claims, and H.M.M. agreed to complete the project as outlined in a “Memоrandum of Understanding” between Fremont and H.M.M.
{¶5} H.M.M. subsequently met with AEG to review the Memorandum of Understanding and to obtain AEG‘s agreement to complete the reservoir project. Following negotations, H.M.M., AEG, and OFIC entered into a “Liquidating and Joint Prosecution Agreement” (“Joint Prosecution Agreement“), in which they agreed to resolve thе payment dispute between them and to collectively prosecute their claims against Fremont. The Joint Prosecution Agreement provided, in relevant part:
CONTRACTOR [H.M.M.] and SUBCONTRACTOR [AEG] agree to jointly prosecute their respective claims relating to the project against the Project Owner through Contractor‘s existing lawsuit in the Common Pleas Court of Sandusky County, (Case No. 12 CV 758) (“Lawsuit“) which claims will include those of SUBCONTRACTOR. Although SUBCONTRACTOR need not be a party to that Lawsuit to mitigate SUBCONTRACTOR‘s legal expense. CONTRACTOR consents to sponsor SUBCONTRACTOR‘s claims in the Lawsuit and all related alternative dispute resolution procedures, with SUBCONTRACTOR‘s reasonable cooperation, in аccordance with the Contract and applicable law, subject to CONTRACTOR‘s sole right to direct and manage litigation.
{¶6} The litigation between H.M.M. and Fremont remained unresolved, and H.M.M. and Freemont participated in a second mediation in October 2012. The parties
{¶7} In an effort to settle all the litigation, Fremont, Arcadis, H.M.M., and another construction company participated in a third mediation in January 2013 (“the Global Mediation“). H.M.M. invited AEG to attend the mediation, but AEG declined. H.M.M. and Fremont resolved their dispute at the mediation, and Fremont paid H.M.M. a lump sum of $6.75 million to settle all claims. Although AEG claimed it was entitled to almost $1 million, H.M.M. only paid AEG $144,622. As a result, AEG filed a complaint against appellants in the Cuyahoga County Common Pleas Court, asserting claims for (1) breach of contract, (2) a declaratory judgment declaring that H.M.M.‘s payment under the Joint Prosecution Agreement was not properly calculated under the terms of that agreement, and (3) a claim against the payment bond for the reservoir project. Appellants answered the complaint and asserted two counterclaims for declaratory judgment declaring (1) that H.M.M. properly paid AEG in full under the Joint Prosecution Agreement, and (2) that OFIC is not obligated to pay any additional amounts to AEG under the payment bond.
{¶8} In September and October 2013, AEG issued subpoenas duces tecum to Fremont and Arcadis, neither of whom are parties to this case. AEG served appellants with notice of the subpoenas. In November 2013, appellants filed a motion to quash the
{¶9} In an order denying the motion to quash, the trial court stated:
Insofar as the motion is for a protective order, the issue is not yet justiciable because I cannot assess whether the claimed privilege applies to any of the documents without knowing what the documents are.
* * *
Therefore, once the plaintiff gets the documents it must produce a complete copy of them to the defendants. Once the defendants review the documents, they are welcome to file another motion for protective order to prevent plaintiff from using privileged mediatiоn communications in discovery or at trial and to “claw back” any such communications. The motion should include a request for an in camera inspection of the documents at issue.
In the meantime, until the privilege is decided, the plaintiff‘s counsel is prohibited from sharing with the plaintiff, consulting experts, and other witnessеs, any documents received in response to the subpoenas.
Appellants now appeal from this judgment.
Final Appealable Order
{¶10} As a threshold matter, we must determine whether the appeal is properly before us. Pursuant to
{¶12}
- The order in effect determines the action with respect to the provisional remedy and prevents a judgment in thе action in favor of the appealing party with respect to the provisional remedy.
- The appealing party would not be afforded a meaningful or effective remedy by an appeal following final judgment as to all proceedings, issues, claims, and parties in the action.
{¶13} This court has held that аn order for the production of privileged information is a provisional remedy. Johnson v. Univ. Hosps. of Cleveland, 8th Dist. Cuyahoga No. 80117, 2002 Ohio App. LEXIS 1428, * 17 (Mar. 28, 2002). In this case, AEG sought production of documents generated during the mediation of two separate lawsuits. Subject to certain limitations, communications exchanged in mediation are confidential аnd are neither discoverable nor admissible.
{¶14} Next, we must determine whеther the disclosure of the documents would conclusively determine the action with regard to those materials.
{¶15} Finally, we must determine whether appellants would have a meaningful remedy by way of appeal following final judgment on all issues, claims, and parties.
{¶16} Accordingly, we find the trial court‘s judgment is a final, appealable order.
Standard of Review
Mediation Privilege
{¶18} In their sole assignment of error, appellants argue the trial court erred in denying their motion to quash and for protective order. They contend the trial court should have granted the motion because the requested documents are privileged.
{¶19} The party seeking to exclude documents bears the burden of demonstrating that the documents are confidential or privileged. Eberhard Architects L.L.C., v. Schottenstein, Zox & Dunn Co., 8th Dist. Cuyahoga No. 99867, 2013-Ohio-5319, ¶ 14, citing Covington v. MetroHealth Sys., 150 Ohio App.3d 558, 2002-Ohio-6629, 782 N.E.2d 624, ¶ 24 (10th Dist.). Merely claiming the information is privileged is insufficient to sustain this burden. Id., citing Ro-Mai Industries v. Manning Props., 11th Dist. Portage No. 2009-P-0006, 2010-Ohio-2290, ¶ 28.
{¶20} In this case, appellants asserted that AEG‘s subpoenas duсes tecum sought documents from Arcadis and Freemont that were privileged under Ohio‘s Uniform
{¶21} For practitioners in the area of mediation, the expectation of confidentiality and the privilege afforded mediation communication is critical to the success of mediation. Disregarding the privilege contained under Ohio‘s Uniform Mediation Act not only contravenes well-established law, but it also threatens the vitality of mediation. Therefore, where there is evidence of privileged mediation communications, a trial court should not order the release of such privileged сommunications, even if disclosure is limited to the opposing party‘s counsel.
{¶22} The record contains evidence that AEG‘s subpoenas duces tecum seek documents from Arcadis and Fremont that were privileged under Ohio‘s Uniform Mediation Act. In fact, AEG even acknowledged in its response in opposition to H.M.M. аnd OFIC‘s motion to quash and motion for a protective order that it was seeking “certain information about the mediation.” Although AEG did not attend the mediation,
{¶23} Further, it is apparent from the trial court‘s order that the trial court also recognized that a privilege exists in at least some of the requested documents. Notably, the trial court did not outright deny H.M.M.‘s motion to quash and motion for a protective order. Instead, the trial court limited the release of the documents to AEG‘s counsel only. The trial court believed that any harm in releasing privileged documents to AEG‘s counsel could be remedied later through the filing of another motion for a protective order and a “claw back” of the privileged documents. This solution violates Ohio‘s Uniform Mediation Act.
{¶24} Some of the documents AEG seeks by subpoena may not be subject to the mediation privilege. In order to separate privilegеd from unprivileged material, the trial court should have conducted an in camera inspection of the records to make that determination, prior to the release of the documents. See Csonka-Cherney v. Arcelormittal Cleveland, Inc., 8th Dist. Cuyahoga No. 100128, 2014-Ohio-836, ¶ 16 (when there is a dispute over whether certain documents are privileged, “a court should conduct an in сamera inspection of those records to make that determination“).
{¶26} The trial court‘s attempt to mitigate the damage caused by the disclosure of confidential recоrds by limiting the release of the documents only to AEG‘s counsel is insufficient to protect the privileged documents. Once privileged information is disclosed, there is no way to undo the disclosure. Therefore, we conclude that the trial court abused its discretion in ordering the release of all the requested documеnts, including those that fall within the ambit of a mediation communication.
{¶27} Our decision does not make a determination on whether the contractual relationship between AEG and H.M.M. moots the issue of privilege altogether. AEG concedes in its brief that “[t]he issue of who is a mediation party is not addressed in the trial court‘s dеcision and is not properly before this Court.”
{¶28} Accordingly, the sole assignment of error is sustained.
It is ordered that appellant recover of appellee costs herein taxed.
The court finds there were reasonable grounds for this appeal.
It is ordered that a special mandate be sent to the common pleas court to carry this judgment into execution.
A certified copy of this entry shall constitute the mandate pursuant to Rule 27 of the Rules of Appellate Procedure.
EILEEN T. GALLAGHER, JUDGE
MARY J. BOYLE, A.J., and MARY EILEEN KILBANE, J., CONCUR